Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider  

 

Dounreay Has Successfully Joined With Magnox Limited

3rd April 2023

Photograph of Dounreay Has Successfully Joined With Magnox Limited

Dounreay has successfully joined with Magnox Limited, effective as of April 1st 2023.

This joining is part of the NDA group's wider programme of change.

First bringing together the organisations involved in delivering its decommissioning mission into one group, and then strengthening and simplifying the operating model around four operating companies: Magnox and Dounreay; Sellafield; Nuclear Transport Solutions and Nuclear Waste Services.

As part of the new arrangements, the Nuclear Site Licence for Dounreay is now held by the Magnox Limited Board. There will be no fundamental change to the current work programmes at the Magnox sites or Dounreay. The focus remains on decommissioning the sites safely, securely and cost-effectively.

Magnox Sites
Magnox is responsible for defuelling and decommissioning 12 nuclear sites and operating one hydro-electric plant in the UK.

Magnox is licensed under the Nuclear Installations Act 1965 as the legal entity responsible for the following sites, which are owned by the Nuclear Decommissioning Authority.

Berkeley Site
Berkeley Site is located on a 27 hectare site of special scientific interest on the bank of the River Severn in Gloucestershire. The site generated 43 terawatt hours of electricity during its 27 years of operation and shut-down in 1989. Berkeley is in its decommissioning phase and has completed a number of key activities, including disposing of its 310 tonne boilers and entering both reactors into a safestore state. Priorities for the site now include removing all legacy wastes and emptying the active waste vaults.

Bradwell Site
Bradwell Site is located on a 30 hectare site close to the Essex coastline. The site generated 60 terawatt hours of electricity during its 40 years of operation and shut-down in 2002.
Bradwell is following an accelerated decommissioning programme, due for completion late in 2018. This will see it become the first reactor site in the UK to enter the care and maintenance phase. The majority of decommissioning activities are now complete, including the conditioning of all intermediate level waste. The final projects to be completed include cladding reactor two and installing a pond and vaults over clad building.

Chapelcross Site
Chapelcross Site is located on the 92 hectare site of an old airfield in Dumfriesshire. The site stopped operating in 2004 after generating more than 60 terawatt hours of electricity over 45 years. The site completed defuelling ahead of schedule and is now in its decommissioning phase. Priorities including the design, installation and commissioning of plant and equipment to safely recover intermediate level waste from buildings and the former cooling ponds.

Dungeness A Site
Dungeness A Site is located on a 22 hectare site of special scientific interest on the Kent coast. The site stopped generating electricity in 2006 with a lifetime output of 120 terawatt hours. The site is now in its decommissioning phase and is making steady progress, including demolishing its turbine hall and decontaminating its ponds. Priorities for the site now include draining reactor one pond, resin retrieval and packaging.

Harwell Site
Harwell Site is located on a 102 hectare site in Oxfordshire and is the birthplace of the UK nuclear industry. Originally an RAF station, it became Britain's Atomic Energy Research Establishment in 1946. There were 14 experimental reactors on the site over its lifetime, with just three remaining to be decommissioned. Significant progress is being made in decommissioning the site, with waste being treated, sorted and disposed of and the construction of a new intermediate level waste store.

Hinkley Point A Site
Hinkley Point A Site is located on a 19 hectare site on the Somerset coast. It is a twin reactor site which stopped generating electricity in 2000 having completed 35 years of operation, generating 103 terawatt hours. Hinkley Point A Site is now being decommissioned and its focus is on the safe and secure retrieval, packaging and storing of its legacy waste. Priorities for the site include completing the build and commissioning of the intermediate level waste store and installing the modular active effluent treatment plant.

Hunterston A Site
Hunterston A Site is located on a 36 hectare site on the Ayrshire coast. The twin reactor site stopped generating electricity in 1989 after producing 73 terawatt hours. Hunterston is part way through its decommissioning phase, with the current focus on recovery of intermediate level waste from various facilities and final decommissioning of the cartridge cooling ponds, which have already been drained of water.

Oldbury Site
Oldbury Site is located on a 39 hectare site on the bank of the River Severn in South Gloucestershire. It stopped generating in February 2012 after 44 years, generating 137.5 terrawatt hours of electricity.
The site completed defuelling in 2016 and moved into its decommissioning phase. Progress has been made in the former cooling ponds and an alternative electrical supply has been installed on the site, allowing disconnection from the national grid. Priorities are completion of ponds decommissioning work and retrieving, packaging and conditioning other forms of radioactive waste on site. Conventional demolition work will also begin to reduce the footprint of the site.

Sizewell A Site
Sizewell A Site is located on a 10 hectare site in Suffolk. The site generated 110 terawatt hours of electricity during its 40 years of operation and shut-down in 2006. The site is in its decommissioning phase and the focus is now firmly on waste management and hazard reduction, with the cooling ponds the current priority. Two major projects to accelerate demolition work have been completed, removing the cooling water crane and the two off-shore structures. Building demolition continues with a number of facilities being dismantled and cleared, including the administration building, engineering building and C02 plant. The demolition of the National Grid sub-station has been completed.

Trawsfynydd Site
Trawsfynydd Site is located on a 15 hectare site in Snowdonia National Park, Gwynedd. It drew cooling water from Llyn Trawsfynydd, which was formed in 1928 to retain water for Maentwrog Hydroelectric Station. Trawsfynydd generated 69 terawatt hours of electricity during 26 years of operation and shut-down in 1993. The site is decommissioning and key successes include bulk asbestos removal and storage of all solid intermediate level waste, resins and liquid in the interim storage facility. Site infrastructure has been upgraded, redundant buildings demolished and the reactor safestores are being reconfigured in preparation for a major project to reduce their height by around two thirds.

Winfrith Site
Winfrith Site is located on a 129 hectare site in Dorset. It was constructed in the 1950s to enable vital research into reactor design. The site housed nine experimental reactors at various times with only two remaining today, both of which are being decommissioned. Fifty hectares of the site was transferred to different ownership in 2003 following its decommissioning and progress since has seen the skyline change dramatically. Ponds have been emptied, bulk asbestos removed and waste sorted. Winfrith is working towards reaching its interim end state, at which point the land will be returned to heathland with public access.

Wylfa Site
Wylfa Site is located on a 20 hectare site on the north coast of Anglesey. It was the last and biggest of the Magnox stations to be built. It was shut down in 2015 having completed almost 45 years of operation, generating a total of 232 terawatt hours of electricity. The site has now been defuelled and a remediation project is underway to remove and clean asbestos from areas within the reactor buildings and turbine hall.
Wylfa is also responsible for the Maentwrog hydroelectric station near Blaenau Ffestiniog, Gwynedd, which continues to generate electricity.

Nuclear Decommissioning Authority

Dounreay Site Restoration Ltd (DSRL) and LLW Repository Ltd (LLWR) became wholly owned subsidiaries of the NDA in 2021.

 

Related Businesses

 

Related Articles

Nuclear Restoration Services Has Appointed Dave Wilson As Managing Director Of Its Dounreay DivisionThumbnail for article : Nuclear Restoration Services Has Appointed Dave Wilson As Managing Director Of Its Dounreay Division
He joins from AtkinsRealis, where he was market director and delivery lead for its nuclear decommissioning and waste services business, and officially takes up the post today (18 November 2024), He succeeds John Grierson who has served as interim MD since May.   NRS CEO Rob Fletcher said, "I am very pleased that Dave Wilson has agreed to join the team at Dounreay.  
NDA Supply Chain Award Winners 2024 Revealed
The Nuclear Decommissioning Authority group have announced five organisations as winners of this year's supply chain awards.   Morgan Sindall Infrastructure, The Decommissioning Delivery Partnership, PA Consulting, Antech and The Higher Activity Waste Thermal Treatment Tranche 1 Team are the big winners in this year's supply chain awards.  
UKAEA Monthly Newsletter Latest EditionThumbnail for article : UKAEA Monthly Newsletter Latest Edition
Find out what has been happening at UKAEA in our monthly newsletter.  Read about our recent activities and upcoming events.  
My Experience On The Commissioning Graduate Programme At Sellafield Ltd
With a degree in electrical and electronic engineering and a keen interest in the nuclear sector, Anouschka knew Sellafield would be the best place for her to begin her career in the industry.   That career has already seen her relocate from Sheffield to Cumbria and scooping the title of Sellafield Ltd Graduate of the Year.  
Sellafield Ltd Welcomes Its Largest Ever Graduate CohortThumbnail for article : Sellafield Ltd Welcomes Its Largest Ever Graduate Cohort
More than 140 graduates have started at Sellafield Ltd.   Over 140 graduates have just started their exciting careers with the company in a range of business and technical disciplines, supporting Sellafield Ltd in its mission to create a clean and safe environment for future generations.  
UKAEA Newsletter - Edition 11 Published TodayThumbnail for article : UKAEA Newsletter - Edition 11 Published Today
Find out what has been happening at UKAEA in our monthly newsletter.  Read about our recent activities and upcoming events.  
NDA Group Investing In Our CommunitiesThumbnail for article : NDA Group Investing In Our Communities
The Nuclear Decommissioning Authority (NDA) group has on 26 September 2024 published its 2023 to 2024 socio-economic report detailing a record investment in projects across the UK.   Over the last five years, the NDA group has invested £60 million in projects that enable permanent and sustainable change in its site communities, leveraging many millions more from partners.  
What Is Thorp? - Thermal Oxide Reprocessing PlantThumbnail for article : What Is Thorp? - Thermal Oxide Reprocessing Plant
Today, the ponds inside the Thermal Oxide Reprocessing Plant (or as we like to call it, Thorp) are used to store nuclear fuel that has been used in the UK's 7 operational nuclear reactors.   Before taking on this new mission, Thorp reprocessed 9,000 tonnes of used nuclear fuel from around the world, generating an estimated £9 billion in revenue for the UK over 2 decades.  
Record Numbers Join The NDA Group Graduate ProgrammeThumbnail for article : Record Numbers Join The NDA Group Graduate Programme
Over 100 graduates join the Nuclear Decommissioning Authority group today as applications open for 2025.   As applications open for 2025, the Nuclear Decommissioning Authority (NDA) group also welcomed its largest ever cohort of graduates today, with more than 100 new recruits ready to support delivery of one of the world's most important environmental programmes.  
Autonomous Robot Paves The Way For Future Fusion MaintenanceThumbnail for article : Autonomous Robot Paves The Way For Future Fusion Maintenance
In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility.   In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility.