Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider  

 

57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay

6th April 2012

Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.
A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.

The coolant - an alloy of sodium and potassium (NaK) - was a major chemical and radiological hazard. An estimated 1000 trillion becquerels of caesium-137 was removed from the coolant during the chemical process that turned the 57 tonnes of liquid metal into 20,000 tonnes of salty water and took four years to complete.

Scotland's Cabinet Secretary for the Environment Richard Lochhead saw the last batches being processed.
He said: "This is a tremendous achievement and another example of how the highly skilled Dounreay workforce is delivering a world-class clean-up operation at one of the most complex nuclear sites in Europe.

"The Scottish Government welcomes today's announcement that Dounreay have successfully destroyed 57,000 litres of highly radioactive liquid metal from the Dounreay Fast Reactor."

The Nuclear Decommissioning Authority said it was "extremely pleased" the liquid metal no longer posed a hazard.
"This was very high on the list of hazards we wanted reduced across our whole estate," said Nigel Lowe, head of the NDA's Dounreay programme. "It's a significant achievement for Dounreay and joins a long list of examples whereby the site has delivered on key objectives and technical challenges."

The reactor - built in the 1950s - was one of only two ever built in Britain to run on liquid metal. Two cooling circuits connected by heat exchangers were filled with more than 161,000 litres of liquid metal.

More than 100,000 litres of NaK from the secondary circuit was destroyed when the reactor shut down in 1977.
Work on the primary circuit - a labyrinth of pipes 9 kilometres in length - stopped in the early 1980s when higher levels of radioactive contamination were detected.

The primary circuit contained 57,000 litres of NaK that flowed over the fuel pins in the reactor core.
The "open vent" design of the fuel cladding allowed the liquid metal to come into direct contact with the fuel, contaminating the primary coolant with huge levels of soluble radioactive caesium. Radiation measurements of the primary coolant showed the presence of 1000 trillion becquerels of caesium-137.

The high level of radioactive contamination added to the chemical hazard of alkali metal that reacts in contact with air or water. Its destruction remained on hold until a decade ago when work started on the construction of a purpose-built clean-up plant. The plant was designed to lift the liquid metal in small batches, neutralise the alkalinity with acid and extract the caesium via ion exchange.

In September 2007, the first of a total of 354 batches was lifted from the reactor. Each batch underwent chemical neutralisation to convert the alkali metal to a salty water before being passed through ion exchange columns that trapped the caesium. Designers thought the plant would decontaminate the effluent by a factor of 1000. Decontamination rates of up to 4 million were achieved during the operation, reducing levels of radioactivity in the effluent to below the limit of detection.

The resin columns used to trap the caesium will now be cemented up and managed as higher-activity waste.
"It's been a fantastic achievement by the whole team to deliver this milestone a year ahead of schedule and to higher environmental standards than anyone thought possible at the design stage," said Andy Swan, the engineer in charge of the reactor decommissioning.

"This stuff was highly volatile and highly radioactive. The chemical and radiological hazards combined to make this a real danger to the workers involved, so we needed to be certain they were protected at every step of the process until the hazard was destroyed. Their safety record throughout this operation was excellent."

Destruction of the liquid metal was among the strategic national priorities of the Department of Energy and Climate Change, which sponsors the Nuclear Decommissioning Authority.

With the reactor vessel empty of liquid metal, attention now turns to cleansing the residual traces from the primary circuit pipework and destroying small pockets in other vessels. When complete, a robotic arm will reach into the reactor vessel and begin removing the burst fuel pin and almost 1000 breeder elements still positioned around the core.

 

Related Businesses

 

Related Articles

Half the fuel gone from iconic Dounreay reactorThumbnail for article : Half the fuel gone from iconic Dounreay reactor
Half of the last remaining radioactive fuel elements jammed for decades inside the iconic Dounreay Fast Reactor (DFR) have now been removed.   DFR with its famous dome once led the world in fast breeder technology.  
Dounreay Apprentices Celebrate Completion Of Training SchemeThumbnail for article : Dounreay Apprentices Celebrate Completion Of Training Scheme
Seven Dounreay apprentices have received their indenture certificates at a special event to mark the successful conclusion of their 4-year training programme.   The latest group ‘graduating' joined the company in 2015 - the 60th year apprentices had been part of the workforce at Dounreay and the first time in more than a decade that design office apprentices had been recruited.  
A new intermediate waste store is being constructed at Dounreay.Thumbnail for article : A new intermediate waste store is being constructed at Dounreay.
The first concrete pour has taken place on a new waste store at Dounreay that will be needed for the closure of the site.   Dounreay awarded the contract to construct the new intermediate level waste store to GRAHAM Construction Ltd.  
Hold The Date For The NDA Supply Chain Event At A New Venue In 2020
The event, now in its ninth year, has been an overwhelming success in engaging with the suppliers who are so essential to achieving our decommissioning mission.   Since launching in 2011, the event has attracted a total of around 10,000 visitors from more than 20 countries, representing thousands of companies both large and small.  
NDA Stakeholder Summit 2019 Main HighlightsThumbnail for article : NDA Stakeholder Summit 2019 Main Highlights
This was the NDA's third summit, and the inspirational setting of the new Coleg Menai facilities, on Anglesey in North Wales, perfectly reflected the NDA’s approach to building sustainable post-nuclear communities around its estate.  Some £4 million of funding from the NDA’s socio-economic budget has been used to create a state-of-the-art educational facility at the heart of the island.  
AECOM signs agreement with Toshiba to perform nuclear decommissioning services in JapanThumbnail for article : AECOM signs agreement with Toshiba to perform nuclear decommissioning services in Japan
The partnership will expand access to the key Asian market that is valued at $50 billion and further underscores AECOM's leading nuclear decontamination and decommissioning capabilities.   LOS ANGELES (June 17, 2019) — AECOM (NYSE:ACM), a premier, fully integrated global infrastructure firm, and Toshiba have signed an Alliance Agreement to work together on decommissioning nuclear reactors in Japan.  
US and UK complete project to remove highly enriched uraniumThumbnail for article : US and UK complete project to remove highly enriched uranium
The Nuclear Decommissioning Authority and US Department of Energy's National Nuclear Security Administration (NNSA) have completed the transfer of around 700kg of highly enriched uranium (HEU) from Dounreay, in the north of Scotland, to the US.   The HEU transfer, from Dounreay to the United States, was announced by the UK Government as part of its commitment to the 2016 Nuclear Security Summit held in Washington DC.  
Supply chain to play key role in decommissioning projects at DounreayThumbnail for article : Supply chain to play key role in decommissioning projects at Dounreay
Dounreay Site Restoration Limited (DSRL) has opened the door to dozens of companies to play an active role in supporting the delivery of Scotland's largest decommissioning project.   Construction of a size reduction facility, shaft and silo decommissioning and demolition of historic active laboratories are just some of the major projects expected to be delivered as part of a decommissioning services framework, potentially worth up to £400 million, which was announced on Tuesday 23rd April 2019.  
Dounreay Communities Fund - Closing Dates For Applications In 2019Thumbnail for article : Dounreay Communities Fund - Closing Dates For Applications In 2019
The fund is provided by the Nuclear Decommissioning Authority and administered by Dounreay in association with the Dounreay Stakeholder Group.   Community organisations or charities that benefit people in Caithness and North Sutherland may be eligible for assistance from the Dounreay Communities Fund.  
Nuclear Decommissioning - Demolition Starts On Windscale ChimneyThumbnail for article : Nuclear Decommissioning - Demolition Starts On Windscale Chimney
The first blocks of concrete have been removed from the top of one of the world's most recognisable chimneys.   This marks the start of the demolition of Sellafield's Windscale Pile One stack.  

[Printer Friendly Version]