Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider  

 

Isolation Of Dounreay's Shaft Commences

26th January 2007

Photo Gallery

Photograph of Isolation Of Dounreay's Shaft Commences

Dounreay has started drilling up to 400 boreholes around the site's waste shaft in the biggest step so far towards its eventual clean-out.

Grout will be injected through the boreholes to seal fissures in the rock around the 65 metre deep shaft and so create a giant containment barrier in the shape of a boot around the shaft that will isolate the radioactive waste from groundwater.

The project - the first of its kind in the world - will prevent large volumes of groundwater flowing into the shaft during waste retrieval and becoming contaminated. It will also reduce the risk of leakage from the shaft in the interim.

The work is being carried out by UKAEA on behalf of the Nuclear Decommissioning Authority and follows agreement by regulatory authorities.

UKAEA's Warren Jones, shaft isolation senior project manager, said: "Decommissioning the waste shaft is one of the biggest clean-up challenges in the world today, so I am delighted that we have now commenced this important phase of work to clean it out."

The boreholes will be drilled in stages in a boot shape around the shaft, with constant monitoring to provide assurance that each stage has been completed successfully.

The change from an oval grout curtain to a boot shape evolved last year following trials by the project team at Dounreay. It was realised a boot shape would be more efficient because it limits the internal surface area of the grout curtain and so helps to minimise the volume of water entering the shaft after construction.

Prior to the construction of the grout curtain, 12,000 tonnes of concrete was poured to create a raised working platform at the top of the shaft. A plug at the base of the shaft, which separates it from a sub-sea tunnel carrying the site effluent discharge pipe, was reinforced and a section of the tunnel infilled.

Isolation of the shaft has commenced four years earlier than previously planned and is expected to take between two to four years to complete. The £16 million isolation contract was awarded to Ritchies, the specialist geotechnical division of Edmund Nuttall Ltd, and the total cost of this phase of the shaft decommissioning is £27 million.

Once complete, isolation is expected to improve safety and environmental conditions during waste retrieval operations. The timescale for this is the subject of discussion with regulators and the NDA about funding availability.
A video telling the history of the shaft, its isolation and showing how it could be emptied was screened for the first time to members of the Dounreay Stakeholder Group on Wednesday 24 January 2007.

The DVD is also available on the UKAEA website and copies are available from the site.
See http://www.ukaea.org.uk/sites/dounreay_site_video.htm

Retrieving the waste from the shaft is one of the most complex decommissioning jobs. Concept designs for removing the waste are still being developed, evaluating what techniques can be utilised, what equipment is needed and how this is operated to successfully retrieve the waste from the shaft and silo. This project is to provide retrieval equipment, a treatment and packaging plant and interim intermediate level waste storage. The footage gives an indication of the plans being proposed.

Steve Efemey, UKAEA's shaft retrieval project manager, said: "We are still in the concept design phase of this project and some significant alterations have been made since the DVD was produced, however it does give some insight into how we intend to approach this incredibly complex project."

During construction of the subsea effluent tunnel at Dounreay in the 1950s, a 65-metre vertical shaft was excavated to remove the spoil. Following the completion of the tunnel, the shaft was plugged at the base and authorised by the Scottish Office for the disposal of solid intermediate-level waste. The last disposal took place in 1977 prior to an explosion.

A detailed independent assessment of this work was carried out by the Scottish Environment Protection Agency. SEPA's agreement to proceed followed UKAEA's response to recommendations in the report, which can be found at
http://www.sepa.org.uk/pdf/radioactivity/dounreay/Dounreay_shaft_technical_assessment.pdf

 

Related Businesses

 

Related Articles

Design Contract Awarded For Dounreay Shaft And Silo WorkThumbnail for article : Design Contract Awarded For Dounreay Shaft And Silo Work
Dounreay has awarded an important waste clean-up contract to Jacobs as the site plans for the future of its deepest historic radioactive waste store.   Jacobs and its supporting partners have been awarded a 6-year contract to provide a design management team to produce a fully integrated design for the shaft and silo project.  
Radiation dose to public from Dounreay reducesThumbnail for article : Radiation dose to public from Dounreay reduces
Dounreay’s radioactive impact on the environment continues to fall, according to a report.  The annual survey report “Radioactivity in Food and the Environment” (RIFE 2012) has recently been published and it can be read here - http://www.sepa.org.uk/radioactive_substances/publications/rife_reports.aspx The report uses data obtained from samples of air, fresh water, grass, soil, and locally sourced meat, fish, milk and vegetables during 2012.  
57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay
Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.  A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.  
Dounreay Dome Paint Job ScrappedThumbnail for article : Dounreay Dome Paint Job Scrapped
Bosses at Dounreay agreed that they won't now be spending £500,000 on a repaint of the sphere.   They money saved will go instead towards actual decommissioning work.  
Clean-up Reveals 6000 Years Of Human HistoryThumbnail for article : Clean-up Reveals 6000 Years Of Human History
Getting rid of Britain's 20th century experiment with fast breeder nuclear reactors is illuminating the history of human settlement on Scotland's north coast stretching back 6000 years.   Archaeologists hired as part of the closure of the nuclear site at Dounreay have pieced together the legacy left by previous generations who occupied the site as long ago as 4000BC.  
New Report Lists Radioactive Wastes At DounreayThumbnail for article : New Report Lists Radioactive Wastes At Dounreay
The Nuclear Decommissioning Authority has published the latest edition of the UK's radioactive waste inventory.   This sets out the type and volumes of radioactive waste at sites such as Dounreay, as of April 1, 2010.  
Nuclear Shutdown Cash Boost For School Skills
Cash from the closure of the fast reactor site at Dounreay is set to breed a new generation of engineers and scientists in the Scottish Highlands.   The money from the Nuclear Decommissioning Authority will fund half the cost of a £50,000 project to increase the number of school-leavers skilled in science, technology, engineering and maths.  
New Vaults Signal Start Of Waste ClearanceThumbnail for article : New Vaults Signal Start Of Waste Clearance
The clearance of tens of thousands of tonnes of radioactive waste from the redundant nuclear site at Dounreay today moved a step closer.   Dounreay Site Restoration Ltd announced the formal award of a contract to develop a disposal site for low-level waste from the decommissioning and closure of the site.  
Ex UKAEA Boss Appointed To Crown Estates Board
THE CROWN ESTATE REAPPOINTS CHRIS BARTRAM, AND APPOINTS DIPESH SHAH OBE AND ANTHONY WHITE AS NON-EXECUTIVE BOARD MEMBERS The Crown Estate has announced yesterday, 22 December 2010, the re-appointment of Chris Bartram and the appointment of Dipesh Shah and Anthony White as Non-Executive Board Members.   Chris Bartram, who has held the appointment as Crown Estate Board Member for four years has been reappointed for a further four year term with effect from 1 January 2011.  
Dounreay Boss Welcomed Funding Announcement
Dounreay Site Restoration Ltd recently welcomed an announcement about how much public money will be available to continue nuclear clean-up in the UK.   DSRL manages the closure of the site on behalf of the Nuclear Decommissioning Authority, which today confirmed that its total expenditure, including income generated, would be maintained at current levels of around £3bn a year.