Wick Campus further update
6th February 2017
Highland Council has today confirmed that the planned decant and operational date for the new Wick Campus will be pushed back, with the facilities now to open following the Easter 2017 school holidays.
Having assessed the building following handover by Hub North Scotland and Morrison Construction, the Council has reached the conclusion that the level of snagging and other works still to be completed does not allow it to commence its February decant plan, as had previously been advised to stakeholders.
The Council has always made clear that it would only commence decant from the existing schools and community facilities once it was satisfied as to the standard and completeness of the new facilities.
Over and above general snagging relating to fittings and finish, the particular matters still to be completed include commissioning and balancing of the heating and ventilation system, to resolve hot and cold spots throughout the Campus, completion and commissioning of the swimming pool and leisure facilities, and configuration of the external network connection to enable ICT installation and setup.
The Council can provide assurance regarding the safety of the Campus, and that no safety issues are a factor in the Council's decision to defer operations. The Council has already committed to provide a written response to local stakeholders regarding the facility, and the rigorous inspection regime in place, including independent certification, prior to the facility being handed over.
Related Businesses
Related Articles
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
Households across Scotland have received £4.1 billion in relief since the Council Tax Reduction scheme was introduced in 2013. People on low incomes are eligible for the benefit if they live in Scotland - there is no equivalent in England where most councils require each household to contribute a minimum amount of council tax, irrespective of ability to do so.
The Highland Council is preparing to carry out improvement works in Thurso at Ormlie Road and at The Mall riverside path adjacent to Janet Street. The scope of works on Ormlie Road will include junction improvements between Castlegreen Road and Juniper Drive with new drop kerbs and tactile paving and some surface repairs.
A Highland-wide partnership launched earlier in 2024 to support people on their journey towards, into and within employment is looking forward to a New Year in 2025 full of exciting opportunities designed to help hundreds more people across the Highlands unlock their work potential. Work.
The Highland Council is delighted to share that its Energy Efficient Scotland: Area Based Scheme has won the Outstanding Project Award at the Scottish Green Energy Awards. Described by Scottish Renewables as a "pioneering clean power scheme", this £7 million project demonstrates the incredible impact that can be achieved through combined public and private sector investment.
The ambitious yet focused ‘Highland Investment Plan' is committed to addressing our asset challenges over the next twenty years. By using a place based approach, to ensure a more integrated community offering through the creation of new community facilities.
Applications to the Inverness Winter Payments Scheme, which is fully funded by the Inverness Common Fund, have already been awarded to 1,035 eligible households within the 7 specified Inverness Wards. Leader of Inverness Area, Councillor Ian Brown said: "Since the Scheme was opened to applications for this winter, already £114,885 has been awarded to people who live in the eligible Wards of Aird and Loch Ness, Inverness West, Inverness Central, Inverness Ness-side, Inverness Millburn, Culloden and Ardersier and Inverness South Wards.
The first Highland-wide virtual jobs fair held last month has proved to be a hit with participants and businesses. The week-long virtual event, which was delivered by the Local Employability Partnership for the West - The Highland Council, Skills Development Scotland, Highlands and Islands Enterprise, Department for Work and Pensions, Developing the Young Workforce and UHI North West and Hebrides was timed to coincide with Scottish Careers Week 2024.