Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider  

 

Dounreay Has Successfully Joined With Magnox Limited

3rd April 2023

Photograph of Dounreay Has Successfully Joined With Magnox Limited

Dounreay has successfully joined with Magnox Limited, effective as of April 1st 2023.

This joining is part of the NDA group's wider programme of change.

First bringing together the organisations involved in delivering its decommissioning mission into one group, and then strengthening and simplifying the operating model around four operating companies: Magnox and Dounreay; Sellafield; Nuclear Transport Solutions and Nuclear Waste Services.

As part of the new arrangements, the Nuclear Site Licence for Dounreay is now held by the Magnox Limited Board. There will be no fundamental change to the current work programmes at the Magnox sites or Dounreay. The focus remains on decommissioning the sites safely, securely and cost-effectively.

Magnox Sites
Magnox is responsible for defuelling and decommissioning 12 nuclear sites and operating one hydro-electric plant in the UK.

Magnox is licensed under the Nuclear Installations Act 1965 as the legal entity responsible for the following sites, which are owned by the Nuclear Decommissioning Authority.

Berkeley Site
Berkeley Site is located on a 27 hectare site of special scientific interest on the bank of the River Severn in Gloucestershire. The site generated 43 terawatt hours of electricity during its 27 years of operation and shut-down in 1989. Berkeley is in its decommissioning phase and has completed a number of key activities, including disposing of its 310 tonne boilers and entering both reactors into a safestore state. Priorities for the site now include removing all legacy wastes and emptying the active waste vaults.

Bradwell Site
Bradwell Site is located on a 30 hectare site close to the Essex coastline. The site generated 60 terawatt hours of electricity during its 40 years of operation and shut-down in 2002.
Bradwell is following an accelerated decommissioning programme, due for completion late in 2018. This will see it become the first reactor site in the UK to enter the care and maintenance phase. The majority of decommissioning activities are now complete, including the conditioning of all intermediate level waste. The final projects to be completed include cladding reactor two and installing a pond and vaults over clad building.

Chapelcross Site
Chapelcross Site is located on the 92 hectare site of an old airfield in Dumfriesshire. The site stopped operating in 2004 after generating more than 60 terawatt hours of electricity over 45 years. The site completed defuelling ahead of schedule and is now in its decommissioning phase. Priorities including the design, installation and commissioning of plant and equipment to safely recover intermediate level waste from buildings and the former cooling ponds.

Dungeness A Site
Dungeness A Site is located on a 22 hectare site of special scientific interest on the Kent coast. The site stopped generating electricity in 2006 with a lifetime output of 120 terawatt hours. The site is now in its decommissioning phase and is making steady progress, including demolishing its turbine hall and decontaminating its ponds. Priorities for the site now include draining reactor one pond, resin retrieval and packaging.

Harwell Site
Harwell Site is located on a 102 hectare site in Oxfordshire and is the birthplace of the UK nuclear industry. Originally an RAF station, it became Britain's Atomic Energy Research Establishment in 1946. There were 14 experimental reactors on the site over its lifetime, with just three remaining to be decommissioned. Significant progress is being made in decommissioning the site, with waste being treated, sorted and disposed of and the construction of a new intermediate level waste store.

Hinkley Point A Site
Hinkley Point A Site is located on a 19 hectare site on the Somerset coast. It is a twin reactor site which stopped generating electricity in 2000 having completed 35 years of operation, generating 103 terawatt hours. Hinkley Point A Site is now being decommissioned and its focus is on the safe and secure retrieval, packaging and storing of its legacy waste. Priorities for the site include completing the build and commissioning of the intermediate level waste store and installing the modular active effluent treatment plant.

Hunterston A Site
Hunterston A Site is located on a 36 hectare site on the Ayrshire coast. The twin reactor site stopped generating electricity in 1989 after producing 73 terawatt hours. Hunterston is part way through its decommissioning phase, with the current focus on recovery of intermediate level waste from various facilities and final decommissioning of the cartridge cooling ponds, which have already been drained of water.

Oldbury Site
Oldbury Site is located on a 39 hectare site on the bank of the River Severn in South Gloucestershire. It stopped generating in February 2012 after 44 years, generating 137.5 terrawatt hours of electricity.
The site completed defuelling in 2016 and moved into its decommissioning phase. Progress has been made in the former cooling ponds and an alternative electrical supply has been installed on the site, allowing disconnection from the national grid. Priorities are completion of ponds decommissioning work and retrieving, packaging and conditioning other forms of radioactive waste on site. Conventional demolition work will also begin to reduce the footprint of the site.

Sizewell A Site
Sizewell A Site is located on a 10 hectare site in Suffolk. The site generated 110 terawatt hours of electricity during its 40 years of operation and shut-down in 2006. The site is in its decommissioning phase and the focus is now firmly on waste management and hazard reduction, with the cooling ponds the current priority. Two major projects to accelerate demolition work have been completed, removing the cooling water crane and the two off-shore structures. Building demolition continues with a number of facilities being dismantled and cleared, including the administration building, engineering building and C02 plant. The demolition of the National Grid sub-station has been completed.

Trawsfynydd Site
Trawsfynydd Site is located on a 15 hectare site in Snowdonia National Park, Gwynedd. It drew cooling water from Llyn Trawsfynydd, which was formed in 1928 to retain water for Maentwrog Hydroelectric Station. Trawsfynydd generated 69 terawatt hours of electricity during 26 years of operation and shut-down in 1993. The site is decommissioning and key successes include bulk asbestos removal and storage of all solid intermediate level waste, resins and liquid in the interim storage facility. Site infrastructure has been upgraded, redundant buildings demolished and the reactor safestores are being reconfigured in preparation for a major project to reduce their height by around two thirds.

Winfrith Site
Winfrith Site is located on a 129 hectare site in Dorset. It was constructed in the 1950s to enable vital research into reactor design. The site housed nine experimental reactors at various times with only two remaining today, both of which are being decommissioned. Fifty hectares of the site was transferred to different ownership in 2003 following its decommissioning and progress since has seen the skyline change dramatically. Ponds have been emptied, bulk asbestos removed and waste sorted. Winfrith is working towards reaching its interim end state, at which point the land will be returned to heathland with public access.

Wylfa Site
Wylfa Site is located on a 20 hectare site on the north coast of Anglesey. It was the last and biggest of the Magnox stations to be built. It was shut down in 2015 having completed almost 45 years of operation, generating a total of 232 terawatt hours of electricity. The site has now been defuelled and a remediation project is underway to remove and clean asbestos from areas within the reactor buildings and turbine hall.
Wylfa is also responsible for the Maentwrog hydroelectric station near Blaenau Ffestiniog, Gwynedd, which continues to generate electricity.

Nuclear Decommissioning Authority

Dounreay Site Restoration Ltd (DSRL) and LLW Repository Ltd (LLWR) became wholly owned subsidiaries of the NDA in 2021.

 

Related Businesses

 

Related Articles

NDA Group Establishes Innovative Partnership To Manage Asbestos Waste At Legacy Nuclear SitesThumbnail for article : NDA Group Establishes Innovative Partnership To Manage Asbestos Waste At Legacy Nuclear Sites
The Nuclear Decommissioning Authority (NDA), in collaboration with its subsidiary Nuclear Waste Services (NWS), has awarded two contracts to establish an innovative partnership for the enhanced management of asbestos waste.   The Asbestos Innovation Partnership (AIP) will work with the NDA, NWS and the supply chain, to test and develop new solutions to treat asbestos waste, helping to deliver efficiencies and enable more effective waste management.  
Dounreay Workers Vote To Strike Over PayThumbnail for article : Dounreay Workers Vote To Strike Over Pay
Workers at the Dounreay nuclear power complex in Caithness have voted to strike in a dispute over pay.   The GMB union said its ballot had an 85% turnout.  
Great British Nuclear To Buy Two Hitachi Sites For New Nuclear DevelopmentThumbnail for article : Great British Nuclear To Buy Two Hitachi Sites For New Nuclear Development
Land is to be acquired by government to underpin nuclear revival.   In a historic day for the UK's energy security, Great British Nuclear (GBN) is buying land for new nuclear development from Hitachi at both Wylfa in Ynys Môn/Anglesey and Oldbury-on-Severn in Gloucestershire.  
Gad Develops Bespoke Benefits Modeller As Nuclear Decommissioning Authority Reforms Pension BenefitsThumbnail for article : Gad Develops Bespoke Benefits Modeller As Nuclear Decommissioning Authority Reforms Pension Benefits
GAD has built a pension benefit modeller to support the Nuclear Decommissioning Authority as it undertakes a pension reform programme.   The Government Actuary's Department (GAD) has supported the Nuclear Decommissioning Authority (NDA) as it undertakes a pension reform programme.  
North Highlands Team Headed For International Robot ChallengeThumbnail for article : North Highlands Team Headed For International Robot Challenge
NRS Dounreay and socio economic partners hosted the second FIRST® LEGO® League Challenge North Highland Tournament in March with local schools taking part.   The North Highland tournament took place in March at ETEC on the University of the Highlands and Islands (UHI) North West and Hebrides Thurso Campus.  
Dounreay Power Station Faces Threat Of Strike ActionThumbnail for article : Dounreay Power Station Faces Threat Of Strike Action
Unite the union confirmed around 450 of its members employed by Magnox Limited based at Dounreay power station are being balloted for strike action in a pay dispute.   The ballot which is now open will close on 2 April.  
NDA Group Hosts First Ever Large-scale Graduate Recruitment EventThumbnail for article : NDA Group Hosts First Ever Large-scale Graduate Recruitment Event
This week, the NDA group hosted it's first ever large-scale graduate recruitment event in Manchester, with over 600 candidates in attendance.   The Nuclear Decommissioning Authority (NDA) group held its first ever large-scale graduate recruitment event in Manchester this week, bringing together more than 600 candidates as it looks to double the number of opportunities across its graduate schemes this year.  
Nuclear Decommissioning Authority - Draft Business Plan 2024 To 2027 For ConsultationThumbnail for article : Nuclear Decommissioning Authority - Draft Business Plan 2024 To 2027 For Consultation
The NDA Draft Business Plan sets out key activities and expected progress for all 17 of the NDA's nuclear sites over the next 3 years.  We want to hear from anyone who has a comment on any aspect of this document.  
Learn And Earn - Apprentice Recruitment Open - Nuclear Waste Services - Dounreay EtcThumbnail for article : Learn And Earn - Apprentice Recruitment Open - Nuclear Waste Services - Dounreay Etc
NRS is delighted to announce that we are recruiting over 30 level 2 - 6 engineering and business apprentices to deliver our decommissioning mission.   John Vickerman, Chief People Officer, commented: "NRS is an exciting place to be.  
NDA Reaffirms Cooperation With Korea Radioactive Waste AgencyThumbnail for article : NDA Reaffirms Cooperation With Korea Radioactive Waste Agency
Leaders from the UK's Nuclear Decommissioning Authority (NDA), and the Korea Radioactive Waste Agency (KORAD) signed their second cooperation statement.   Yesterday, Monday 20 November 2023, leaders from the UK's Nuclear Decommissioning Authority (NDA), and the Korea Radioactive Waste Agency (KORAD) reaffirmed their commitment to share their knowledge, experience and technology in relation to the management of radioactive waste.