Highland Council's proposed capital programme seeks affordable solution to school needs across the Highlands

5th March 2018

The Council's proposed capital programme includes a significant investment of £346m over the next 5 years. This could amount to as much as £481m gross depending on assumptions for grant and funding.

Whilst the level of funding is impressive, the demands on capital investment are equally significant. Highland has 203 schools operational schools, and a large number of those schools have condition, suitability or capacity pressures. As the Council with the largest geographical area in Scotland, there is a hugely diverse range of buildings in terms of size, location, purpose and condition.

The proposed new capital programme is predicated on an annual affordability level of repayment and interest costs of £56.7m which equates to the current budget available for loans charges.

Budget Leader, Councillor Alister Mackinnon said: "The Council's capital programme must always balance competing demands for the resources available. As such, it is not possible to address all needs identified and proposals seek to do the best possible for communities across the Highlands.

"Some projects in the proposed capital programme have project-specific funding associated with them which can only be used for those specific projects.

"The Council must also deliver investment to support expansion in Early Learning and Childcare provision to meet Scottish Government policy. The programme as proposed addresses some of the most urgent of these pressures, where the works can be incorporated and delivered within the required timescale, but in the context of a significantly reduced capital programme, cannot meet all the needs identified.

"Capital spend must be affordable, but we have some of the largest council estate in the UK, with 203 schools as well a huge road infrastructure and other funding needs. We have developed a capital programme which seeks to make the best of the funding available and accept that this will meet only some of the very real need across our communities for school renovations and improvements.

"Our capital programme has been reduced by 50% and we fully recognise that, whatever we do, we cannot meet the demands on every wish list and we have to use recognised criteria to determine where spending should take place.

"Highland is a special case, with our huge geography and significant aging estate and assets. We will be undertaking a major lobbying campaign to bring in additional Scottish Government funding for schools and roads and I will be looking to colleagues across the chamber to support this campaign to make sure Highland gets the investment it needs and deserves."

Councillor Andrew Baxter, Chair of People Committee added:"The number of schools in top condition has risen to 33, compared to 27 in 2016, however, 86 of our schools are currently rated as “poor" condition and 44 are rated as “poor" for suitability.

“To address this, we will be looking at a review of new build techniques that are proven elsewhere for schools and a much greater scrutiny of spend, using the key determinants of Condition, Suitability and Sufficiency for capital investment. We are making a strong and ambitious bid for Scottish Schools for the Future funding for secondary and primary schools and will look at identifying and bidding for other funding sources, including Gaelic funding.

“We have proposed substantial investment in schools in Easter Ross and Inverness, with Alness Academy topping the list at £34m. This is recognising the huge investment which has just gone into schools in Lochaber and Caithness.

“Whilst the criteria and timescales for Schools for the Future funding are not known at this time, we have identified immediate priority schools for such a bid, to include a Tain 3-18 campus; the Nairn and Fortrose secondaries; the schools in Invergordon; Beauly, Broadford, Dunvegan and Tarradale primaries; and the St. Clements special school.

“We also intend to bid into the subsequent Schools for the Future funding, which will include primaries in Alness and Kiltearn.

“There are around 30 primary schools across the Highlands which are either currently, or forecast to be, over capacity over the life of the capital programme so £4.6m has been identified for funding for modular units to meet additional capacity requirements."

The Highland Council has just under £2bn of assets on its balance sheet comprising, amongst other things, 203, over 6,700km of roads and over 2,000 properties.

A key indicator used by councils to assess their borrowing position is to express their annual borrowing costs (loans charges) as a proportion of income from general revenue grants and taxation. For Highland this figure (including borrowing costs associated with PPP schools) stands at over 13%, the fifth highest in Scotland. At a time when the revenue budget is being reduced in real terms, and the Council faces a number of contractual and policy objectives that effectively ring fence a significant proportion of its budget, this situation is not sustainable in the long term.

One of the key determinants for capital investment is the current condition of our schools. The school estate is assessed using guidance from the Scottish Government, particularly in relation to three of the key “Core Facts" (Condition, Suitability and Sufficiency).

For Condition and Suitability, all schools are rated in four overall categories (“A: Good"; “B: Satisfactory"; “C: Poor”; and “D: Bad”). The Condition data can also be used to assess the state of (and to prioritise investment in) separate elements of the building fabric (such as roofs, windows, electrical and heating installations), or individual blocks or buildings within larger school campuses. There is a particular issue with the condition of ageing modular accommodation at a number of our schools.

“It should be noted that Highland has no schools rated as “D: Bad” for either Condition or Suitability and the number of schools rated as “A: Good” for Condition has risen to 33, compared to 27 in 2016. However, 86 (42%) of our schools are rated as “poor” (C category) for condition and 44 schools (89%) are rated as “poor” (C category) for suitability. With regards to Sufficiency, the school roll forecasts are analysed and updated annually to take account of any significant changes.

Leader of the Opposition, SNP Councillor Maxine Smith said,"The Council's Administration is about to cut the capital programme by half, which will severely hamper school building projects. There is no doubt that the programme needed to be changed, as it had turned into a wish list used by the Administration to placate individual group members.

With the Capital Programme now being reduced the Council can no longer look to build its infrastructure projects in the same way as it has always done, therefore it has to look atother methods of construction as per item 10.1 of the Council's capital report for the special meeting. The official Opposition has published a report, which includes an objective look at other models of construction and the reasons why we have to move to these mode's of construction which are cheaper, faster and more reliable as well as easier to maintain in the long run. We have been struggling to get the Council to take this approach seriously.

Councillor Ian Cockburn, the SNP Group's Finance Spokesperson said,"This dated thinking by the Council has to change and change quickly to enable the Council to get more for its £ and the projects it requires to be more quickly constructed, no matter if it is a school or housing. A report on this issue was commissioned for the UK Government in 2016, its title sums up the situation for the building industry, government and Council Procurement of projects, 'Modernise or Die"',

The Highland Council's Capital Programme 2018/19 to 2022/23 will discussed at a meeting of the Council on Wednesday, 7 March 2018 the agenda is online at: https://www.highland.gov.uk/download/meetings/id/73257/item_3_capital_programme_201819_to_202223

 

Related Businesses

 

Related Articles

Yesterday : Local Authority

Britain's Coming Financial Squeeze: Four Questions We Need to Ask Before Spring 2027

There is no shortage of economic forecasts, warnings about inflation, predictions about energy prices and reports about the financial difficulties facing councils and public services.   But what does all this actually mean for ordinary households, and what happens when families can no longer keep up with their bills?.  

22/11/2026 : Local Authority

Scotland's Public Services Face a Financial Squeeze: Are Council and NHS Cuts Now Inevitable?

Scotland's councils and NHS health boards are approaching another difficult round of budget decisions.  Many are already struggling to balance their books, having spent several years absorbing rising costs, increasing demand and funding that has not always kept pace with inflation.  

19/11/2026 : Local Authority

UK Shared Prosperity Fund investment helps grow green skills in the Highlands

Investment through the UK Shared Prosperity Fund is helping UHI Inverness expand access to green skills training and new technologies, supporting the workforce needed for the Highlands' transition to a low carbon economy.   A total of £220,000 of UK Shared Prosperity Fund support has been awarded towards a £234,000 programme, covering three linked projects: green skills training, Solar PV installation, and the purchase of augmented and virtual reality welding equipment.  

17/11/2026 : Local Authority

New Members of the Scottish Youth Parliament elected for Highland

The Scottish Youth Parliament (SYP) has welcomed five new Highland members and one continuing member following the outcome of recent elections.   Members of the Scottish Youth Parliament (MSYP) are elected every two years and become the voice of Scotland's young people.  

16/11/2026 : Advisory / Counseling Services

The People Building Caithness's Future: Meet the Local Entrepreneurs Making Things Happen

When people discuss the future of Caithness, attention often turns to major employers, government investment, renewable energy developments and the search for new industries.   All of these matter.  

16/11/2026 : Local Authority

Caithness Has More to Celebrate Than We Sometimes Realise

Caithness has become accustomed to reading about economic difficulties, declining public services, empty shops, rising costs and the challenges facing rural communities.  These are important issues and should not be ignored.  

16/11/2026 : Local Authority

The Subscription Society: Are Councils and Publicly Funded Charities Charging Us for Too Much?

Councils across Scotland are under considerable financial pressure.  Rising wages, energy bills, borrowing costs and increasing demand for essential services are leaving local authorities searching for ways to balance their budgets.  

15/11/2026 : Local Authority

Caithness: Are We Becoming Britain's Energy Storage Capital?

Caithness has long been associated with energy production.  From the nuclear industry at Dounreay to the development of onshore wind farms, the area has played an important role in Britain's changing energy requirements.  

15/11/2026 : Local Authority

Highland Rangers Do Valuable Work, But Is a Paid Newsletter the Best Use of Their Time?

Highland's Countryside Ranger Service performs an important role in protecting the natural environment, helping people understand local wildlife and encouraging greater appreciation of the countryside.  Its work with schools, communities, visitors and landowners is valuable, and at a time when environmental pressures are increasing, the contribution of Rangers should not be underestimated.  

15/11/2026 : Local Authority

Caithness at a Crossroads: Investment Opportunities Grow, But Are Essential Services Keeping Pace?

Caithness finds itself in an interesting position.  There are opportunities emerging across energy, infrastructure, harbour development, education and construction.