Dounreay Director Sets Out Benefits Of Programme Acceleration

25th June 2006

A workforce that can safely deliver the decommissioning and demolition of Britain's fast reactor experiment at Dounreay is a workforce that will be in demand worldwide for its skills.

This is the message delivered today by Norman Harrison, director of UKAEA Dounreay, in a new publication setting out the benefits of accelerated clean-up of the site and the efforts being made to find alternative employment for staff whose jobs presently depend on this work.

UKAEA has put forward proposals to the Nuclear Decommissioning Authority to accelerate the completion of the clean-up from 2036 to 2033 and, together with its business partners AMEC and CH2MHILL, is looking to advance this further.

Teams of staff are looking at ways to bring forward key dates for completion of the major decommissioning milestones, including emptying of the shaft and silo, clean-out of the Dounreay Fast Reactor and treatment of liquid wastes left over from historical reprocessing. On current plans, employment is predicted to decline from 2012 onwards.

At the same time, a working group formed by community and business leaders is consulting on a draft strategy for economic regeneration of Caithness and north Sutherland.

The eight-page document being issued to staff at Dounreay sets out how acceleration of the work can maintain higher levels of employment in the short-term and bring significant environmental and safety benefits by getting wastes into a safe condition for long-term storage or disposal at the earliest opportunity,

It also lists 31 redundant buildings and structures due for demolition, in addition to 14 cleared last year, as the decommissioning and demolition work moves forward at pace.

In his introduction, Norman Harrison says: "Take one look around the Dounreay site today and no-one can be in any doubt that we mean what we say about accelerated decommissioning. In every corner of the site, redundant facilities are being cleaned out, old facilities pulled down and new buildings being constructed to manage the wastes.

"Dounreay is coming apart. My priority, everyone's priority, is to ensure it comes apart in a way that is safe, secure and environmentally acceptable. And in so doing, we give ourselves the best possible chance of attracting the new jobs we need to succeed decommissioning. A workforce that is recognised worldwide for its achievement in knocking down Dounreay is a workforce that will be in demand."

Dounreay - Delivering for the Nuclear Decommissioning Authority describes how there are overwhelming safety, security and environmental reasons for cleaning out and knocking down the redundant facilities as quickly as it is safe to do so. But it also shows how bringing forward work to achieve this can maintain employment levels at a higher level in the short-term.

It also unlocks funds that otherwise would be spent on maintaining redundant facilities for long periods of time, and these funds can be recycled in a number of ways. They can be used to bring forward other work, or they can be used to support initiatives to create alternative employment. Some of these funds are already being invested in new enterprises with the potential to create new and sustainable economic development.

Dounreay was Britain's centre of fast reactor research and development from 1954 until 1994. It is now being decommissioned by UKAEA, with support from AMEC and CH2MHILL, on behalf of the Nuclear Decommissioning Authority.

Approximately 2000 people are employed on the Dounreay site, working for more than 50 companies. This accounts for one in every five jobs in the local economy. Decommissioning is worth an estimated £70-80 million per annum to the local economy.

A copy of Dounreay - Delivering for the Nuclear Decommissioning Authority can be viewed on the UKAEA website at

Delivering For the Nuclear Decommissioning


 

Related Businesses

 

Related Articles

Design Contract Awarded For Dounreay Shaft And Silo WorkThumbnail for article : Design Contract Awarded For Dounreay Shaft And Silo Work
Dounreay has awarded an important waste clean-up contract to Jacobs as the site plans for the future of its deepest historic radioactive waste store.   Jacobs and its supporting partners have been awarded a 6-year contract to provide a design management team to produce a fully integrated design for the shaft and silo project.  
Radiation dose to public from Dounreay reducesThumbnail for article : Radiation dose to public from Dounreay reduces
Dounreay’s radioactive impact on the environment continues to fall, according to a report.  The annual survey report “Radioactivity in Food and the Environment” (RIFE 2012) has recently been published and it can be read here - http://www.sepa.org.uk/radioactive_substances/publications/rife_reports.aspx The report uses data obtained from samples of air, fresh water, grass, soil, and locally sourced meat, fish, milk and vegetables during 2012.  
57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay
Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.  A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.  
Dounreay Dome Paint Job ScrappedThumbnail for article : Dounreay Dome Paint Job Scrapped
Bosses at Dounreay agreed that they won't now be spending £500,000 on a repaint of the sphere.   They money saved will go instead towards actual decommissioning work.  
Clean-up Reveals 6000 Years Of Human HistoryThumbnail for article : Clean-up Reveals 6000 Years Of Human History
Getting rid of Britain's 20th century experiment with fast breeder nuclear reactors is illuminating the history of human settlement on Scotland's north coast stretching back 6000 years.   Archaeologists hired as part of the closure of the nuclear site at Dounreay have pieced together the legacy left by previous generations who occupied the site as long ago as 4000BC.  
New Report Lists Radioactive Wastes At DounreayThumbnail for article : New Report Lists Radioactive Wastes At Dounreay
The Nuclear Decommissioning Authority has published the latest edition of the UK's radioactive waste inventory.   This sets out the type and volumes of radioactive waste at sites such as Dounreay, as of April 1, 2010.  
Nuclear Shutdown Cash Boost For School Skills
Cash from the closure of the fast reactor site at Dounreay is set to breed a new generation of engineers and scientists in the Scottish Highlands.   The money from the Nuclear Decommissioning Authority will fund half the cost of a £50,000 project to increase the number of school-leavers skilled in science, technology, engineering and maths.  
New Vaults Signal Start Of Waste ClearanceThumbnail for article : New Vaults Signal Start Of Waste Clearance
The clearance of tens of thousands of tonnes of radioactive waste from the redundant nuclear site at Dounreay today moved a step closer.   Dounreay Site Restoration Ltd announced the formal award of a contract to develop a disposal site for low-level waste from the decommissioning and closure of the site.  
Ex UKAEA Boss Appointed To Crown Estates Board
THE CROWN ESTATE REAPPOINTS CHRIS BARTRAM, AND APPOINTS DIPESH SHAH OBE AND ANTHONY WHITE AS NON-EXECUTIVE BOARD MEMBERS The Crown Estate has announced yesterday, 22 December 2010, the re-appointment of Chris Bartram and the appointment of Dipesh Shah and Anthony White as Non-Executive Board Members.   Chris Bartram, who has held the appointment as Crown Estate Board Member for four years has been reappointed for a further four year term with effect from 1 January 2011.  
Dounreay Boss Welcomed Funding Announcement
Dounreay Site Restoration Ltd recently welcomed an announcement about how much public money will be available to continue nuclear clean-up in the UK.   DSRL manages the closure of the site on behalf of the Nuclear Decommissioning Authority, which today confirmed that its total expenditure, including income generated, would be maintained at current levels of around £3bn a year.