Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider  

 

Dounreay Bulletin - Issue 7

25th July 2006

DOUNREAY DIRECTOR TAKES TEMPORARY CHARGE OF UKAEA
Following Dipesh Shah's decision not to seek a further term as chief executive of the UKAEA when his current three-year term ends in November, Norman Harrison, currently the director at Dounreay, has been appointed acting chief operating officer of the UKAEA. While Dipesh Shah will remain as CEO for the balance of his appointment, Norman Harrison's role as acting chief operating officer will ensure continuity in the day-to-day running and performance of the organisation until a new CEO is appointed. To ensure continuity at Dounreay, Simon Middlemas, currently site manager, has been appointed acting director.

REPORT SETS OUT YEAR OF PROGRESS TO DECOMMISSION DOUNREAY
The first annual report on progress to decommission the former experimental reactor site at Dounreay has been published today. Dounreay Review 2005/06 has been produced by UKAEA, the body carrying out the safe clean-up and dismantling of the 140-hectare site.

Its publication covers the 12-month period since April 1, 2005, when UKAEA's clean-up role changed to that of a contractor to the new Nuclear Decommissioning Authority. The report outlines the key decommissioning achievements during the year as well as safety, environmental and financial indicators, and summarises the performance-based incentives that are used by the NDA to measure delivery and award fee.

The report can be downloaded at http://www.ukaea.org.uk/downloads/dounreay/Dounreay_Review_2005-06.pdf
Hard copies are available on request from the communications department at Dounreay (tel: 01847 806080).

NEW PLANT STARTS FOR NEXT PHASE OF SODIUM CLEAN-UP
The sodium inventory disposal (SID) facility has commenced active commissioning at the Prototype Fast Reactor (PFR). This symbolises a major step forward, as it allows UKAEA to start removing the final traces of sodium from redundant plant equipment being stored at PFR.

The pioneering facility, constructed within the sodium tank farm, uses the water vapour nitrogen process developed at the Janetstown off-site test facility to remove tritiated alkali metal residues from plant and vessels made redundant by decommissioning work on the Dounreay site. The facility has been designed, built and safely commissioned for UKAEA by the Alkali Metal Residue Recovery (AMRR) alliance of companies.

The new plant is currently being used to clean the reaction vessel from the thermal stripping rig, which was part of D8530 and was decommissioned in 1999. Operation of the new facility will allow vessels and components currently stored at PFR to be cleaned, allowing decommissioning of these systems to progress in the near future. The facility has also been designed to allow future modification to clean items wetted with the sodium-potassium metal used in the DFR, and the four remaining tanks within the sodium tank farm - all key parts of the site's future clean-up plan.

PFR POND CLEAN-UP COMMENCED
For the first time since the Prototype Fast Reactor commenced operation in 1974, the removal of items from the buffer store pond has commenced.

In the early 1980s two trial irradiated sub assemblies were placed in the pond as corrosion experiments to assess the corrosion effects of water on fuel. They were placed in modified spent fuel cans, with holes top and bottom, which allowed water to flow through the cans while the pond water was sampled for activity. With routine monitoring it was known early in the experiment that activity was present in the water, and in the mid-90s, due to the corrosion trial, the activity level in the pond water was steadily rising and continued to do so until the pond clean-up plant was commissioned last year. The revolutionary removal project began over five years ago, with the preparation of safety assessments.
More: http://www.ukaea.org.uk/sites/dounreay_project_updates.htm#July0602

On July 1, an unplanned discharge of krypton 85 gas occurred as a result of this work. While unplanned, the emission did not breach the discharge authorisation for PFR decommissioning and amounted to less then one per cent of the site's discharge authorisation for krypton 85. Regulators were notified and an internal investigation started.

UKAEA LISTENS TO PUBLIC VIEWS ON PARTICLES
An independent report on the views of people in Caithness and north Sutherland about radioactive particles in the marine environment has been published. The report summarises the feedback from more than 400 people who took part in a series of information-gathering events ahead of formal consultation later this year on the options for dealing with the particles. UKAEA's response to the views has also been published.
More: http://www.ukaea.org.uk/news/2006/11_07_06.html

Meanwhile, work is underway to begin a technical assessment of the options. A scoring panel has been set up and meets this week for the first time. The group consists of independent members representing a wide range of expertise, including environment, health and safety, socio-economics and marine engineering. They will initially screen out options which are not technically feasible or are illegal, then assess the options left against a set of criteria. Once that is done work will begin combining on-shore and off-shore options before carrying out final scoring. All information will be made available and there will be full consultation to determine the best practical environmental option (BPEO).

DUNNET BEACH CLEAN
Staff from Dounreay took time out to undertake a beach clean at Dunnet. Forty-one volunteers and their families struck it lucky with a beautiful sunny day and worked from 1pm to 5pm, collecting over 250 bags of rubbish from the beach. The clean-up was organised by the site after a follow-up particle survey found nothing. Simon Middlemas, acting Dounreay director, said: "I was pleased when it was reported that no particles had been detected following the second survey of the beach. Dunnet is a beautiful beach and a beach clean was just what it needed to allow people to enjoy the beach to the full - especially with the weather being so good."

MEP SEES INSIDE REACTOR DECOMMISSIONING
Struan Stevenson, a Scottish Conservative Member of Parliament, made a fact-finding visit to Dounreay on July 19. He met with senior management, trade union representatives and saw inside the decommissioning of the Dounreay Fast Reactor.

BOARD HOSTS RECEPTION
The board of the UKAEA met at Dounreay on July 3. The preceding evening, members hosted a reception at the Park Hotel, Thurso, attended by over 100 figures from the local community.

AT A GLANCE
Number of days since a lost time accident - 33 days
(No. of man-hours since a lost time accident - 454,279 hours)

Liquid metal destroyed in decommissioning Prototype Fast Reactor

Volume: 1136 tonnes
Percentage complete: 75 %


NB Plant currently shut down while major reactor components are jacked up out of their seal.

Research reactor reprocessing liquor conditioned as solid intermediate-level waste

Total no. of drums to date: 1,879
Percentage complete to date: 37.6%
Conditioned in current financial year: 0

NB Plant currently shut down while spillage is cleaned up.

Solid Low Level Waste processed for disposal
Total so far this financial year: 2,101 drums

Employment levels
UKAEA - Full Time Equivalents
May 1,173
June 1,160
July 1,144

Sub-contractors - number of personal passes
1,220
1,206
1,198

Sub-contractors - number of gate-held passes
232
179
180

 

Related Businesses

 

Related Articles

Design Contract Awarded For Dounreay Shaft And Silo WorkThumbnail for article : Design Contract Awarded For Dounreay Shaft And Silo Work
Dounreay has awarded an important waste clean-up contract to Jacobs as the site plans for the future of its deepest historic radioactive waste store.   Jacobs and its supporting partners have been awarded a 6-year contract to provide a design management team to produce a fully integrated design for the shaft and silo project.  
Radiation dose to public from Dounreay reducesThumbnail for article : Radiation dose to public from Dounreay reduces
Dounreay’s radioactive impact on the environment continues to fall, according to a report.  The annual survey report “Radioactivity in Food and the Environment” (RIFE 2012) has recently been published and it can be read here - http://www.sepa.org.uk/radioactive_substances/publications/rife_reports.aspx The report uses data obtained from samples of air, fresh water, grass, soil, and locally sourced meat, fish, milk and vegetables during 2012.  
57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay
Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.  A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.  
Dounreay Dome Paint Job ScrappedThumbnail for article : Dounreay Dome Paint Job Scrapped
Bosses at Dounreay agreed that they won't now be spending £500,000 on a repaint of the sphere.   They money saved will go instead towards actual decommissioning work.  
Clean-up Reveals 6000 Years Of Human HistoryThumbnail for article : Clean-up Reveals 6000 Years Of Human History
Getting rid of Britain's 20th century experiment with fast breeder nuclear reactors is illuminating the history of human settlement on Scotland's north coast stretching back 6000 years.   Archaeologists hired as part of the closure of the nuclear site at Dounreay have pieced together the legacy left by previous generations who occupied the site as long ago as 4000BC.  
New Report Lists Radioactive Wastes At DounreayThumbnail for article : New Report Lists Radioactive Wastes At Dounreay
The Nuclear Decommissioning Authority has published the latest edition of the UK's radioactive waste inventory.   This sets out the type and volumes of radioactive waste at sites such as Dounreay, as of April 1, 2010.  
Nuclear Shutdown Cash Boost For School Skills
Cash from the closure of the fast reactor site at Dounreay is set to breed a new generation of engineers and scientists in the Scottish Highlands.   The money from the Nuclear Decommissioning Authority will fund half the cost of a £50,000 project to increase the number of school-leavers skilled in science, technology, engineering and maths.  
New Vaults Signal Start Of Waste ClearanceThumbnail for article : New Vaults Signal Start Of Waste Clearance
The clearance of tens of thousands of tonnes of radioactive waste from the redundant nuclear site at Dounreay today moved a step closer.   Dounreay Site Restoration Ltd announced the formal award of a contract to develop a disposal site for low-level waste from the decommissioning and closure of the site.  
Ex UKAEA Boss Appointed To Crown Estates Board
THE CROWN ESTATE REAPPOINTS CHRIS BARTRAM, AND APPOINTS DIPESH SHAH OBE AND ANTHONY WHITE AS NON-EXECUTIVE BOARD MEMBERS The Crown Estate has announced yesterday, 22 December 2010, the re-appointment of Chris Bartram and the appointment of Dipesh Shah and Anthony White as Non-Executive Board Members.   Chris Bartram, who has held the appointment as Crown Estate Board Member for four years has been reappointed for a further four year term with effect from 1 January 2011.  
Dounreay Boss Welcomed Funding Announcement
Dounreay Site Restoration Ltd recently welcomed an announcement about how much public money will be available to continue nuclear clean-up in the UK.   DSRL manages the closure of the site on behalf of the Nuclear Decommissioning Authority, which today confirmed that its total expenditure, including income generated, would be maintained at current levels of around £3bn a year.