Wick Campus Delay Until 2017
22nd September 2016
At a Wick stakeholders meeting held on Monday 19 September at Wick High School, representatives from Hub North Scotland and Morrison Construction gave an update on reasons for the delay and outlined a revised programme for the Wick campus delivery.
The meeting was chaired by Highland Councillor for Wick Bill Fernie who expressed the Council's disappointment at the delay, and re-stated the Council's priorities to ensure that the flagship facility is completed to the standard expected, and accepting handover only at that point.
Angus MacFarlane, Chief Executive of Hub North Scotland advised the group of a revised handover date for the Campus of Friday 2 December 2016 which remains subject to a number of risks.
He explained that there is a detailed dialogue taking place between Highland Council, Hub North Scotland and Morrison Construction on the revised programme and decant arrangements for Wick High School, Newton Park Primary and High Life Highland community facilities.
The head of Morrisons construction also laid to rest several rumours regarding the construction that there was no sinking/subsidence of any foundations and any broken windows were repaired as required. The faulty steel beam had been replaced. Several people who had been round to see the position were happy with what is going to be provided when the school finally opens.
The Council is working on detailed plans for the school moves with Head Teachers and High Life Highland, and is considering options for the moves either side of the festive period, with anticipated occupation of the new campus in early January, or around the mid-term break in February, with occupation by the end of February. The Council made clear to the Stakeholder Group that the move plans are still being developed and had to be realistic, achievable, and not impact on the learning and teaching of pupils. The Council recognises that pupils and parents will want early notification of when the schools' will commence within the new facility and that will be provided as soon as possible.
Depending on Hub north Scotland and their contractor Morrison Construction handing over the building and the Council accepting it on 2 December, the Council will provide early notification to parents of the expected occupation arrangements.
Ian MacGillivray from the Council's Project Design Unit provided an update on the delayed Safer Routes to Schools elements of work on the approaches to the school. BEAR Scotland will install a new pedestrian crossing on Francis Street and the Council's contractor will carry out work in Seaforth Avenue and Thurso Road - all during October.
There will be a further package of safety improvements next spring after demolition of the existing school is complete. The delay to the Road Traffic Orders for the 20mph zone around Wick Noss school is also being prioritised as a matter of urgency.
Related Businesses
Related Articles
Yesterday, Thursday 16 May, representatives from the tourism sector in the Highlands gathered in Inverness to take part in a Sustainable Tourism Strategy Workshop hosted by The Highland Council. The meeting, which was well attended with representatives from across Highland and different interests, follows the launch of the Council's public consultation on its Draft Sustainable Tourism Strategy.
First Minister John Swinney has confirmed the opening of a £1.5 million fund to support councils in removing the impact of school meal debt from families across the country. Mr Swinney said this commitment will help ensure no child is penalised for struggling to pay for school meals as a result of the cost of living crisis.
Todays Audit Scotland report Local government budgets 2024/25 reveals how dire council budgets are. This makes many more cuts in services likely in coming years.
At the Highland Council Economy and Infrastructure Committee. (Thursday 2 May 2024) Members had the opportunity to review the work the Council is doing to progress active travel and improve road safety before approving the next steps.
At the meeting of the Economy and Infrastructure Committee members had the opportunity to review the last two years of the Community Regeneration Funding Programme before agreeing changes to how the 2024/25 programme will be delivered. Committee Chair, Cllr Ken Gowans said: "Following a successful two years, it is a good time to review what has gone well and what can be done better so we can continue to build on success, and seamlessly move the focus onto how best to support the delivery of projects." "With 279 live projects and over £6million of committed funds still to be claimed, there is no doubt as to the value and impact of the programme's potential.
The Highland Council's In-House bus service pilot project was launched in January 2023. The success of its first year of operation in delivering savings and creating a valued and reliable service was highlighted at today’s Economy and Infrastructure Committee.
Members of Highland Council's Economy and Infrastructure Committee today (2 May 2024) approved the local authority's draft Ecology Strategy and Action Plan which will now move forward to an 12-week public consultation. The Ecology Strategy sets out an ambitious set of actions to tackle biodiversity loss and address the ecological emergency.
Economy and Infrastructure Committee members today (2 May 2024) agreed to direct £100K from the Council's share of the UK Shared Prosperity Fund (UKSPF) to fund a new staff training programme at the Inverness Castle Experience. The funding will enable the project team to provide specialist visitor attraction training to young people identified through partners at Developing the Young Workforce (DYW) and the University of the Highlands and Islands (UHI).
The Housing and Property Committee met on Wednesday 1 May 2024 and noted the Housing Service performance report 2023/24 that met the agreed priorities and associated initiatives in the Local Housing Strategy 2023-2028. The report highlighted a number of achievements in 2023/24 in increasing housing supply.
Kate Lackie, Malcolm MacLeod and Allan Gunn have been appointed as Assistant Chief Executives with The Highland Council. Convener of the Council, Cllr Bill Lobban said: "I am delighted to say that Kate Lackie, Malcolm MacLeod and Allan Gunn have been appointed as Assistant Chief Executives with The Highland Council.