NDA sets out Dounreay clean-up tasks
30th March 2015
The Nuclear Decommissioning Authority, the public body that owns Dounreay and funds its clean up, has published its annual business plan, setting out key tasks for the site licence company DSRL to deliver in the next 12 months.
These include: -
Decontamination of Prototype Fast Reactor pond to meet regulatory requirements - Completion of construction of new fuel characterisation facilities -
Material Test Reactor raffinate immobilisation complete -
Continuous improvement in health, safety and environmental performance.
The plan, laid before the UK and Scottish parliaments following a period of consultation, also sets out planned key activities for 2016-18: -
Complete removal of all fuels from Dounreay Fast Reactor -
Dounreay Fast Reactor raffinate immobilisation complete -
Prototype Fast Reactor raffinate immobilisation complete -
Letters of consent received from disposal authority for all wastes in store at interim end state
Planned expenditure on Dounreay during the next 12 months is £209 million.
This includes additional money allocated for additional work required by NDA to complete the closure of the site.
"In early 2015, a revised Lifetime Plan for Dounreay will be approved, incorporating scope that had not been finalised when the original contract was agreed," states the NDA.
"Dounreay will continue to deliver within its previously assigned annual site funding limits, whilst also delivering additional scope.
"This will result in an extension to the date by which Dounreay will achieve its Interim End State.
"The activities below now reflect the revised Lifetime Plan, however, agreement is still to be reached with DSRL regarding the specifics of activities associated with the additional scope and thus they have not been included."
The plan lists some of the key milestones on the path to site closure:
2017 -Complete Dounreay Fast Reactor fuel removal from reactor
2022 - Decontamination of Dounreay Fast Reactor structures suitable for demolition
2024 - Prototype Fast Reactor liquid metal residues destroyed
2027 - Shaft backfi lled and capped 2029/30 - Interim End State achieved
DSRL said its priority was to deliver the NDA programme in a way that causes no harm to people or the environment.
See the NDA business plan at -
http://www.nda.gov.uk/2015/03/business-plan-published/
Related Businesses
Related Articles
He joins from AtkinsRealis, where he was market director and delivery lead for its nuclear decommissioning and waste services business, and officially takes up the post today (18 November 2024), He succeeds John Grierson who has served as interim MD since May. NRS CEO Rob Fletcher said, "I am very pleased that Dave Wilson has agreed to join the team at Dounreay.
The Nuclear Decommissioning Authority group have announced five organisations as winners of this year's supply chain awards. Morgan Sindall Infrastructure, The Decommissioning Delivery Partnership, PA Consulting, Antech and The Higher Activity Waste Thermal Treatment Tranche 1 Team are the big winners in this year's supply chain awards.
More than 140 graduates have started at Sellafield Ltd. Over 140 graduates have just started their exciting careers with the company in a range of business and technical disciplines, supporting Sellafield Ltd in its mission to create a clean and safe environment for future generations.
Find out what has been happening at UKAEA in our monthly newsletter. Read about our recent activities and upcoming events.
The Nuclear Decommissioning Authority (NDA) group has on 26 September 2024 published its 2023 to 2024 socio-economic report detailing a record investment in projects across the UK. Over the last five years, the NDA group has invested £60 million in projects that enable permanent and sustainable change in its site communities, leveraging many millions more from partners.
Over 100 graduates join the Nuclear Decommissioning Authority group today as applications open for 2025. As applications open for 2025, the Nuclear Decommissioning Authority (NDA) group also welcomed its largest ever cohort of graduates today, with more than 100 new recruits ready to support delivery of one of the world's most important environmental programmes.
In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility. In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility.
At the Nuclear Decommissioning Authority biannual stakeholder summit, CEO David Peattie announced up to £5 million over five years to support around 20 PhDs. On the 17th and 18th of September the Nuclear Decommissioning Authority (NDA) hosted its biannual in person stakeholder summit, bringing together over 170 delegates from national and local government, the nuclear sector and site communities.
Nuclear Decommissioning Authority (NDA) group publishes overview of progress being made against sustainability goals. The Nuclear Decommissioning Authority (NDA) group has today published an overview of progress being made against its sustainability goals.
The Nuclear Decommissioning Authority (NDA), in collaboration with its subsidiary Nuclear Waste Services (NWS), has awarded two contracts to establish an innovative partnership for the enhanced management of asbestos waste. The Asbestos Innovation Partnership (AIP) will work with the NDA, NWS and the supply chain, to test and develop new solutions to treat asbestos waste, helping to deliver efficiencies and enable more effective waste management.