Year of progress in nuclear clean-up

23rd June 2013

Photograph of Year of progress in nuclear clean-up

Crucial milestones were achieved in the clean-up of the UK's nuclear legacy last year, the Nuclear Decommissioning Authority (NDA) has revealed in its annual report and accounts.

Progress was generally good across the NDA's 19 licensed sites, with achievements during 2012/13 including:.

completion of defueling at Chapelcross and Dungeness A, removing 99% of radioactivity from those sites

agreement of a plan to bring forward the closure of Winfrith and Harwell research sites by a combined 32 years, with potential cost savings of �500 million

integration of a new contract at Dounreay, expected to save taxpayers �1bn and bring forward closure by 17 years

higher than expected commercial income of almost �900m, aided by extended generation at Wylfa and land sale at Capenhurst worth �50m

progress on a �7 billion competition to run 12 sites

largest ever programme of work in decommissioning programme for 10 Magnox sites
completion of first five years under private control for the Low Level Repository in Cumbria, which has so far saved taxpayers �30m

strong industrial safety performance at Sellafield whilst delivering three key projects to enable future retrieval of radioactive waste from legacy storage facilities

successful completion of the third shipment of vitrified highly active waste to Japan

NDA chief executive John Clarke, who has completed his first full year in charge of the authority, said:"Sellafield remains our top priority. It is the world's most complex nuclear site with unprecedented challenges. Against this background, performance in the year has been mixed with some notable milestones achieved on legacy ponds and silos balanced by some disappointing project cost increases and schedule slippages together with operational performance impacted by unreliable plant.

"I'm pleased to note good performance elsewhere in the estate, particularly across the Magnox sites which has this year delivered its largest-ever programme of work. We look forward to seeing Bradwell and Traswfynydd becoming the first UK nuclear sites to enter the care and maintenance phase within the next two to three years.

"At Research Sites Restoration Ltd, an optimised plan will bring forward closure of Winfrith by 27 years and take Harwell to care and maintenance five years earlier than originally planned, with the potential to save �500 million.

"The new contract at Dounreay Site Restoration Ltd, awarded to the Babcock Dounreay Partnership, has been successfully incorporated into the site's Lifetime Plan, and is expected to deliver more than �1bn in savings while achieving site closure up to 17 years earlier than originally anticipated.

"At the Low Level Waste Repository near Drigg, the contract awarded to UK Nuclear Waste Management (UKNWM) in 2008 has been extended for a further five years following a successful first five-year term, which secured around �30m in savings, extended the life of the facility, reduced volumes of waste sent to the Repository through the opening up of alternative waste management routes and saw the opening of a new vault.

"We are also part-way through the last major competition, award of the �7bn contract for the 12 sites operated by Magnox Ltd and RSRL Ltd, and are pleased to see a healthy level of interest from four high-calibre consortia.
"When looking at the overall costs of the clean-up programme over the next 120 years or so, we see a continuation of recent trends whereby life time costs are reducing in all parts of our estate with the exception of Sellafield, where some significant uncertainties remain. The net result is that the undiscounted figure for the long term clean-up programme is relatively stable."

Baroness Verma, Department of Energy and Climate Change minister with responsibility for nuclear decommissioning, said:"I've been impressed by the approach and professionalism of the NDA as the strategic authority acting on behalf of Government to oversee this vital programme.
"An absolute priority is to deal with the legacy, particularly at Sellafield. On visiting Sellafield I saw the sheer size, scale and complexity of the challenges facing the NDA. It is absolutely right that there is a relentless focus on tackling the inherited legacies of the first-generation nuclear power stations.

"The process will take many decades and will need to address many of the unique, high-hazard problems that accumulated in the post-war years.

"Significant milestones have also been achieved elsewhere in the NDA estate, delivering innovation, reduced timeframes and savings for the taxpayer as various research and former generating sites are progressively being defueled and decommissioned with land returned for future use."

The Dounreay section includes the following -
Dounreay Site Restoration Limited (DSRL) is the SLC responsible for
the operation of the Dounreay site.
The PBO is Babcock Dounreay Partnership Limited (BDP).
(a consortium comprising Babcock, CH2M Hill and URS)

DSRL is making good progress with the strategy for the remediation and decommissioning of the shaft and silo.

DSRL continue to progress the hazard reduction to expedite safe delivery of the site
interim end state.

three Material Test Reactor (MTR) storage tanks have been emptied, with 100m� of
MTR raffinate transferred and processed return of four shipments of MTR Belgian waste have taken place, and twenty six batches of Sodium Potassium (NaK) were processed through the NaK Disposal Plant, (NDP).

BDP took over the ownership of the Dounreay site following successful completion of share transfer on 31 March 2012. This is the first closure contract to take an NDA site to Interim End State.

DSRL has completed a successful year, with the consolidation phase of the new contract
successfully completed.

DSRL is making good progress with the new LLW Facility which will be used for disposal of demolition LLW from the Dounreay and Vulcan sites to allow decommissioning and site restoration to continue. All concrete foundations and walls have been poured for the two LLW vaults with commencement of the erection of the steelwork for the demolition of the LLW vault.

DSRL has commenced removal of legacy fuels from Dounreay and five shipments of fuel have been transferred to Sellafield for reprocessing and storage.

The full report can be found at -
http://www.nda.gov.uk/documents/upload/Annual-Report-and-Accounts-2012-2013.pdf

 

Related Businesses

 

Related Articles

NDA calls for engagement on refreshed decommissioning strategyThumbnail for article : NDA calls for engagement on refreshed decommissioning strategy
The NDA has published its strategy for consultation, setting out the roadmap to decommission the UK's earliest nuclear sites safely, securely and sustainably.   Today, the Nuclear Decommissioning Authority (NDA) has published its revised strategy for public consultation, setting out a clear roadmap for one of the UK's most complex long-term environmental challenges.  
NDA appoints two new Non-Executive Board Members
NDA announces Catriona Schmolke CBE FREng and Dr Neil Bruce OBE CEng as NDA Board members.   The Nuclear Decommissioning Authority (NDA) has announced that Catriona Schmolke CBE FREng and Dr Neil Bruce OBE CEng have been appointed to the NDA Board as Non-Executive Board members.  
New reports examine impact of nuclear decommissioning in ScotlandThumbnail for article : New reports examine impact of nuclear decommissioning in Scotland
Research offers a positive outlook for communities impacted by the decommissioning process.   A new study has revealed that Scotland's £25 billion nuclear decommissioning programme could deliver significant long-term economic and social benefits at both national and local levels over the next 90 years and beyond.  
NDA group deliver defueling milestone with EDFThumbnail for article : NDA group deliver defueling milestone with EDF
The Nuclear Decommissioning Authority (NDA) group played a pivotal role in defueling Hunterston B on time and on budget.   On 24 April 2025 EDF announced Hunterston B nuclear power station has been successfully defueled on time and on budget, in less than three years, following rigorous checks by the Office for Nuclear Regulation (ONR).  
NDA funds Plutonium Ceramics Academic Hub with universitiesThumbnail for article : NDA funds Plutonium Ceramics Academic Hub with universities
The Nuclear Decommissioning Authority has announced it's establishing a Plutonium Ceramics Academic Hub with the Universities of Manchester and Sheffield.   The Nuclear Decommissioning Authority (NDA) has announced it's establishing a Plutonium Ceramics Academic Hub with the Universities of Manchester and Sheffield.  
NDA group celebrates progress and innovation in parliamentThumbnail for article : NDA group celebrates progress and innovation in parliament
NDA utilises innovative technology to bring to life progress in delivering its nationally important mission at ‘Nuclear Week in Parliament'.   The Nuclear Decommissioning Authority (NDA) group utilised innovative technology to bring to life progress in delivering its nationally important mission at the Nuclear Industry Association's ‘Nuclear Week in Parliament' (NWIP).  
NDA group holds 10th Supply Chain EventThumbnail for article : NDA group holds 10th Supply Chain Event
The NDA group's Supply Chain Event saw 2,000 people and 300 exhibitors assemble at Telford International Centre yesterday (Thursday) for the decommissioning-focused networking event.   The day was launched by David Peattie, Chief Executive of the NDA group.  
NDA Opens New Specialised Cyber FacilityThumbnail for article : NDA Opens New Specialised Cyber Facility
The Nuclear Decommissioning Authority (NDA) group has launched a specialised cyber facility to accelerate collaboration across nuclear operators and the supply chain.  The adoption of innovative technologies such as AI and robotics is enhancing their collective ability to successfully defend against cyber threats.  
Nuclear Restoration Services Has Appointed Dave Wilson As Managing Director Of Its Dounreay DivisionThumbnail for article : Nuclear Restoration Services Has Appointed Dave Wilson As Managing Director Of Its Dounreay Division
He joins from AtkinsRealis, where he was market director and delivery lead for its nuclear decommissioning and waste services business, and officially takes up the post today (18 November 2024), He succeeds John Grierson who has served as interim MD since May.   NRS CEO Rob Fletcher said, "I am very pleased that Dave Wilson has agreed to join the team at Dounreay.  
NDA Supply Chain Award Winners 2024 Revealed
The Nuclear Decommissioning Authority group have announced five organisations as winners of this year's supply chain awards.   Morgan Sindall Infrastructure, The Decommissioning Delivery Partnership, PA Consulting, Antech and The Higher Activity Waste Thermal Treatment Tranche 1 Team are the big winners in this year's supply chain awards.