Meygen Tidal Project - Navigation & Fisheries

11th December 2011

Photograph of Meygen Tidal Project - Navigation & Fisheries

Information from the Meygen materials supplied at the public meetings in December 2011. The full pubicatiosn are online at www.meygen.com.

Navigation
The 86 turbines are fully submerged and will have a minimum under-keel
clearance of 8m to Lowest Astronomical Tide (LAT).
Data collected on users of the Inner Sound found 3 distinct groups:
1) The Pentland Ferry - operating a service from Gills Bay to St Margaret's
Hope, running north to south either side of the Stroma depending on
the local conditions
2) Transiting vessels - going east/west. These are generally i shing vessels
with draughts between 3 and 8m
3) Local creel boats working and transiting the area.

Navigation Risk Assessment
A Navigation Risk Assessment was carried out to quantify the risks associated
to vessels from the Project, now and on future predicted levels of traffic:
The key impacts identified were:
1) Drifting/Powered collision with installation vessel during construction phase
2) Displacement of vessels during construction phase (including safety zones for installation vessels)
3) Drifting/Powered collision risk with operating turbines
4) Increase in vessel-to-vessel collision risk due to re-routeing

Installation and maintenance vessels -
Work vessels and their associated safety could severely restrict the sea room available to vessels transiting east-west through the Inner Sound if a standard 500m zone is used. However, MeyGen seeks only to establish the minimum safety zone required to ensure the safety of working vessels and allow suitable sea room for transiting and working vessels. MeyGen will continue consultation with the MCA, DECC, the appointed contractor and local stakeholders on this matter.

Turbine Collision
For shallow-deep draught vessels, the risk of collision with turbines is assessed to be low. This assumes industry good practice will be applied to minimise this impact, including correct charting and publication of turbines and liaison with local stakeholders.

Fisheries
From the i shing vessel tracks recorded during the combined AIS survey period (16 weeks from 2010 to 11), 37 vessels used the Inner Sound and 96 used the Outer Sound. All were transiting as opposed to i shing. Coni rmed by analysis of VMS data and sightings data from over-l ights and Royal Navy patrols. All the sources agreed that vessels tended to transit the Inner Sound as opposed to i shing, and that the vast majority were UK-registered.

From the local consultation, three John O'Groats based skippers were identified to fish in the Inner Sound. The creel boats they use are less than 12m in length and have draughts up to about 1.5m. These local vessels use creels to catch lobsters, brown crabs and velvet crabs. They also fish areas to the west, around Stroma and further east. The centre of the Inner Sound where the Project area is located is mostly fished in spring/summer and mainly for lobster. However, fishing is limited as it requires a combination of neap tides and good weather, due to the time it takes to deploy and haul creels between tides.

Fisheries impacts
Throughout the Project life-cycle there is likely to be some exclusion to the local fishing fleet, including displacement from a small percentage of the local fishing grounds and access restrictions during installation and maintenance operations. However, such impacts will be of a temporary nature and will only affect a small number of fishing vessels.

For more about the project and MeyGen go to www.meygen.com

 

Related Businesses

 

Related Articles

10/12/2014
MeyGen Public Open Days, 16th - 17th December 2014Thumbnail for article : MeyGen Public Open Days, 16th - 17th December 2014
It is MeyGen's intention to start onshore construction at Ness of Quoys near to the village of Mey early next year and they are planning on holding two open days next week in order to assist with any questions about the works and the project in general.   Members of the MeyGen team will be on hand between 11am - 9pm on Tuesday 16th December at Mey Hall and 11am - 9pm on Wednesday 17th December at Caithness Horizons.  
11/11/2014
ANDRITZ to supply tidal current turbines to MeyGenThumbnail for article : ANDRITZ to supply tidal current turbines to MeyGen
ANDRITZ HYDRO Hammerfest, part of international technology Group ANDRITZ, has received an order from MeyGen Ltd.  to supply three 1.5-megawatt tidal current turbines to the planned tidal array in the Inner Sound of the Pentland Firth, Scotland.  
6/11/2014
World's largest tidal array development wins prestigious international AwardThumbnail for article : World's largest tidal array development wins prestigious international Award
The UK's 'MeyGen Project' awarded the ICOE's inaugural 'Navigator Award'.   5th November 2014: Last night, the 398MW MeyGen project was awarded the first ever 'Navigator Award' at the International Conference on Ocean Energy (ICOE), in recognition of the project's significant contribution to the global marine renewable industry.  
20/10/2014
Mojo Maritime and James Fisher Marine Services Ready For Meygen's Inner Sound Tidal ProjectThumbnail for article : Mojo Maritime and James Fisher Marine Services Ready For Meygen's Inner Sound Tidal Project
Mojo Maritime has signed a contract with James Fisher Marine Services (JFMS) which will see them provide significant marine operational and engineering expertise to the construction phase of the MeyGen Inner Sound tidal project.   Over the next two years, Mojo will work closely with JFMS carrying out the detailed design, planning and execution of the subsea cable, foundation and turbine installation.  
20/10/2014
Meygen Returns To Caithness To Update Locals On Progress
MeyGen Ltd's Chief Executive Officer Mr Dan Pearson to speak in public about progress with its Marine Power Station on 22nd October 2014.   Mr Dan Pearson, the Chief Executive Officer of MeyGen Ltd, is to address folk in North East Caithness from the platform at Mey Village Hall, in NE Caithness, on the evening of Wednesday October 22nd at 7:30 pm.  
24/10/2013
MeyGen Surveys UnderwayThumbnail for article : MeyGen Surveys Underway
In recent weeks members of the Caithness public may have noticed some activity by MeyGen Ltd.  around the Pentland Firth Inner Sound and at Ness of Quoys.  
23/9/2013
Meygen Set To Go On Pentland Firth Tidal ProjectThumbnail for article : Meygen Set To Go On Pentland Firth Tidal Project
Up to six turbines will be initially placed in the Inner Sound of the Pentland Firth off the north coast of Caithness, Scotland, the first phase of what developers hope will be a much larger project.   MeyGen Ltd.  
11/12/2011
Meygen Tidal Energy Project - MapThumbnail for article : Meygen Tidal Energy Project - Map
This map shows the area of the first phase of 86 turbines and the lines for the cables.   For more about the project and MeyGen got to www.meygen.com.  
11/12/2011
Meygen Driving Forward With Pentland Energy ProjectThumbnail for article : Meygen Driving Forward With Pentland Energy Project
One of the first companies to get going with their plans to extract the huge energy potential form the Pentland Firth is Meygen.   Their plans were unveiled to Caithness people at Mey Hall a few days ago.  
26/10/2010
MeyGen named as successful bidder for Pentland Firth "Crown Jewel" siteThumbnail for article :  MeyGen named as successful bidder for Pentland Firth "Crown Jewel" site
MeyGen today announces entry into an 'Agreement for Lease' with The Crown Estate for the Pentland Firth Inner Sound tidal power site.   MeyGen is a joint venture between independent power generator International Power plc (45%), investment bank Morgan Stanley (45%), and tidal technology provider Atlantis Resources Corporation (10%), dedicated to developing the Inner Sound tidal site.