57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay

6th April 2012

Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.
A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.

The coolant - an alloy of sodium and potassium (NaK) - was a major chemical and radiological hazard. An estimated 1000 trillion becquerels of caesium-137 was removed from the coolant during the chemical process that turned the 57 tonnes of liquid metal into 20,000 tonnes of salty water and took four years to complete.

Scotland's Cabinet Secretary for the Environment Richard Lochhead saw the last batches being processed.
He said: "This is a tremendous achievement and another example of how the highly skilled Dounreay workforce is delivering a world-class clean-up operation at one of the most complex nuclear sites in Europe.

"The Scottish Government welcomes today's announcement that Dounreay have successfully destroyed 57,000 litres of highly radioactive liquid metal from the Dounreay Fast Reactor."

The Nuclear Decommissioning Authority said it was "extremely pleased" the liquid metal no longer posed a hazard.
"This was very high on the list of hazards we wanted reduced across our whole estate," said Nigel Lowe, head of the NDA's Dounreay programme. "It's a significant achievement for Dounreay and joins a long list of examples whereby the site has delivered on key objectives and technical challenges."

The reactor - built in the 1950s - was one of only two ever built in Britain to run on liquid metal. Two cooling circuits connected by heat exchangers were filled with more than 161,000 litres of liquid metal.

More than 100,000 litres of NaK from the secondary circuit was destroyed when the reactor shut down in 1977.
Work on the primary circuit - a labyrinth of pipes 9 kilometres in length - stopped in the early 1980s when higher levels of radioactive contamination were detected.

The primary circuit contained 57,000 litres of NaK that flowed over the fuel pins in the reactor core.
The "open vent" design of the fuel cladding allowed the liquid metal to come into direct contact with the fuel, contaminating the primary coolant with huge levels of soluble radioactive caesium. Radiation measurements of the primary coolant showed the presence of 1000 trillion becquerels of caesium-137.

The high level of radioactive contamination added to the chemical hazard of alkali metal that reacts in contact with air or water. Its destruction remained on hold until a decade ago when work started on the construction of a purpose-built clean-up plant. The plant was designed to lift the liquid metal in small batches, neutralise the alkalinity with acid and extract the caesium via ion exchange.

In September 2007, the first of a total of 354 batches was lifted from the reactor. Each batch underwent chemical neutralisation to convert the alkali metal to a salty water before being passed through ion exchange columns that trapped the caesium. Designers thought the plant would decontaminate the effluent by a factor of 1000. Decontamination rates of up to 4 million were achieved during the operation, reducing levels of radioactivity in the effluent to below the limit of detection.

The resin columns used to trap the caesium will now be cemented up and managed as higher-activity waste.
"It's been a fantastic achievement by the whole team to deliver this milestone a year ahead of schedule and to higher environmental standards than anyone thought possible at the design stage," said Andy Swan, the engineer in charge of the reactor decommissioning.

"This stuff was highly volatile and highly radioactive. The chemical and radiological hazards combined to make this a real danger to the workers involved, so we needed to be certain they were protected at every step of the process until the hazard was destroyed. Their safety record throughout this operation was excellent."

Destruction of the liquid metal was among the strategic national priorities of the Department of Energy and Climate Change, which sponsors the Nuclear Decommissioning Authority.

With the reactor vessel empty of liquid metal, attention now turns to cleansing the residual traces from the primary circuit pipework and destroying small pockets in other vessels. When complete, a robotic arm will reach into the reactor vessel and begin removing the burst fuel pin and almost 1000 breeder elements still positioned around the core.

 

Related Businesses

 

Related Articles

Dounreay - The End Planning Phase - Your Chance To CommentThumbnail for article : Dounreay  - The End Planning Phase - Your Chance To Comment
A planning application will be submitted to Highland Council later this year to cover the next phase of planning at the Dounreay site.  Planning permission from 2018 to the shutdown of the site, also known as the interim end state, is the third phase of the planning required for the Dounreay decommissioning programme.  
Up To 200 Jobs To Go At DounreayThumbnail for article : Up To 200 Jobs To Go At Dounreay
The clean-up of the nuclear estate is a key priority for both the Scottish and United Kingdom governments.   Dounreay's decommissioning is well established with the site due to reach an interim end state by the early 2030s.  
Dounreay's High Street MakeoverThumbnail for article : Dounreay's High Street Makeover
A major upgrade and expansion of Dounreay's Thurso town centre office has been completed.   David Flear, Chair of Dounreay Stakeholder Group, officially reopened the building which sits at the entrance to the high street and has been the site's public information office for almost a decade.  
Doors Open At Unique Nuclear ArchiveThumbnail for article : Doors Open At Unique Nuclear Archive
A unique new archive, funded by the Nuclear Decommissioning Authority, has opened its doors to the public for the first time, bringing together historical nuclear records from all over the UK.   Speaking today at the Nucleus (Nuclear and Caithness Archive) in Wick, NDA chairman Stephen Henwood, said:Today we see a new chapter in the important role Caithness has played in the UK's nuclear history.  
First Cut Out Of Reactor Pond Wall At DounreayThumbnail for article : First Cut Out Of Reactor Pond Wall At Dounreay
The first block of concrete has been removed from the structure of one of Dounreay's cooling ponds - representing a major first step in demolishing the redundant giant chamber.   The pond is one of two concrete pits, six metres deep, which was used to store spent fuel from the Dounreay Fast Reactor (DFR).  
More Than 30,000 Bricks Removed From Redundant PlantThumbnail for article : More Than 30,000 Bricks Removed From Redundant Plant
More than 30,000 bricks have been removed from three pits within a redundant facility as part of a project to decommission a former effluent treatment plant.   A scaffold platform has been constructed to allow operators, wearing full airline suits, access to remove the bricks using small electrically operated hand tools.  
Waste contract signals Dounreay's community commitmentThumbnail for article : Waste contract signals Dounreay's community commitment
Amec Foster Wheeluker has been awarded a contract to design and build a new effluent treatment plant at Dounreay.   The agreement signals a landmark move for the Caithness site as the first to incorporate socio-economic commitments following the introduction of a new procurement policy earlier this year.  
Japanese Ambassador visits DounreayThumbnail for article : Japanese Ambassador visits Dounreay
His Excellency, Mr Koji Tsuruoka, Ambassador of Japan to the United Kingdom, Mr Yosuki Ishigami from the Economic Section of the Japanese Embassy and Mr Daisuke Matsunaga, Consul General of Japan in Edinburgh visited Dounreay during a two-day visit to the north of Scotland as a guest of Dr Paul Monaghan MP.   At Dounreay the group toured the Prototype Fast Reactor (PFR), including the reactor hall.  
Waste contract signals Dounreay's community commitmentThumbnail for article : Waste contract signals Dounreay's community commitment
Amec Foster Wheeler has been awarded a contract to design and build a new effluent treatment plant at Dounreay.  The agreement signals a landmark move for the Caithness site as the first to incorporate socio-economic commitments following the introduction of a new procurement policy earlier this year.  
10 New Apprentices Start At DounreayThumbnail for article : 10 New Apprentices Start At Dounreay
Dounreay has said "you're hired" to ten local newcomers who have started their careers at Dounreay this week.  This makes it the 61st consecutive year that apprentices have joined the site.  

[Printer Friendly Version]