Dounreay Decomissioning Speeds Up Again

1st April 2012

Senior figures from government and industry are gathering at Dounreay today to hear the site's new clean-up team set out their vision to accelerate the demolition of Britain's second largest civil nuclear site.

Three of the world's biggest engineering and project management companies - Babcock International, CHM2HILL and URS - have come together to win the largest site closure contract ever let in the UK.

Their aim is to complete the decommissioning of the site by 2022-25 and reduce the cost to the UK taxpayer by over 1 billion.

The consortium, known as the Babcock Dounreay Partnership, officially took over Dounreay Site Restoration Ltd at the weekend. It will use the company's 950 staff and supply chain to clean up and demolish the remainder of the site.

"We will be setting new standards for decommissioning delivery, safety and environmental protection. We want to establish Dounreay as the European reference site for nuclear decommissioning and site closure," said Roger Hardy, a senior Babcock executive who becomes managing director of DSRL.

He is joined initially by a team of 10 other secondees from the three parent companies who now fill positions in the site licence company.

"We are delighted now to be officially in contract and able to implement the partnership's new vision for the Dounreay site," he added.

"Babcock, CH2MHILL and URS bring international know-how and proven technologies new to the UK to one of the world's most demanding clean-up and closure jobs. I'm excited by the opportunity to work with staff, the supply chain and regulators on their implementation.

"We will reduce the cost to the UK Government of closing down this site through proven innovation, not just by doing the same thing better. We are excited by the prospect of working with the DSRL team to complete the mission they've started and deliver a world-class clean-up safely and cost-effectively."

The redundant nuclear site consists of three nuclear reactors, fuel reprocessing plants, laboratories and various waste facilities that are a legacy of the site's 20th century role as Britain's centre of fast reactor research and development.

The first Dounreay site restoration plan published in 2000 projected a clean-up taking until 2063 to complete at a cost of 4 billion.

By 2005, when the Nuclear Decommissioning Authority was established and took over the site, this had reduced to 2036 and 2.7 billion.

Two years ago, the NDA invited companies to tender for a contract to complete the site's closure for a price not exceeding 150 million a year.

Babcock Dounreay Partnership's 2022-25 bid earned it preferred bidder status from the NDA in November 2011. Its acquisition of DSRL was completed at the weekend following a four-month transition period.

The contract is to clear away all the redundant plant, get the resultant radioactive waste into a condition that is safe for long-term storage or disposal, and the site into a condition that is safe for future generations.

The new management team today begin the process of overwriting DSRL's existing clean-up programme with their successful bid. Changes to the programme are subject to normal regulatory controls governing safety, security and environmental protection.

Key features include a new target cost incentive fee contract arrangement (involving sharing risk with the NDA), an accelerated closure date, a new project-focussed methodology and a programme of support and mentoring for the local business community as it adjusts to the site closure.

The Nuclear Decommissiong Authority today marked the completition of its competitive tendering process with a VIP event at the site. Guests included Michael Moore, Secretary of State for Scotland at the UK Government; Richard Lochhead, Cabinet Secretary for Rural Affairs and the Environment at the Scottish Government; NDA chairman Stephen Henwood and chief executive John Clarke; Kevin Thomas, chair of Babcock Dounreay Partnership; and local parliamentarians John Thurso MP and Rob Gibson MSP
.
During tours of the site, they were shown progress to date to dismantle the redundant nuclear plant and were taken inside the spherical reactor hall of the part-decommissioned experimental fast reactor.

About 80 invited guests attended a ceremony in the site's canteen to mark the contract award.
Tonight, the new management team hosts a reception for community representatives at the University of the Highlands and Islands campus in Thurso where they will outline their plans to help the area adjust to the social and economic consequences of site closure.

 

Related Businesses

 

Related Articles

Up To 200 Jobs To Go At DounreayThumbnail for article : Up To 200 Jobs To Go At Dounreay
The clean-up of the nuclear estate is a key priority for both the Scottish and United Kingdom governments.   Dounreay's decommissioning is well established with the site due to reach an interim end state by the early 2030s.  
Dounreay's High Street MakeoverThumbnail for article : Dounreay's High Street Makeover
A major upgrade and expansion of Dounreay's Thurso town centre office has been completed.   David Flear, Chair of Dounreay Stakeholder Group, officially reopened the building which sits at the entrance to the high street and has been the site's public information office for almost a decade.  
Doors Open At Unique Nuclear ArchiveThumbnail for article : Doors Open At Unique Nuclear Archive
A unique new archive, funded by the Nuclear Decommissioning Authority, has opened its doors to the public for the first time, bringing together historical nuclear records from all over the UK.   Speaking today at the Nucleus (Nuclear and Caithness Archive) in Wick, NDA chairman Stephen Henwood, said:Today we see a new chapter in the important role Caithness has played in the UK's nuclear history.  
First Cut Out Of Reactor Pond Wall At DounreayThumbnail for article : First Cut Out Of Reactor Pond Wall At Dounreay
The first block of concrete has been removed from the structure of one of Dounreay's cooling ponds - representing a major first step in demolishing the redundant giant chamber.   The pond is one of two concrete pits, six metres deep, which was used to store spent fuel from the Dounreay Fast Reactor (DFR).  
More Than 30,000 Bricks Removed From Redundant PlantThumbnail for article : More Than 30,000 Bricks Removed From Redundant Plant
More than 30,000 bricks have been removed from three pits within a redundant facility as part of a project to decommission a former effluent treatment plant.   A scaffold platform has been constructed to allow operators, wearing full airline suits, access to remove the bricks using small electrically operated hand tools.  
Waste contract signals Dounreay's community commitmentThumbnail for article : Waste contract signals Dounreay's community commitment
Amec Foster Wheeluker has been awarded a contract to design and build a new effluent treatment plant at Dounreay.   The agreement signals a landmark move for the Caithness site as the first to incorporate socio-economic commitments following the introduction of a new procurement policy earlier this year.  
Japanese Ambassador visits DounreayThumbnail for article : Japanese Ambassador visits Dounreay
His Excellency, Mr Koji Tsuruoka, Ambassador of Japan to the United Kingdom, Mr Yosuki Ishigami from the Economic Section of the Japanese Embassy and Mr Daisuke Matsunaga, Consul General of Japan in Edinburgh visited Dounreay during a two-day visit to the north of Scotland as a guest of Dr Paul Monaghan MP.   At Dounreay the group toured the Prototype Fast Reactor (PFR), including the reactor hall.  
10 New Apprentices Start At DounreayThumbnail for article : 10 New Apprentices Start At Dounreay
Dounreay has said "you're hired" to ten local newcomers who have started their careers at Dounreay this week.  This makes it the 61st consecutive year that apprentices have joined the site.  
New camera provides clear images of bowels of reactorThumbnail for article : New camera provides clear images of bowels of reactor
An off the shelf CCTV camera is providing crystal clear images from the depths of Dounreay's Prototype Fast Reactor (PFR).   Fifty years on from the construction of PFR, the reactor decommissioning team is viewing footage that will enable it to pull apart the innards of the second and last fast reactor to be built in the UK.  
Dounreay meets target for liquid hazard reductionThumbnail for article : Dounreay meets target for liquid hazard reduction
The last of the higher activity liquid waste produced during Dounreay Fast Reactor (DFR) fuel reprocessing has been made safe for future generations.  It is an important milestone in the immobilisation of the historic liquid waste, known as raffinate, created from reprocessing undertaken during the operation of Dounreay's three reactors.  