Internal Audit Report into Caithness Heat and Power

13th January 2010

Caithness Heat and Power is a joint project supported by The Highland Council since its inception in 2004 because of its potential to provide renewable energy in an area of fuel poverty via an innovative biomass district heating system at Pulteneytown, Wick.

The project has, to date, failed to achieve its objective due to problems relating to technology, and an internal audit report by The Highland Council's Head of Audit and Risk Management into the enterprise has highlighted that the Council's and the company's governance arrangements covering the project should have been stronger .

The report, covering the governance activities of the project leading to its inception in 2004 until August 2008 when the Council took over the company, was considered today (Tuesday) at a special meeting of The Highland Council in Inverness, where the Director of Audit (Local Government), Audit Scotland, was also in attendance.

The project was set up in 2004 by the Council, Inver House Distillers Ltd and Pulteneytown Peoples' Project, who each had a director on the board of the company. The Council took over the running of the company in August 2008, when it was clear the project was not achieving its aims of providing heat and power via the biomass boiler or electricity via a gasification plant.

Since taking over the company, the Council has appointed members of the council to the new Board and has considered options for the future operation of the company.

To reflect the financial liabilities of CHaP, the financial statements for the year ended 31 March 2009 include a provision of £6.9 million, which reflected £4 million for financial guarantees in favour of the Clydesdale Bank and £2.9 million for the possible repayment of funding from the Energy Savings Trust if funding conditions are not met.

The council's costs incurred on the project to date are:

sum committed by council in Nov 2005 - £1.600 million

total working capital advances loaned to CHaP to-date - £3.550 million (this could rise to a maximum of £4.970 million as agreed by council)

related in-house development and procurement costs - £300K (maximum agreed by the council)

Potential future costs of the project are uncertain until it is decided how the project is to be taken forward. The Council is in discussion with two bidders, who have shown an interest in taking over the district heating system and the Council is considering detailed solutions, which set out how the bidders would fund, design, install and operate new equipment required to connect into the existing pipe network, which serves 250 homes.

The bids will be evaluated by a Council project team and its advisers. The results of the evaluation will be reported to the Board of Caithness Heat and Power for decision on whether to proceed to invite final tenders. In order to reach that decision the Board will need to agree that the detailed submissions are sufficiently clear and robust to provide confidence that they can deliver the Council's objectives

The Council accepted a number of actions for improvement to ensure better governance in any future venture of this nature.

The findings of the internal audit, which focused on the period covering the governance activities of the project leading to its inception in 2004 until August 2008, include weaknesses in the following areas:

; formal project appraisal, business planning, governance arrangements, and a comprehensive statement of resource implications

technological and financial risk assessments were not adequately undertaken or reported to the council and did not feature in the council's risk register.

The Council noted that the External Auditor, Audit Scotland had been kept fully informed of the problems associated with the ChaP project, which led to the internal audit investigation. In compiling his report, the Head of Internal Audit and Risk Management had liaised with the External Auditor to discuss the report findings and conclusions.

The Council accepted that many improvement actions had already been taken. In addition, the Council accepted a number of further actions for improvement to processes to ensure that failures of the CHaP enterprise are not repeated in any future venture of this nature.

The Highland Council Convener Councillor Sandy Park said: "The internal audit sets out what went wrong and the steps we must take to ensure we never repeat the failure of this enterprise in any future project of this nature. Looking ahead, we hope we can secure a partner to deliver a district heating scheme fuelled by a local renewable source at an affordable price."

 

Related Businesses

 

Related Articles

17/5/2024
Focus On Tourism As Representatives Gather
Yesterday, Thursday 16 May, representatives from the tourism sector in the Highlands gathered in Inverness to take part in a Sustainable Tourism Strategy Workshop hosted by The Highland Council.   The meeting, which was well attended with representatives from across Highland and different interests, follows the launch of the Council's public consultation on its Draft Sustainable Tourism Strategy.  
16/5/2024
Helping Clear School Meal Debt In Scotland
First Minister John Swinney has confirmed the opening of a £1.5 million fund to support councils in removing the impact of school meal debt from families across the country.   Mr Swinney said this commitment will help ensure no child is penalised for struggling to pay for school meals as a result of the cost of living crisis.  
15/5/2024
Highland Council Has The Biggest Budget Gap In Scotland Of All 32 CouncilsThumbnail for article : Highland Council Has The Biggest Budget Gap In Scotland Of All 32 Councils
Todays Audit Scotland report Local government budgets 2024/25 reveals how dire council budgets are.   This makes many more cuts in services likely in coming years.  
3/5/2024
Committee Gives Green Light To Active Travel And Road Safety Work
At the Highland Council Economy and Infrastructure Committee.  (Thursday 2 May 2024) Members had the opportunity to review the work the Council is doing to progress active travel and improve road safety before approving the next steps.  
3/5/2024
Highland Councillors Agree Community Regeneration Support For Communities To Continue
At the meeting of the Economy and Infrastructure Committee members had the opportunity to review the last two years of the Community Regeneration Funding Programme before agreeing changes to how the 2024/25 programme will be delivered.   Committee Chair, Cllr Ken Gowans said: "Following a successful two years, it is a good time to review what has gone well and what can be done better so we can continue to build on success, and seamlessly move the focus onto how best to support the delivery of projects." "With 279 live projects and over £6million of committed funds still to be claimed, there is no doubt as to the value and impact of the programme's potential.  
3/5/2024
Success Of Highland Council's In-house Bus Service Pilot Is HighlightedThumbnail for article : Success Of Highland Council's In-house Bus Service Pilot Is Highlighted
The Highland Council's In-House bus service pilot project was launched in January 2023.   The success of its first year of operation in delivering savings and creating a valued and reliable service was highlighted at today’s Economy and Infrastructure Committee.  
3/5/2024
Economy And Infrastructure Committee Approve Council's Draft Ecology Strategy And Action Plan
Members of Highland Council's Economy and Infrastructure Committee today (2 May 2024) approved the local authority's draft Ecology Strategy and Action Plan which will now move forward to an 12-week public consultation.   The Ecology Strategy sets out an ambitious set of actions to tackle biodiversity loss and address the ecological emergency.  
3/5/2024
Councillors Agree To Utilise UK Shared Prosperity Fund To Support Castle Recruitment & TrainingThumbnail for article : Councillors Agree To Utilise UK Shared Prosperity Fund To Support Castle Recruitment & Training
Economy and Infrastructure Committee members today (2 May 2024) agreed to direct £100K from the Council's share of the UK Shared Prosperity Fund (UKSPF) to fund a new staff training programme at the Inverness Castle Experience.   The funding will enable the project team to provide specialist visitor attraction training to young people identified through partners at Developing the Young Workforce (DYW) and the University of the Highlands and Islands (UHI).  
2/5/2024
Highland Reports Achieving Priorities On Local Housing Strategy
The Housing and Property Committee met on Wednesday 1 May 2024 and noted the Housing Service performance report 2023/24 that met the agreed priorities and associated initiatives in the Local Housing Strategy 2023-2028.   The report highlighted a number of achievements in 2023/24 in increasing housing supply.  
1/5/2024
Highland Council Appoints 3 Assistant Chief ExecutivesThumbnail for article : Highland Council Appoints 3 Assistant Chief Executives
Kate Lackie, Malcolm MacLeod and Allan Gunn have been appointed as Assistant Chief Executives with The Highland Council.   Convener of the Council, Cllr Bill Lobban said: "I am delighted to say that Kate Lackie, Malcolm MacLeod and Allan Gunn have been appointed as Assistant Chief Executives with The Highland Council.