Within a few years, much of the experimental nuclear site at Dounreay will
disappear from the landscape.

Many of the facilities that have dominated the skyline of Scotland's north
coast for the past 50 years will be razed to the ground.

As the demolition of the entire site gets nearer, members of the public
will be invited in the near future to take part in a debate about which
aspects of Britain's abandoned experiment with fast reactors should be
preserved for posterity when everything else has gone.

The three-month debate early in the new year aims to identify opportunities
and discuss the options. It is expected to result in a heritage strategy
that will leave in place a legacy for future generations to interpret
Dounreay's significance in the industrial history of the last century.

It's the first time in the UK that a heritage strategy has been developed
for an entire nuclear site.

"The impetus stems from the consultation we carried out two years ago about
the 'end state' for decommissioning. This focused minds on the condition we
leave the place in when all the redundant facilities have been cleared
away," explained Doug Graham, environment team leader at Dounreay Site
Restoration Ltd.

"One of the recommendations was 'an open and transparent decision on the
future of the fast reactor sphere'. Discussions with Historic Scotland
around the same time lead us to believe we needed a heritage strategy for
the site as a whole. The heritage of the site is a lot broader and deeper
than simply one building and it's important we debate and explore all
aspects as part of this exercise."

All the redundant buildings at Dounreay are due to be demolished by 2025,
with more than 100 structures flattened already.

The only buildings needed after 2025 will be those required to look after
an estimated 15,000m3 of intermediate-level radioactive waste from
decommissioning and to exclude the public from tracts of land where
radioactive contamination will be left undisturbed.

DSRL hired Atkins Heritage to prepare a draft strategy that identifies
those aspects of the present site that are feasible to preserve, celebrate
or commemorate.

"Most buildings will be beyond economic repair, given their age and a
legacy of radioactive contamination," said James Gunn, the site's heritage
officer.

"But there are some aspects of the work that went on inside them that can
be preserved. It's important we explore what people want to see kept and
the draft strategy builds on some of the ideas that have come forward
already, such as relocating the fast reactor control room to a museum, 3D
computer models and capturing the memories of retired workers of the early
pioneering days. It's important, too, that the exercise considers cost
issues, who will look after saved items in the future and how."

A consultative document will be published and the public given three months
to make their views known. The feedback will help to shape recommendations
to the site's owners, the Nuclear Decommissioning Authority, next summer

 

Related Businesses

 

Related Articles

Dounreay Workers Vote To Strike Over PayThumbnail for article : Dounreay Workers Vote To Strike Over Pay
Workers at the Dounreay nuclear power complex in Caithness have voted to strike in a dispute over pay.   The GMB union said its ballot had an 85% turnout.  
Gad Develops Bespoke Benefits Modeller As Nuclear Decommissioning Authority Reforms Pension BenefitsThumbnail for article : Gad Develops Bespoke Benefits Modeller As Nuclear Decommissioning Authority Reforms Pension Benefits
GAD has built a pension benefit modeller to support the Nuclear Decommissioning Authority as it undertakes a pension reform programme.   The Government Actuary's Department (GAD) has supported the Nuclear Decommissioning Authority (NDA) as it undertakes a pension reform programme.  
North Highlands Team Headed For International Robot ChallengeThumbnail for article : North Highlands Team Headed For International Robot Challenge
NRS Dounreay and socio economic partners hosted the second FIRST® LEGO® League Challenge North Highland Tournament in March with local schools taking part.   The North Highland tournament took place in March at ETEC on the University of the Highlands and Islands (UHI) North West and Hebrides Thurso Campus.  
Dounreay Power Station Faces Threat Of Strike ActionThumbnail for article : Dounreay Power Station Faces Threat Of Strike Action
Unite the union confirmed around 450 of its members employed by Magnox Limited based at Dounreay power station are being balloted for strike action in a pay dispute.   The ballot which is now open will close on 2 April.  
NDA Group Hosts First Ever Large-scale Graduate Recruitment EventThumbnail for article : NDA Group Hosts First Ever Large-scale Graduate Recruitment Event
This week, the NDA group hosted it's first ever large-scale graduate recruitment event in Manchester, with over 600 candidates in attendance.   The Nuclear Decommissioning Authority (NDA) group held its first ever large-scale graduate recruitment event in Manchester this week, bringing together more than 600 candidates as it looks to double the number of opportunities across its graduate schemes this year.  
Nuclear Decommissioning Authority - Draft Business Plan 2024 To 2027 For ConsultationThumbnail for article : Nuclear Decommissioning Authority - Draft Business Plan 2024 To 2027 For Consultation
The NDA Draft Business Plan sets out key activities and expected progress for all 17 of the NDA's nuclear sites over the next 3 years.  We want to hear from anyone who has a comment on any aspect of this document.  
Learn And Earn - Apprentice Recruitment Open - Nuclear Waste Services - Dounreay EtcThumbnail for article : Learn And Earn - Apprentice Recruitment Open - Nuclear Waste Services - Dounreay Etc
NRS is delighted to announce that we are recruiting over 30 level 2 - 6 engineering and business apprentices to deliver our decommissioning mission.   John Vickerman, Chief People Officer, commented: "NRS is an exciting place to be.  
Register Now For The Largest Nuclear Decommissioning Supply Chain Event In EuropeThumbnail for article : Register Now For The Largest Nuclear Decommissioning Supply Chain Event In Europe
Today, Monday 20 November, the NDA has opened registration for its tenth nuclear decommissioning supply chain event, which will be held at The International Centre in Telford on 27 June 2024.   Launched in 2011, the supply chain event has gone on to attract a total of around 10,000 visitors from more than 20 countries over the years, representing thousands of companies both large and small.  
Work Begins To Permanently Secure Low Level Nuclear Waste VaultsThumbnail for article : Work Begins To Permanently Secure Low Level Nuclear Waste Vaults
A key programme of work at the Low Level Waste Repository in Cumbria is making real progress.   The Repository, which is part of Nuclear Waste Services (NWS) and manages disposal of the UK's low level radioactive waste, has started key work on the final capping of historic trenches and vaults which are now full and ready for permanent closure.  
Science Fair Connecting Students To A Future In NuclearThumbnail for article : Science Fair Connecting Students To A Future In Nuclear
Nuclear Waste Services (NWS) and Women in Nuclear (WiN UK) hosted an event for young people to promote and showcase career opportunities in the nuclear industry.   Around 150 students attended the first ever Nuclear Connection Science Fair in Oxford, hosted by NWS and Women in Nuclear (WiN UK) on 10 November 2023.