Work on new link road for Dingwall starts next week
15th October 2015
Work on the first stage of the Kinnairdie Link Road Scheme in Dingwall will begin on Monday when contractor, Pat Munro (Alness) Ltd will be on site to carry out improvements to the junction of the A862 Newton Road and the A834 Burn Place near to the Council Offices.
The A862 will be widened to provide additional stacking length on the approach to the junction from the South. An additional dedicated right turn lane serving Mart Road will be added North of the junction. The whole junction and the A862 for about 150m each side will be resurfaced. Footways will be resurfaced and the traffic signals replaced. Signs and street lights will be relocated and replaced where necessary and drainage improved.
The work, which is scheduled to take 18 weeks, will be tackled in four phases with individual traffic management arrangements for each. Existing traffic routes will be maintained where possible but the council is advising all motorists to allow extra time for their journey.
North bound traffic flow on the A862 will be maintained through the works during all phases. It will however be necessary for Southbound traffic on the A862 to be diverted via Mart Road and Station Road. A signed diversion will be in place for Strathpeffer bound traffic, initially via Tulloch Avenue and motorists are asked to follow the shown diversion route.
The traffic management will be monitored at all times during the works and arrangements modified where necessary.
Related Businesses
Related Articles
At the Highland Council Economy and Infrastructure Committee. (Thursday 2 May 2024) Members had the opportunity to review the work the Council is doing to progress active travel and improve road safety before approving the next steps.
At the meeting of the Economy and Infrastructure Committee members had the opportunity to review the last two years of the Community Regeneration Funding Programme before agreeing changes to how the 2024/25 programme will be delivered. Committee Chair, Cllr Ken Gowans said: "Following a successful two years, it is a good time to review what has gone well and what can be done better so we can continue to build on success, and seamlessly move the focus onto how best to support the delivery of projects." "With 279 live projects and over £6million of committed funds still to be claimed, there is no doubt as to the value and impact of the programme's potential.
The Highland Council's In-House bus service pilot project was launched in January 2023. The success of its first year of operation in delivering savings and creating a valued and reliable service was highlighted at today’s Economy and Infrastructure Committee.
Members of Highland Council's Economy and Infrastructure Committee today (2 May 2024) approved the local authority's draft Ecology Strategy and Action Plan which will now move forward to an 12-week public consultation. The Ecology Strategy sets out an ambitious set of actions to tackle biodiversity loss and address the ecological emergency.
Economy and Infrastructure Committee members today (2 May 2024) agreed to direct £100K from the Council's share of the UK Shared Prosperity Fund (UKSPF) to fund a new staff training programme at the Inverness Castle Experience. The funding will enable the project team to provide specialist visitor attraction training to young people identified through partners at Developing the Young Workforce (DYW) and the University of the Highlands and Islands (UHI).
The Housing and Property Committee met on Wednesday 1 May 2024 and noted the Housing Service performance report 2023/24 that met the agreed priorities and associated initiatives in the Local Housing Strategy 2023-2028. The report highlighted a number of achievements in 2023/24 in increasing housing supply.
Kate Lackie, Malcolm MacLeod and Allan Gunn have been appointed as Assistant Chief Executives with The Highland Council. Convener of the Council, Cllr Bill Lobban said: "I am delighted to say that Kate Lackie, Malcolm MacLeod and Allan Gunn have been appointed as Assistant Chief Executives with The Highland Council.
As intimated in Highland Council's budget plan, a new senior management structure is to be implemented following approval by Council 14th March. It reconfigures the senior management team into two layers, rather than three and brings Highland Council into line with other benchmarked authorities.
Today, Morrison Construction introduced some of their local apprentices who are working on the UK Governments' Levelling Up Funded refurbishment project at the Northern Meeting Park in Inverness. All these apprentices have been recruited from the Highland area.
The by-election to elect a councillor to represent Ward 19 - Inverness South on The Highland Council has been won by Duncan Cameron McDonald - Independent who was one of the eight candidates who contested the vacancy. Voters in the ward went to the poll yesterday (Thursday 11 April) and the by-election count was held this morning in The Highland Council Headquarters in Inverness.