Alternative Waste Route Found For Dounreay's Bulk Metal Items
11th May 2022
Two large redundant items that were removed from Dounreay's facilities have now left the site for disposal or diversion, opening up new waste routes.
Dounreay in partnership with Nuclear Waste Services and its contractor Cyclife first trialled an alternative treatment option for the site's metallic waste in 2019, when 66 tonnes of redundant metal equipment were sent to Cyclife's specialist facility for recycling.
Following this successful trial, a flask adaptor plug weighing 10 tonnes recently left site for the recycling facility.
DSRL Assistant Project Manager Catherine Strathdee said, "Now that this route is available to us, we will use it regularly to recycle large items that are too large to fit inside standard waste containers.
Cyclife Managing Director Joe Robinson said, "Cyclife is delighted to have supported DSRL and Nuclear Waste Services over the last 3 years to enable the DSRL mission. The project team has developed a strong integrated and collaborative working environment, which has contributed to the success of the project.
Dounreay is also trialling other waste routes that are available when recycling is not feasible. This includes disposal of a redundant supercompactor unit, removed from a waste facility in 2011, which has now been successfully transported offsite for disposal in a suitable licensed landfill site in England.
This is a new offsite disposal option that will enable Dounreay to dispose of items with low specific activity that are not suitable for recycling due to the presence of other hazardous substances or disposal within the low-level waste vaults. To make this happen, Dounreay has collaborated with Nuclear Waste Services, Cyclife UK Ltd, a strategic waste partner and Augean, the landfill owner.
These new waste routes will minimise the number of low-level waste vaults that the site will need as it is decommissioned.
DSRL Head of Waste Operations, Alistair Ross, said, "Off-site diversion and disposal options for our waste are key to the successful decommissioning of the Dounreay site. These ensure that the waste is disposed of or recycled through the most appropriate route that provides safe, compliant disposition coupled with value for money and offers decommissioning projects alternatives to disposal to the low-level waste vaults or interim storage."
Related Businesses
Related Articles
The NDA has published its strategy for consultation, setting out the roadmap to decommission the UK's earliest nuclear sites safely, securely and sustainably. Today, the Nuclear Decommissioning Authority (NDA) has published its revised strategy for public consultation, setting out a clear roadmap for one of the UK's most complex long-term environmental challenges.
A Pictish stone believed to date back 1,700 years has been retrieved and preserved for future generations with financial help from Dounreay's operators. Dounreay isn't the only site in Caithness where relics of the past are being retrieved and made safe for the future.
NDA announces Catriona Schmolke CBE FREng and Dr Neil Bruce OBE CEng as NDA Board members. The Nuclear Decommissioning Authority (NDA) has announced that Catriona Schmolke CBE FREng and Dr Neil Bruce OBE CEng have been appointed to the NDA Board as Non-Executive Board members.
NRS Dounreay has been awarded Gold status for skills and training for the fourth consecutive year by the Engineering Construction Industry Training Board. The engineering construction industry values its members, who design, construct, maintain, renew and dismantle the UK's strategically important industrial infrastructure.
Research offers a positive outlook for communities impacted by the decommissioning process. A new study has revealed that Scotland's £25 billion nuclear decommissioning programme could deliver significant long-term economic and social benefits at both national and local levels over the next 90 years and beyond.
One of the most challenging puzzles in the UK's nuclear clean-up programme is being solved. Waste is now being routinely retrieved from one of the world's oldest nuclear waste stores for the first time in its history.
The Nuclear Decommissioning Authority (NDA) group played a pivotal role in defueling Hunterston B on time and on budget. On 24 April 2025 EDF announced Hunterston B nuclear power station has been successfully defueled on time and on budget, in less than three years, following rigorous checks by the Office for Nuclear Regulation (ONR).
Spot, the robot "dog," recently assisted colleagues in Dounreay's Fuel Cycle Area by reactivating a crucial building crane in a reprocessing plant. The crane had been deactivated at the switchboard in 2023 due to concerns about the ageing asset.
The Nuclear Decommissioning Authority has announced it's establishing a Plutonium Ceramics Academic Hub with the Universities of Manchester and Sheffield. The Nuclear Decommissioning Authority (NDA) has announced it's establishing a Plutonium Ceramics Academic Hub with the Universities of Manchester and Sheffield.
One of Britain's most complex environmental restoration projects is taking on 23 new apprentices. The decommissioning of the former centre of fast reactor research and development at Dounreay is continuing to create long-term opportunities for young people.