Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider  

 

Eight-ton Fans Will Drive Fuel Plants Clean-up

21st May 2009

Photograph of Eight-ton Fans Will Drive Fuel Plants Clean-up

Like a giant Meccano set, some 1500 parts are being fitted together to create a new ventilation system that will protect workers decommissioning some of Dounreay's most hazardous facilities.

The network of fans, electrical infrastructure, supports, ducts, chambers and stacks will vent the airflow during the next stages of cleaning out and dismantling the key plants that made up the Fuel Cycle Area.

This was the part of the site dating from the 1950s where nuclear fuels were assembled, dissolved, examined and re-assembled in support of Britain's research and development of nuclear energy.

Decommissioning the Fuel Cycle Area is expected to cost 550 million and involves dismantling sealed facilities that are contaminated with some of the most hazardous radioactive debris.

Some of these plants have already been cleaned out and one, the former fuel fabrication plant, has been demolished - the first plant of its type ever successfully decommissioned in Scotland.

The installation of a modern ventilation system will allow teams of decommissioning staff to complete the clean-out and demolish the rest of the facilities by 2025.

The steelwork, weighing some 300 tonnes in total, was delivered to the site in pre-fabricated sections in 150 lorry-loads and installation is now almost 90 per cent complete.

The main contractor is JGC Engineering and Technical Services, with a team of about 40 people now working on the 9 million project.

"We're on schedule to inactively commission the system by the end of October," said project manager Iain Lyall of Dounreay Site Restoration Ltd. "This will be followed by a period of testing, with a target of the end of March 2010 to complete active commissioning."

Each of the dozen buildings that make up the heart of the Fuel Cycle Area has its own extract ventilation system with high integrity fans and ductwork, extracting contaminated air through high efficiency filters and exhausting into common ducts which terminate in the existing 55m high, 4.5m diameter vent stack.

By next March, the existing stack will have been replaced by a new system comprising two 30m high vent stacks, each 2m in diameter, fed by duty/standby inverter-driven 90kW & 132kW fans connected to the existing common ducts. The variable duty provided by inverter control will meet the decreasing ventilation needs as the facilities are demolished sequentially over the coming years.

Halifax Fans, West Yorkshire, supplied the four fans which, at 69 ins and 78 ins impeller diameters and weighing 8.5 tonnes each, were the largest nuclear specification gas-tight fans ever built by the company.

The fan impeller design was based upon Halifax's Beaufort fans, with self-cleaning backward curved impellers which can be withdrawn from the drive side so that should it prove necessary, this can be achieved without the need to disconnect any ductwork. The exterior steelwork was shot blasted and painted with a high integrity offshore/chemical works 3-coat paint system with a minimum dry film thickness of 220m. The fans were fitted with rotation sensors and vibration monitoring equipment along with gas-tight EPDM rubber flexible connections on the fan inlets and outlets and each unit was supported on anti-vibration mounts. Following fabrication, all four fans were pneumatically pressure tested in-house and witness run-tested prior to despatch to site.

 

Related Businesses

 

Related Articles

Major Contract To Support Next Stage Of Dounreay Clean-upThumbnail for article : Major Contract To Support Next Stage Of Dounreay Clean-up
Construction of a new facility to support the decommissioning of reactors and demolition of historic active laboratories are just two of Dounreay's major projects expected to be delivered as part of a new framework agreement, potentially worth up to £400 million, which is being published in the Official Journal of the European Union (OJEU) today.  - www.ojeu.eu The decommissioning services framework agreement will initially be for a period of up to 4 years with the possibility of extensions of up to 3 years meaning skyline changes could be delivered over the next decade under the arrangements.  
Brakes Are Off As Reactor Clean-up Moves ForwardThumbnail for article : Brakes Are Off As Reactor Clean-up Moves Forward
Engineers at Dounreay have raided a scrap car and a kitchen can opener to help decommission one of the site's reactors.   The handbrake from a vintage 1968 Ford Cortina has been used to help steer a camera, attached to wheels taken from can openers, into the Prototype Fast Reactor (PFR) where a detailed survey inside the plant was completed.  
End Of The Dome Now In Sight At DounreayThumbnail for article : End Of The Dome Now  In Sight At Dounreay
Dounreay Site Restoration Limited has submitted a planning application to the Highland Council covering a series of decommissioning projects expected to take place between 2018 and the site's shut down, also known as the interim end state.   The application, which is the last of three planning phases covering the overall decommissioning of the site, follows engagement undertaken earlier this year including public events and an opportunity to comment on draft documents online.  
Dounreay switches to dronesThumbnail for article : Dounreay switches to drones
Drone technology is helping Dounreay reduce the risk of accidents and save money on its inspection of buildings.  A camera mounted on an unmanned aerial vehicle is taking over tasks previously carried out by workers on elevated work platforms.  
Dounreay Team Begins To Empty Reactor Of Nuclear MaterialThumbnail for article : Dounreay Team Begins To Empty Reactor Of Nuclear Material
Work is underway to retrieve the last remaining radioactive fuel elements that have been stuck for decades inside the iconic Dounreay Fast Reactor (DFR).   The experimental dome-shaped nuclear reactor once led the world in fast breeder technology and after it closed in 1977 most of the core fuel was removed.  
Graduating Apprentices "the Future Of The Far North"Thumbnail for article : Graduating Apprentices "the Future Of The Far North"
Eleven young people who have completed their Dounreay apprentice training are "very much a part of the future of the far north." Guest speaker Jamie Stone MP told the audience at the apprentice indenture ceremony that took place last Friday that, as Dounreay continues to decommission, the newly indentured apprentices would be an important part of the area's ability to offer a skilled and innovative workforce.   Dounreay Managing Director and former nuclear industry apprentice Phil Craig added: “I am very proud that we are celebrating yet another group of talented apprentices.  
Companies Set To LINC With DounreayThumbnail for article : Companies Set To LINC With Dounreay
Companies are being invited to LINC together and support Scotland's largest decommissioning project thanks to an innovative new scheme designed to increase the number of small and medium enterprises (SMEs) delivering clean-up work at Dounreay.   Up to five companies will be invited to help understand and develop the best proposal for size-reducing all of the machinery and components that will need to be removed from Dounreay's Prototype Fast Reactor (PFR) - the largest to be built at the Caithness site.  
Graduates Kick Start Their Career At DounreayThumbnail for article : Graduates Kick Start Their Career At Dounreay
Graduates from as far afield as Portugal and London arrived in Caithness last week to kick start their career at Dounreay.   Ten new recruits have started on the two-year graduate scheme with educational backgrounds as diverse as engineering, law and digital forensics and ethical hacking.  
Dounreay's Oldest Reactor To Be DemolishedThumbnail for article : Dounreay's Oldest Reactor To Be Demolished
It is 60 years this weekend since the first criticality was achieved in Scotland using a test rig at Dounreay.  Now the decommissioning team responsible for the site is marking that milestone by taking a major step towards demolishing the oldest reactor that remains at the former fast reactor research centre.  
Fast Reactors The Caithness Dimension - Film Made In 1994Thumbnail for article : Fast Reactors The Caithness Dimension - Film Made In 1994
This film, produced by AEA Technology in 1994, looks back on the history of the fast reactor development programme at Dounreay..  

[Printer Friendly Version]