Caithness Heat & Power - Accounts Commission Report

2nd March 2011

Highland Council failed to establish effective governance arrangements for innovative heat and power project

The Accounts Commission has considered a report on The Highland Council's Caithness Heat and Power (CHaP) project, which was run by an arms-length community enterprise. In its findings the Commission says the lack of appropriate risk management and effective governance arrangements for the project was a corporate failure by the council. It also highlights aspects of the performance of two senior officers in relation to governance.

The Highland Council established a not for profit company in 2004 to provide a heating system to 500 houses in Wick. The company failed to deliver its objectives and the project experienced technological and financial problems. The council's total commitment to the project including provisions stands at around £13.8 million. It has spent around £10.5 million so far but because the project is still ongoing the full cost and any losses cannot be determined yet.

The Commission says that there were weaknesses in the council's arrangements for oversight of the project. From the start there was a lack of appropriate risk management. The council did not monitor progress effectively and failed to ensure that appropriate control mechanisms were in place.

The Commission notes that the council has taken action to avoid a similar situation happening again. The structure of the council has also changed in recent years and there is now less emphasis on area-based decision making.

Chair of the Accounts Commission for Scotland John Baillie said: "The CHaP project was established as an innovative scheme to benefit the local community. Unfortunately the council's arrangements for managing its interest in the project were not as good or as effective as they should have been. However, The Highland Council has been addressing the difficulties in governance and financial stewardship and has taken action to avoid a similar position developing again.

"Many councils deliver projects and services through arms length bodies. The history of this project has important lessons for elected members and senior officers. Effective governance and risk management are always needed from the start to ensure best use of public money."

The following is an extract from the Accounts Commission for Scotland meeting on 17th February 2011. The full meeting covering many other matters apart from Caithness Heat and Power can be found on the Accounts Commission web site at -
http://www.audit-scotland.gov.uk/about/ac/papers.php

A REPORT BY THE CONTROLLER OF AUDIT TO THE ACCOUNTS COMMISSION
UNDER SECTION 102(1) OF THE LOCAL GOVERNMENT (SCOTLAND) ACT 1973
THE HIGHLAND COUNCIL: CAITHNESS HEAT AND POWER - FOLLOW-UP REPORT

Summary
1. This report is in response to the Accounts Commission's direction to the Controller of Audit for further investigations into The Highland Council's involvement in the Caithness Heat and Power (CHaP) project. The investigation involved careful consideration of the role of key individuals in the governance of the project and has provided a fuller understanding of the context in which key decisions concerning the project were made.

2. In summary, I have concluded that:
• In the period between project approval in October 2004 and May 2008 when the significant problems were identified, only three reports were made to the Council. In each case these were when the CHaP company was urgently seeking funds.
• The Council failed to establish effective governance for its interests in CHaP. As a result, it was not well placed to deal with key issues as they emerged and only became aware of the full significance of the company's decision in 2006 to procure high risk gasification technology two years later.
• The former Chief Executive was aware of governance concerns and initiated actions but did not follow through to ensure these actions were effective. For his part, the
Director of Finance should have been more forthright in pursuing his concerns about project governance.
• The elected member on the CHaP company board could have done more at key stages to ensure the Council was aware of the position. The dissolution of the area committee structure and the associated departure of locally based officers meant that he became increasingly isolated.

3. Overall, there was a lack of a co-ordinated, corporate response to governance and ultimately the project, service users and council finances were left exposed. The project is ongoing but it seems likely that it will not achieve all its objectives and that service users will not receive the full benefits anticipated. It is also unlikely that full value for public money will be achieved. However, because the project is ongoing I am not in a position at this stage to identify overall costs or to quantify any losses that may have been, or will be, incurred.

4. I understand from the Council that currently its total commitment to CHaP including provisions stands at £13.77 million and that the total amount spent by it on CHaP is £10.5 million. However, the Council has indicated that this is a moving picture and that it will be required to advance more funds to CHaP soon to keep the company's overdraft within its current approved £0.25 million limit.

*Introduction and audit approach

*5. In February 2009, the Council considered a report on Caithness Heat and Power (CHaP) and was informed that its internal auditors were undertaking an audit of the project. Internal audit reported to the Council in January 2010, having carried out a detailed, desk-based review of reports, email and other documentation covering the period from August 2002 when the idea for the project first came to light to August 2008 when the Council took direct control of the project.

6. The external auditors' annual audit report to the Council and the Controller of Audit in October 2009 referred to CHaP and highlighted a range of technological, financial and governance problems. In view of the serious nature of the issues the Controller decided to report1 to the Accounts Commission.

7. The purpose of that report was to highlight to the Commission and the public the serious and wide-ranging deficiencies in the Council's dealings with CHaP and the problems which can occur when councils do not observe the 'following the public pound' principles2, which apply when councils decide to deliver projects or services through arms-length external organisations (ALEOs). As such, it was a high level report drawing together the findings from the audit work to date, principally the key issues identified by internal audit. The Controller's initial report was dated 7 June 2010 and is attached as Appendix 2.

8. The Commission considered the Controller of Audit's report at its meeting on 17 June 2010. The Commission directed the Controller to carry out further investigations and to report back on project governance and accountability, particularly the roles of the Council's statutory officers and the elected member who represented the Council on the CHaP company board.

9. The further investigation therefore focussed on senior individuals' involvement in the Council's governance of the CHaP project, between 2002 and 2008. In particular, we
interviewed:
• the current Chief Executive (who until July 2007 was the Director of Corporate
Services & Depute Chief Executive and the Council's monitoring officer)
• the current Depute Chief Executive & Director of Finance (who was and remains the
Council's proper officer for finance)
• the former Chief Executive (who retired on 11 July 2007 and was the Council's head of paid service)
• the elected member who represented the Council on the CHaP company board.
10. Subsequently, in view of his central role in monitoring the Council's interest in CHaP, we also interviewed the Council's current Corporate Manager. He held the role of Caithness Area Manager between October 2002 and April 2007 at which point he was appointed and remains Corporate Manager. As Area Manager he reported directly to the former Chief Executive.

11. Taken together with evidence gathered by internal audit and further information obtained from the Council as part of this investigation, these interviews helped me gain a fuller understanding of the context in which key decisions concerning the project were made and individuals' roles in the governance of the project. The individuals interviewed have had the opportunity to comment on a draft of this report and I am grateful to them and other Council officers for their co-operation in the follow-up audit investigation.

12. My report first considers the background to the project and the reports made to the Council between 2004 and 2008. I then review the steps taken to establish governance over the Council's interests in the project and then the roles of the Council's statutory officers and the elected member who represented the Council on the CHaP company board. Throughout, the focus is on the Council and its interaction with the project and the CHaP company; governance within the CHaP company is outwith the scope of this report.

*Project background and reporting to the Council

*In the period between project approval in October 2004 and May 2008 when the significant problems were identified, only three reports were made to the Council. In each case these were when the CHaP company was urgently seeking funds.

13. The decentralised area committee structures in place at the time of the inception of the CHaP project in 2002 provided the environment for the project to gain substantial momentum. The Caithness Area Committee envisaged a district heating system fuelled by woodchip that would provide benefits for local housing and business. Centrally, the Council was aware of the initiation of the project, viewing it as a relatively straightforward development financed by monies set aside to improve council housing and consistent with corporate priorities relating to renewable energy and sustainability.

14. The Council's decentralised structure was highlighted in a Best Value audit report4 in April 2006. It noted the rationale for these arrangements but concluded that the associated management structures were complex and difficult for officers and elected members to understand and access. The report also noted that the decentralised structures promoted an environment where local priorities predominated.

15. The relationship between the Caithness area and the Council's Headquarters in Inverness (HQ) provides important context to the CHaP project. The Area Committee, and subsequently the CHaP company board, was supported by Council officers based locally who focussed on the project and the benefits it could bring to the area. Officers at HQ observed the decentralised structure, implemented decisions by local elected members and were keen to support local initiatives.

16. When the Council approved the CHaP project and the formation of a company to deliver it in October 2004, it was on the basis that it would involve a free-standing, wood-fuelled plant and waste heat from the local distillery. The report by the Director of Planning and Development noted the prospect of future phases involving gasification5 to generate electricity as well as heat. Assurances were provided that each phase would be self-contained and fully funded. In November 2005, the Council committed £1.6 million from housing budgets to support the district heating system. The report, by the Caithness Area Manager, again assured the Council that the project involved distinct phases, with later phases requiring no financial input from the Council.

17. Faced with steeply rising woodchip prices, locally based Council officers advised the CHaP company board to combine project phasing and to proceed with gasification, despite the previous assurances to the Council. The company advertised the contract late in 2005 and considered tenders in April 2006.

18. The Council's £1.6 million commitment in November 2005 was based on its understanding that the project involved a relatively straightforward district heating system. Developments soon after that, involving gasification, should have been reported to the Council so it was aware of the shift and to allow it to reconsider its position.

19. It was not until October 2006 that the Council received its next report on CHaP and this referred to the fact that the phases of the project had blended into one. The report, by the Director of Finance, noted a risk with gasification but that the company's heating consultant was confident the technology would provide heat and power as anticipated. The Council agreed to provide short term finance to the company in the form of a £0.55 million loan facility, to meet cash flow requirements until Energy Saving Trust grant instalments were received and bank loan finance secured.

20. In April 2007, the former Chief Executive reported to the Council that the company's bank was pressing for further safeguards relative to the loan it was providing to part-fund
the project. To secure funding for the project he had exercised emergency powers to extend existing guarantees, firstly the period over which the Council would guarantee the Company's £3 million bank loan and secondly the ongoing guarantee of the Company's overdraft facility to £1 million for the year to July 2008. As was the case in October 2006, the report referred to gasification and the possibility that the equipment would not meet expectations and in the extreme case might fail. However, the report stated that this risk had been minimised as far as possible, for example, by the company's engagement of an acknowledged energy expert.

21. By summer 2007, the equipment was in place and it was envisaged that the project would be successfully delivered. There were delays in commissioning but there was no indication at that stage that the technology would fail.

22. In January 2008, emerging financial difficulties became apparent. In light of this, the
current Chief Executive initiated work to obtain a clear understanding of the financial and technical position and this led to a report to the Council in May 2008. In that report the current Chief Executive and Depute Chief Executive & Director of Finance updated the Council on its commitments to CHaP and informed it that the Chief Executive had used emergency powers to increase the Council's level of guarantee for the company's overdraft, from £1 million to £1.2 million. The Council agreed to this and to further increase its guarantee for the overdraft up to £1.9 million. The report highlighted problems in commissioning the gasification plant.

23. The current Chief Executive and Depute Chief Executive & Director of Finance reported again to the Council in June 2008 advising of the need for the Council to cap its inancial support for CHaP and of the failure to commission the plant. These officers reported again in August 2008, at which point the Council considered options to protect its interest and agreed to take control of the company. It was only at that point, in August 2008, that the Council had the opportunity to assess full information on the technical position and the options available to it.

24. The key reporting events set out in this section are summarised in Appendix 1. In the period between project approval in October 2004 and May 2008 when the significant problems were identified, only three reports were made to the Council, in November 2005, October 2006 and April 2007. In each case these were at points when the company was urgently seeking funds. There was no reporting to the Council on attempts to commission the gasification plant or on the impact on the company finances and ultimately, the impact on the Council's finances.

*Steps taken to establish governance

*The Council failed to establish effective governance for its interests in CHaP. As a result, it was not well placed to deal with key issues as they emerged and only became aware of the full significance of the company's decision in 2006 to procure high risk gasification technology two years later.

25. Governance is about clear direction and control and is central to the success of all organisations. In cases where councils decide to deliver projects and services through an arms-length organisation such as the CHaP company, it is vital to establish sound arrangements from the outset and to ensure that these are applied effectively in practice. This section of the report considers steps taken to establish governance for CHaP; the following sections consider the roles of individual statutory officers and the elected member who represented the Council on the CHaP company board.

26. In approving the CHaP project in October 2004, the Council gave the Caithness Area Manager a clear remit to ensure that the project complied with all legal, financial and contractual requirements. His role was to take an overview of the Council's involvement in the company and to maintain a watching brief to represent the Council's interests. However, he was not suitably active in this role and did not give the project sufficient
attention at key points, including at the time of the Company's decision to procure high risk gasification technology and when it became apparent that there were problems in commissioning the equipment.

27. The Council operated a Joint Ventures Board (JVB) of senior officers from across services to monitor a range of significant projects which the Council delivered with partners and this acted as a forum to bring together specialist technical, legal and financial interests.

28. At a JVB meeting in October 2004, concern was expressed regarding the lack of control over CHaP and the need for proper governance arrangements was noted. Further concerns were expressed at the JVB in December 2004 and the former Chief Executive felt there were sufficient reasons for a 'full audit' of the scheme and how it was managed. In April 2005 the JVB noted that the scheme was moving too quickly; further phases were being worked on and it was felt that the focus should be on ensuring that the first phase was a success. In June 2005, following concerns from senior staff in his service about how best to secure the governance of the project, the Director of Finance suggested a written paper should be presented to every JVB setting out on an ongoing basis progress and proposals, as a means of keeping everyone up to date and informed and to allow consideration of the implications.

29. However, following discussion at the JVB meeting in April 2005, there was no further consideration of CHaP at the JVB. We were unable to determine why this was the case. The current Chief Executive and the Director of Finance are of the view that CHaP should have remained on the JVB agenda but they were not clear why the Board lost sight of the project. The former Chief Executive, who we understand controlled the JVB agenda, is of the view that CHaP was a housing project to provide heating to council houses and that dealing with this through the usual Committee channels (other than the JVB) for such projects was consistent with the scheme of delegation. He also informed us that a project to provide a district heating system for council houses with proven technology was not the kind of project that the JVB would have taken forward given its housing purpose and then scale.

30. As indicated, in December 2004, as a result of discussion at the Joint Ventures Board, the former Chief Executive requested the Director of Finance to undertake an audit of CHaP. Early in 2005, a group of officers met to discuss the 'following the public pound' requirements set out in the Accounts Commission/COSLA Code. The former Chief Executive was informed about the outcome of those discussions in January 2005 and his advice was sought on whether he wished to proceed to a full audit of the project. However, actions were not formalised and were not addressed, no further follow-up action was taken and the former Chief Executive did not respond to the question about a full audit.

31. At its meeting in October 2006 the Council agreed that as a condition of providing the bridging finance and/or any future guarantee, the former Chief Executive should negotiate with the company about the suitability of its governance structure. The former Chief Executive called a meeting in December 2006 to discuss governance and in advance the Director of Finance highlighted a range of issues to be addressed. Later that month the former Chief Executive set out six fundamental issues which needed to be resolved including completion of contracts between the Council and CHaP, the need to strengthen business and technical expertise on the CHaP board and the separation of Council and company interests in the role of Council officers.

32. In April 2007, the Caithness Area Manager who was responsible for overseeing the Council's interests provided assurance by email that actions had been taken across the six points raised by the former Chief Executive. Around the same time, the Director of Finance provided the former Chief Executive with a less positive picture of the outstanding governance issues by email and flagged a clear need to agree how the Council might seek to protect its interests and its exposure to the financial guarantees. The Director of Finance raised further concerns by email in May 2007 indicating that it would be useful to discuss the position on governance as he was unclear as to the position. This was not followed up by the former Chief Executive.

33. Reference was made to CHaP at a senior managers' Weekly Business Meeting early in June 2007 during discussions about the agenda for the Council meeting later that month. The Council agenda item related to an appointment to the CHaP Board resulting from the formation of the new Council following the May 2007 elections. However the Weekly Business Meeting minutes show that it was agreed the Corporate Manager (formerly the Caithness Area Manager) would review the measures taken to improve governance and provide advice to the former Chief Executive, the Depute Chief Executive and the Director of Finance before papers were sent out for the Council meeting. However, there is no evidence that any action was taken and this was not followed up.

34. Between 2004 and 2007, locally based officers became closely involved in the day to day running of the project. The Area Development Manager and the Area Finance Manager attended the majority of the Company Board meetings. In effect, they took on the role of professional managers of the project and were more aligned to the company than the Council.

35. The combined effect of inactivity on the part of the Area Manager in his role as the main link between the project and the Council, ineffective governance at HQ and the lack of appropriate separation between the role of local council officers and the CHaP company meant that at key stages the Council was not aware of developments. The fact that CHaP ceased to feature in discussions at the JVB is central. In principle, discussion at the JVB would have provided the opportunity for a coordinated, cross-service approach at the formative stage of the project, before the Council had committed substantial funds and guarantees. The JVB could also have provided or ensured effective governance over the Council's involvement in CHaP. No alternative cross- service scrutiny arrangements were put in place. Consequently, project oversight fell to the Chief Executive's service through the project monitoring and reporting responsibilities assigned to the Area Manager who was accountable to his line manager, the former Chief Executive.

36. Significantly, at the crucial point in 2006 when the company decided to take a fundamental change in direction and combine project phasing and procure high risk gasification technology, council officers did not realise the full extent of the risks involved. Even when they became aware they did not realise the full significance and the implications. It was only in 2008 that the full extent of the technical problems became apparent. At that point the Council took an informed decision that it was not in its interests to see the project fail given the serious consequences for those council tenants already connected to the part-functioning heating system and the scale of the loss the Council would incur.

37. Over the course of the Council's involvement, the Council and its officers realised that strong governance was required to protect the Council's interest in the project. Key events are set out in Appendix 1. However, despite an acknowledged need for improved governance, the Council failed at the outset and over a long period to establish effective and co-ordinated governance to monitor its interest in CHaP.

38. Strong governance would not have guaranteed the success of the project but it would have provided earlier identification of concerns and a more immediate, co-ordinated response. The Council would have been more aware and could have been given the opportunity to consider the position in more detail and reassess the extent and nature of its involvement.

*The roles of the Council's statutory officers

*The former Chief Executive was aware of governance concerns and initiated actions but did not follow through to ensure these actions were effective. For his part, the Director of
Finance should have been more forthright in pursuing his concerns about project
governance.

39. Statutory officers have specific powers and responsibilities as set out in local government legislation. The Controller's June 2010 report states that senior officers should have exercised greater influence, to varying degrees, on the governance of the project through the application of their statutory roles. This section of the report builds on this by considering the statutory roles and those senior officers' wider responsibilities for the governance of CHaP.

40. The roles of head of paid service and monitoring officer are defined tightly in statute. In summary, the head of paid service is responsible to elected members for council staffing and management structures. The monitoring officer is responsible for reporting to the council if it appears that a proposal or decision is likely to contravene legislation. On those strict interpretations, there appears to have been no reason for the statutory officers to have applied their statutory roles in relation to CHaP.

41. The statutory 'section 95' proper officer role for finance is much broader, with overall responsibility for the council's financial affairs. While the role is personal, it requires supporting structures which allow oversight of all aspects of council finances, including in relation to the council's involvement in arms-length external organisations.

42. In addition to their statutory duties, senior officers have wider responsibilities. In particular, the chief executive has a central role and ultimately has responsibility for all aspects of the management of the council and for ensuring that other statutory officers have appropriate access and influence in carrying out their roles7. Senior officers also have an important role in promoting and enforcing strong corporate governance. This depends on clear roles and accountabilities and clear instructions and processes for checking implementation, including through strong staff supervision.

43. The previous section of this report shows that the former Chief Executive initiated action to establish governance arrangements for CHaP. However, there were a number of occasions on which he did not follow through to ensure these actions were effective. For example, in December 2004 following discussion at the Joint Ventures Board he requested an audit of the project. Initial work was carried out and was reported to him, but no further action was taken. Also, in response to the actions identified by the Council in October 2006 he called a meeting to discuss governance and in December 2006 issued an email setting out the actions required. However, by that time the project was at an advanced stage and, in the event, key actions were not implemented.

44. The Director of Finance and his team raised concerns with the former Chief Executive about CHaP governance on a number of occasions. For example, the Director of Finance emailed the former Chief Executive in December 2006 and identified a range of governance issues to be addressed. In April 2007, the Director of Finance reminded the former Chief Executive by email that there was a clear need to agree how the Council might seek to protect its interests and its exposure to the financial guarantees as the project moved forward. In May 2007, the Director of Finance emailed the former Chief Executive again expressing uncertainty about the position on governance.

45. Operationally, the Caithness Area Manager reported directly to the former Chief Executive. When the project was approved in October 2004, the Council gave the Area Manager what should have been a central role in its governance arrangements for CHaP. At interview, the Area Manager reported that no steps were taken by the former Chief Executive following the Council meeting to establish what the monitoring role for CHaP involved and the reporting arrangements. It is clear that the Area Manager attached less significance to the CHaP related aspect of his role than the Council minute envisaged. Taking account of his other responsibilities and other officers' involvement, he was content to adopt a less active role.

46. The former Chief Executive initiated actions to establish and strengthen governance. However, these were not effective and he could have done more to ensure a coordinated and effective response to known governance concerns. He should also have attached more importance to the concerns raised by the Council's statutory officer for finance. Following the shift away from the Joint Ventures Board, his service carried responsibility for project monitoring and he should also have done more in terms of his line management responsibilities to ensure the Area Manager was more effective in that aspect of his role.

47. As indicated, the Director of Finance expressed concerns to the former Chief Executive in December 2006, April 2007 and May 2007 about the way matters relating to CHaP were developing. Before that, in January 2005, the Director of Finance was aware that a senior member of his team had asked the former Chief Executive whether the initial audit work should move towards a full audit and in June 2005 the Director of Finance suggested to the same member of his staff that he take concerns about governance to the forthcoming JVB. The Director of Finance was therefore aware of the need for action and he should also have been aware when no action was taken or when the action taken was ineffective.

48. The report to the Council in October 2006 was made in his name but at interview he reported that he had been on holiday at the time the report was prepared and returned to find the report on the Council agenda. He said that his lack of involvement in either the discussion or drafting of the report prevented him contributing to the nature and style of the report submitted. Later, in spring 2007, there was discussion between the former Chief Executive and the Director of Finance about in whose name the April 2007 report to Council should be made. In the event, the report was made in the Chief Executive's name only. This was on the Director of Finance's advice, because the report concerned the former Chief Executive's personal authority in applying delegated emergency powers. However, it is apparent that the Director of Finance had misgivings about the reports to the Council in October 2006 and April 2007. In terms of the April 2007 report, it is interesting to contrast the position with the report in May 2008, when under the new management structure the report seeking ratification of the current Chief Executive's use of emergency powers was made in the joint names of the current Chief Executive and the Director of Finance.

49. Operationally, the locally based finance officer who reported indirectly to the Director of Finance was able to take on the role of CHaP company Treasurer without the knowledge of the Director, resulting in conflict of interest and blurring the boundaries between the Council's finances and those of the CHaP company. For example, in January 2006 the locally based officer was involved in the detailed financial review which concluded that the gasification technology should be pursued. If detected earlier, it would have allowed a more objective assessment of the direction the project had taken and the financial consequences for the Council as project funder and guarantor.

50. As the proper officer for finance, the Director of Finance was clearly concerned about the project and governance weaknesses. He raised concerns but did not follow these through. Ultimately, these concerns proved to be well founded. As proper officer for finance he should have been more forthright, either in discussion with the former Chief Executive or, if he felt it appropriate, through alternative channels in the Council. These may have included for example, informal and formal discussions with internal and external audit, discussions with other senior Council officers, more formal exchanges with the former Chief Executive and, ultimately, raising matters with elected members.

51. In summary, the former Chief Executive was aware of weaknesses in governance and should have done more to establish effective, corporate governance over the Council's interest in the CHaP project. Specifically, the former Chief Executive should have attached more importance to the concerns raised by the Director of Finance and taken action. For his part, the Director of Finance was aware of governance concerns and that these were not being satisfactorily addressed. He should have been more forthright in pursuing his well founded concerns about project governance and finance.

*The role of the elected member who represented the Council on the company board

The elected member on the CHaP company board could have done more at key stages to ensure the Council was aware of the position. The dissolution of the area committee
structure and the associated departure of locally based officers meant that he became
increasingly isolated.

52. When appointed to the boards of companies and other arms-length external organisations (ALEOs), elected members take on additional responsibilities which sit alongside their responsibilities to the Council. In the case of CHaP, one of the local elected members was appointed to the CHaP company board which at that time consisted of three directors i.e. representatives from the Council, the distillery and the Pultneytown People's Project (a local community group). From that point, in addition to his ongoing responsibilities as an elected member of the Council, as a Board member he
had responsibilities to the company. He did his own research to understand the company director role although he also received training from the Council and had some experience from being on the Board of another Council ALEO.

53. As with others based locally, it is clear that the elected member was enthusiastic about the prospects and the potential the CHaP project offered and became one of the main drivers. The elected member was aware that combining the project phases and moving ahead with gasification was risky but took comfort from the advice he received from locally based officers and technical experts. However, the locally based officers were not sufficiently objective and the technical experts appointed by the company had by association a clear financial interest in the project. Had he had independent technical advice to hand, he would have been better equipped to question and challenge at a local level and to protect the Council's wider interests.

54. The position in terms of support for the elected member deteriorated further in summer 2007 when management restructuring took place and when the area committee arrangements ended, leaving him with significantly less Council based support. At interview, he said the project lost the support of HQ based officers at that time. Area based officers closely involved in CHaP either left the Council or took on different, wider
responsibilities and as a result the direct involvement of Council officers reduced significantly.

55. Having found himself in that position, the elected member became increasingly isolated. The monitoring and reporting arrangements he assumed were in place but in practice were neither systematic nor robust, no longer existed. The elected member had concerns about progress, particularly in the period between July and December 2007, and relied on assurances from the consultants that plant commissioning was imminent but this proved not to be the case. He informed us that during that time he contacted various officers informally to inform them about commissioning but in doing so he also indicated he was confident the problems would soon be overcome.

56. In summary, the elected member appointed to the CHaP company board was not sufficiently supported in the role, specifically in terms of independent technical advice which was essential at key stages throughout the development of the project and when the area based structure ended. His role required him to balance his responsibilities to the Council with his responsibilities to the company. At key stages, particularly as it became apparent from the summer of 2007 that there were serious problems in commissioning the plant, he could have done more to ensure that the Council had a balanced picture of the position.

*Conclusion

*57. The CHaP project gained strong local momentum which was encouraged in the then area based structure. Corporately, the Council did not establish effective governance and as a result, when the company decided in spring 2006 to pursue gasification, the significance was missed. There was a lack of a corporate, joined-up approach and as a result there were no effective mechanisms for monitoring events as they unfolded. Actions to improve governance came too late and were not effective and, ultimately, the project, services and public funds were not subject to the degree of scrutiny and protection required.

58. As the Accounts Commission's report on roles and working relationships makes clear, statutory officers have a vital role in supporting good governance and decision making. It is particularly concerning that when the need for action aimed at establishing and improving governance for CHaP was identified and when individuals expressed concerns, these were not effectively followed through. Ultimately, the Council found itself in the position where it considered its only option was to take control of the company and the project.

59. The key test of the strength of governance arrangements is at times of pressure and tensions, such as in the case involving CHaP. In light of the information he was receiving about weaknesses in governance, including from the statutory proper officer for finance, the former Chief Executive should have done more to ensure effective and co- ordinated corporate governance. This is particularly so in a context where the only mechanism for systematic and regular review of the project rested with his department through the Area Manager, for whom he had direct line management responsibilities.

60. The Council's proper officer for finance clearly had concerns but he did not bring to bear the influence attached to the proper officer for finance role. I accept there are additional complexities in applying the proper officer role when funding is provided to an ALEO but, in my opinion, had the proper officer for finance been more forthright in that role this may have led to more effective intervention at an earlier stage.

61. The local elected member who took on additional responsibilities on the CHaP company board became a strong advocate for the project but at key stages did not fully discharge his ongoing responsibilities to the Council due in part to a lack of support and technical expertise. At key stages he should have reassessed the balance between his responsibilities locally and to the company and his corporate responsibilities to the Council as a whole.

62. It is clear that the Council has taken this matter seriously and has approached the earlier internal audit and subsequent investigations by me in an open and constructive manner, with the overall aim of learning lessons from its involvement in CHaP and seeking to avoid any recurrence. The Council is also seeking to find a solution that best protects local people and services and its overall financial position.

63. The initial report by the Controller set out steps which have been taken at the Council in terms of awareness sessions for managers and elected members on lessons learned from the Council's involvement in CHaP. Through this officers and elected members should now have a stronger sense of what is required of them in terms of governance and scrutiny. The management culture has also changed, with a more collective approach and a stronger focus on responsibilities and accountabilities.

64. The Council's approach is consistent with the most recent Best Value audit report which found that the Council has strong managerial leadership and the current Chief Executive promotes a positive and inclusive management approach by setting out clear accountabilities and responsibilities. The report also highlighted that changed political and management arrangements have strengthened corporate working and reduced the inconsistency between the former district council areas while retaining a local focus and sense of identity. Overall, the audit report concluded that the Council is now demonstrating that it is 'improving well' and it is 'well placed to deliver future improvement'.

65. The Council's discussions with a new provider continue. I have requested the external auditors to monitor the position, including the action the Council is taking to protect its interests.

FRASER McKINLAY
CONTROLLER OF AUDIT
9 FEBRUARY 2011

 

Related Businesses

 

Related Articles

27/3/2024
Wick Public Service Obligation Celebrates Successful Second Year Subsidising Wick Aberdeen FlightsThumbnail for article : Wick Public Service Obligation Celebrates Successful Second Year Subsidising Wick Aberdeen Flights
The Highland Council is delighted to confirm a highly successful second year for Public Service Obligation (PSO) flights between Wick and Aberdeen.   The period from April 2023 to March 2024 has seen a substantial increase in passenger numbers, with several months seeing over 1,000 passengers using the service, and overall the service has seen year on year growth of 25%.  
18/3/2024
Members Agree Digital Ambition For Highland Council - Or How To Make Cuts Without Saying SoThumbnail for article : Members Agree Digital Ambition For Highland Council - Or How To Make Cuts Without Saying So
Members of Highland Council, who met on Thursday 14 March 2024, approved a corporate Digital Ambition, which has been designed to deliver significant organisational change across Council services, recognising the current priorities within the organisation.   The Strategy, which is embedded within the wider Council Delivery Plan, has been developed to focus attention and resources on areas of change which will deliver the greatest benefit to the Council.  
14/3/2024
Clarification On The Role Of MCR Pathways' Coordinators And Mentors In Highland Schools
The Council remains committed to supporting mentoring in our schools, including the support that is currently delivered through the MCR Pathways programme.   Highland Council is currently undertaking a review of Employability Support provided by a number of different council services and how these relate to the work carried out by external partners and in our schools.  
15/3/2024
Council Agrees A New Draft Highland Outcome Improvement Plan
Highland Council members have considered and agreed a revised draft Highland Outcome Improvement Plan.   The partnership plan has been reviewed and updated by the Community Planning Partnership.  
15/3/2024
Members agree Highland Council's new Community Wealth Building Strategy
Members at today's (14 March 2024) meeting of The Highland Council agreed the local authority's new draft Community Wealth Building Strategy.   They were also asked to note that a period of public engagement on the draft will now begin, with a final strategy returning to full Council for consideration in September.  
15/3/2024
£60m Capital Investment Approved For Roads And Infrastructure In Highland
Plans to invest up to £60m new Capital in Highland roads and infrastructure have been approved by Members at the Council meeting on 14 March 2024.   The decision will see an additional £40m Capital investment in roads and transport infrastructure.  
10/3/2024
Highland Council Budget - Delivery Plan Sets Out Roadmap To Deliver Savings And Investment
A draft Delivery Plan sets out a roadmap which will ensure the delivery of £54.6m savings and over £100m investment agreed by Council over the next 3 years.   The report is a difficult to follow series looing at areas but does not specify where the cuts to jobs will come over the next three years.  
Cuts And More Cuts But Still Cash For Arts In Highland - £30,000 For TapestriesThumbnail for article : Cuts And More Cuts But Still Cash For Arts In Highland - £30,000 For Tapestries
The Co-Chairs of the Inverness Castle Delivery Group, Fergus Ewing MSP and Cllr Ian Brown, are delighted to announce the award of £30,000 from Highlands and Islands Enterprise (HIE) in support of framing the 57 panels that will form the Tapestry of the Highlands and Islands.   This financial commitment from HIE has contributed significantly to the preservation of the 57 panels created by communities across the Highlands and Islands, of which 32 will be included in the first exhibition as part of the Inverness Castle Experience.  
6/3/2024
Council Employee Receives Special Recognition At The Scottish Empty Homes AwardsThumbnail for article : Council Employee Receives Special Recognition At The Scottish Empty Homes Awards
Dawn Meston from The Highland Council's Housing team won a prestigious award at the Scottish Empty Homes Awards held at The Studio, Glasgow on Thursday 29 February 2024 in recognition of her contribution to bringing empty homes back into use across Highland.   Between 1 April and 31 December 2023, a total of 25 empty properties were brought back into use following Dawn's intervention as Highland's Empty Homes Officer.  
5/3/2024
Highland Council Confirms Dates For Thermal Trial To Start In ThursoThumbnail for article : Highland Council Confirms Dates For Thermal Trial To Start In Thurso
The Chair of The Highland Council's Economy and Infrastructure Committee has confirmed details of a trial, to start next week, of a thermal process for carrying out pothole repairs.   An external contractor, Thermal Road Repairs, has been appointed to undertake the work using a thermal repair process.