Particles Could Be Cleaned Up Earlier Than Expected

3rd October 2007

The clean-up operation for radioactive particles offshore could be substantially complete within seven years while onshore monitoring with removal of detected particles would continue for a longer period if UKAEA's recommended way forward is accepted.

Following a review of all the information gained from public consultation, studies, test & trials, independent expert reports, improvements in the monitoring technologies and the knowledge gained by offshore mapping surveys, it is believed that an environmentally and publicly acceptable clean up could be achieved within this timescale.

Over the last two years UKAEA has conducted a public consultation programme and has, as the final stage, now come forward with a draft recommendation to implement particle removal from the offshore environment alongside monitoring onshore and recovery.

Over the next three summers, remotely-operated vehicle(s) would scour an area of seabed equivalent to 600,000m2 (60 football pitches) where the most hazardous particles are located. The fourth summer of monitoring and recovery will be integrated with the remediation of the old diffuser with a further three summers for re-checking and recovery. This area is almost certainly the source of particles found on local beaches and the progressive clean-up of this area should reduce and eventually eliminate the supply of the pollution to the beaches. Onshore monitoring and recovery would continue, until the seabed clean up has been demonstrated to be effective, at frequencies agreed with the Scottish Environment Protection Agency and the relevant landowner. The cost of monitoring and recovery both onshore and offshore over this seven year period has been estimated at in the region of £18-25million. Offshore trials of remote recovery equipment at the end of 2007, should allow this estimate to be
improved.

Sandside Estate which owns the affected Sandside Bay beach welcomes the UKAEA's draft recommendation.

Simon Middlemas, Dounreay Director said, "We have done an enormous amount of technical studies and have accumulated a huge amount of information which allows us to move forward to identify options which clearly, after extensive consultation, shows that this is an environmentally and publicly acceptable way forward. We have also been able to utilise recent offshore survey work and the information gained from enhanced beach surveys at Sandside into our recommendation. I would like to stress that this is a
preliminary recommendation and we have invited further public comment before we review and agree on how to take this forward with the key agencies and affected land owners"

Phil Cartwright, Contaminated Land and particles manager said "There is a far greater understanding of the extent of particle contamination now, monitoring systems are continually improving and we have a greater certainty of particle detection both on and offshore. In particular the co-operation of Sandside Estate and discussion with their experts, over the past 18 months, has aided this process.

"The recommendation is a broad strategy and the technical details will continue to be considered with the key agencies and stakeholders involved. Development of detection and recovery systems will continue, especially for the offshore environment.

"We do recognise that the removal of all particles from the environment is not going to be possible. Therefore the recovery strategy has to be considered in conjunction with the information on health effects in relation to particle activity ranges.

"There is a lot of historical information on particles and how they were released from Dounreay, as well as recent information on where the main concentrations of particles are now. The preliminary recommendation, identified from the best practical environmental option process, provides a good opportunity to move forward with something that is broadly acceptable to everyone. Following this final stage, of public comment, the important thing will be to get on with the clean-up and with the information gained, continue to look for further improvements to hasten the removal of large numbers of particles from the seabed. This is expected, within the next 10 years, to lead to lower numbers and lower activity particles being found on the local beaches where the majority of particles have been found, at Dounreay and at Sandside."

Geoffrey Minter of Sandside Estate commenting today said, "Co-operation between Dounreay and Sandside in recent times has permitted the exchange of detailed information. The recent seabed survey has for the first time proved the prediction that many more radioactive particles are on their way to Sandside which is the only publicly accessible beach where particles of relevance have and will continue to beach. It has also proved that something has to be done about the problem which will not go away by
itself.

"I am now confident that something will be done and there are clear signals that the issue is beginning to receive the attention it deserves. To that end I have today given UKAEA consent for the first in-depth survey and three dimensional mapping of Sandside beach which will be conducted in October. Following this, excavation work for which I have also given consent, can be conducted for the first time to reveal to us just what lies
in the Sandside sands below the surface that Ground Hog can reliably reach with its detectors. We both consider that this work should provide the last piece in the jigsaw puzzle of the particles at Sandside from which to move forward. I would stress that UKAEA's projected end dates are all subject to what is found along the way."

The final stage of the consultation allows members of the public to feedback their views which will be considered by UKAEA before producing their final recommendation to SEPA.

 

Related Businesses

 

Related Articles

UKAEA Monthly Newsletter Latest EditionThumbnail for article : UKAEA Monthly Newsletter Latest Edition
Find out what has been happening at UKAEA in our monthly newsletter.  Read about our recent activities and upcoming events.  
UKAEA Newsletter - Edition 11 Published TodayThumbnail for article : UKAEA Newsletter - Edition 11 Published Today
Find out what has been happening at UKAEA in our monthly newsletter.  Read about our recent activities and upcoming events.  
Corwm Visits Dounreay Nuclear SiteThumbnail for article : Corwm Visits Dounreay Nuclear Site
Members were given an overview of the scale of the problem and challenges faced in the decommissioning of the site.   In the last week of March 2024, several members of CoRWM led by the Chair, Sir Nigel Thrift, made the long journey up to the North of Scotland to visit the Dounreay nuclear site, now managed by Nuclear Restoration Services.  
Design Contract Awarded For Dounreay Shaft And Silo WorkThumbnail for article : Design Contract Awarded For Dounreay Shaft And Silo Work
Dounreay has awarded an important waste clean-up contract to Jacobs as the site plans for the future of its deepest historic radioactive waste store.   Jacobs and its supporting partners have been awarded a 6-year contract to provide a design management team to produce a fully integrated design for the shaft and silo project.  
Radiation dose to public from Dounreay reducesThumbnail for article : Radiation dose to public from Dounreay reduces
Dounreay’s radioactive impact on the environment continues to fall, according to a report.  The annual survey report “Radioactivity in Food and the Environment” (RIFE 2012) has recently been published and it can be read here - http://www.sepa.org.uk/radioactive_substances/publications/rife_reports.aspx The report uses data obtained from samples of air, fresh water, grass, soil, and locally sourced meat, fish, milk and vegetables during 2012.  
57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay
Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.  A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.  
Dounreay Dome Paint Job ScrappedThumbnail for article : Dounreay Dome Paint Job Scrapped
Bosses at Dounreay agreed that they won't now be spending £500,000 on a repaint of the sphere.   They money saved will go instead towards actual decommissioning work.  
Clean-up Reveals 6000 Years Of Human HistoryThumbnail for article : Clean-up Reveals 6000 Years Of Human History
Getting rid of Britain's 20th century experiment with fast breeder nuclear reactors is illuminating the history of human settlement on Scotland's north coast stretching back 6000 years.   Archaeologists hired as part of the closure of the nuclear site at Dounreay have pieced together the legacy left by previous generations who occupied the site as long ago as 4000BC.  
New Report Lists Radioactive Wastes At DounreayThumbnail for article : New Report Lists Radioactive Wastes At Dounreay
The Nuclear Decommissioning Authority has published the latest edition of the UK's radioactive waste inventory.   This sets out the type and volumes of radioactive waste at sites such as Dounreay, as of April 1, 2010.  
Nuclear Shutdown Cash Boost For School Skills
Cash from the closure of the fast reactor site at Dounreay is set to breed a new generation of engineers and scientists in the Scottish Highlands.   The money from the Nuclear Decommissioning Authority will fund half the cost of a £50,000 project to increase the number of school-leavers skilled in science, technology, engineering and maths.