57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay

6th April 2012

Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.
A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.

The coolant - an alloy of sodium and potassium (NaK) - was a major chemical and radiological hazard. An estimated 1000 trillion becquerels of caesium-137 was removed from the coolant during the chemical process that turned the 57 tonnes of liquid metal into 20,000 tonnes of salty water and took four years to complete.

Scotland's Cabinet Secretary for the Environment Richard Lochhead saw the last batches being processed.
He said: "This is a tremendous achievement and another example of how the highly skilled Dounreay workforce is delivering a world-class clean-up operation at one of the most complex nuclear sites in Europe.

"The Scottish Government welcomes today's announcement that Dounreay have successfully destroyed 57,000 litres of highly radioactive liquid metal from the Dounreay Fast Reactor."

The Nuclear Decommissioning Authority said it was "extremely pleased" the liquid metal no longer posed a hazard.
"This was very high on the list of hazards we wanted reduced across our whole estate," said Nigel Lowe, head of the NDA's Dounreay programme. "It's a significant achievement for Dounreay and joins a long list of examples whereby the site has delivered on key objectives and technical challenges."

The reactor - built in the 1950s - was one of only two ever built in Britain to run on liquid metal. Two cooling circuits connected by heat exchangers were filled with more than 161,000 litres of liquid metal.

More than 100,000 litres of NaK from the secondary circuit was destroyed when the reactor shut down in 1977.
Work on the primary circuit - a labyrinth of pipes 9 kilometres in length - stopped in the early 1980s when higher levels of radioactive contamination were detected.

The primary circuit contained 57,000 litres of NaK that flowed over the fuel pins in the reactor core.
The "open vent" design of the fuel cladding allowed the liquid metal to come into direct contact with the fuel, contaminating the primary coolant with huge levels of soluble radioactive caesium. Radiation measurements of the primary coolant showed the presence of 1000 trillion becquerels of caesium-137.

The high level of radioactive contamination added to the chemical hazard of alkali metal that reacts in contact with air or water. Its destruction remained on hold until a decade ago when work started on the construction of a purpose-built clean-up plant. The plant was designed to lift the liquid metal in small batches, neutralise the alkalinity with acid and extract the caesium via ion exchange.

In September 2007, the first of a total of 354 batches was lifted from the reactor. Each batch underwent chemical neutralisation to convert the alkali metal to a salty water before being passed through ion exchange columns that trapped the caesium. Designers thought the plant would decontaminate the effluent by a factor of 1000. Decontamination rates of up to 4 million were achieved during the operation, reducing levels of radioactivity in the effluent to below the limit of detection.

The resin columns used to trap the caesium will now be cemented up and managed as higher-activity waste.
"It's been a fantastic achievement by the whole team to deliver this milestone a year ahead of schedule and to higher environmental standards than anyone thought possible at the design stage," said Andy Swan, the engineer in charge of the reactor decommissioning.

"This stuff was highly volatile and highly radioactive. The chemical and radiological hazards combined to make this a real danger to the workers involved, so we needed to be certain they were protected at every step of the process until the hazard was destroyed. Their safety record throughout this operation was excellent."

Destruction of the liquid metal was among the strategic national priorities of the Department of Energy and Climate Change, which sponsors the Nuclear Decommissioning Authority.

With the reactor vessel empty of liquid metal, attention now turns to cleansing the residual traces from the primary circuit pipework and destroying small pockets in other vessels. When complete, a robotic arm will reach into the reactor vessel and begin removing the burst fuel pin and almost 1000 breeder elements still positioned around the core.

 

Related Businesses

 

Related Articles

24/8/2015
Connect and innovate at the NDA Estate Supply Chain event
The Nuclear Decommissioning Authority (NDA), in association with the Site Licence Companies (SLCs), invite you to ‘connect and innovate' at their fifth annual event.   Entry is free of charge to delegates and exhibitors.  
15/8/2015
Nuclear Archive At WickThumbnail for article : Nuclear Archive At Wick
The PFR stone table with the inscription 'Out of Caithness to the World' will become the centre piece of the NDA Archive when it opens its doors in 2017.   Construction of the new facility has begun at Wick and was officially opened by David Flear, Dounreay Stakeholder Group chairman, when he cut the first turf at an opening ceremony in August.  
6/8/2015
From Caithness to the World Thumbnail for article : From Caithness to the World
A ceremonial turf cutting ceremony marked the official start of building work on the new archive that will store nuclear records from across the UK.   David Flear, chairman of the Dounreay Stakeholder Group, dug into the ground at the Wick site where the Nuclear Decommissioning Authority's Nuclear Archive will start to take shape over the next 12 months.  
29/7/2015
UKAEA secures role in Europe's new spallation sourceThumbnail for article : UKAEA secures role in Europe's new spallation source
UKAEA has been selected to supply the Hot Cell Remote Handling Facility for the new €1.8 billion European Spallation Source (ESS).   ESS is currently under construction in Sweden.  
29/7/2015
Dounreay announces new managing director designateThumbnail for article : Dounreay announces new managing director designate
DSRL have announced the new managing director designate, Phil Craig.   With more than 20 years' experience in the nuclear industry, Phil’s career has focused on supporting the UK nuclear decommissioning, defence and existing power generation sectors.  
24/7/2015
Students get 'Ready Steady' for work
Twelve students successfully completed the Ready Steady Work course held in early July.   The four day course sponsored by DSRL and North Highland College was offered to all senior secondary schools in Wick, Thurso and Farr.  
16/7/2015
AREVA Awarded A Contract for Nuclear Site Decommissioning
The contract applies to twelve sites throughout the UK managed by the decommissioning company Magnox Ltd as well as the nuclear site at Dounreay in Caithness, Scotland, Radioactive Waste Management Limited's site in Harwell and the Low-Level Waste Repository in West Cumbria.   A number of segments make up the contrac.  
23/5/2015
Dounreay low level waste vaults begin to accept wasteThumbnail for article : Dounreay low level waste vaults begin to accept waste
A major programme milestone has been achieved with the placement of the first low level waste disposed into the new Low Level Waste Facilities at Dounreay.   DSRL were granted planning permission to construct up to six vaults in April 2009.  
30/3/2015
Removal of trapped fuel elements from the Dounreay Fast Reactor Thumbnail for article : Removal of trapped fuel elements from the Dounreay Fast Reactor
The removal of trapped fuel elements from the Dounreay Fast Reactor moved a step closer with the successful trial of bespoke equipment to lift off the top plate.   Decommissioning the 50-year-old experimental reactor is one of the most technically challenging projects in the NDA estate.  
30/3/2015
NDA sets out Dounreay clean-up tasksThumbnail for article : NDA sets out Dounreay clean-up tasks
The Nuclear Decommissioning Authority, the public body that owns Dounreay and funds its clean up, has published its annual business plan, setting out key tasks for the site licence company DSRL to deliver in the next 12 months.   These include: - Decontamination of Prototype Fast Reactor pond to meet regulatory requirements - Completion of construction of new fuel characterisation facilities - Material Test Reactor raffinate immobilisation complete - Continuous improvement in health, safety and environmental performance.  