Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider  

 

Innovative Camera Records Final Sodium Removal

19th March 2008

Dounreay's Prototype Fast Reactor has now been drained of all 1500 tonnes of liquid metal that once flowed through its primary and secondary circuits.

The last batch of hazardous sodium has been transferred from the base of the reactor vessel and is now being destroyed in a purpose-built chemical treatment plant that extracts the radioactivity and converts the sodium to common salt that can be discharged safely to the sea.

It means the site has almost completed the destruction of one of the major hazards leftover from its research days.

PFR decommissioning manager James McCafferty said it had been achieved without a lost-time accident for more than three years.

"The team behind this achievement is drawn from several different companies but all had one thing in common - to deliver the removal of this hazard from the reactor to the highest standards of personal and environmental safety," he said.

Staff were able to see the last remaining few tonnes being removed from the bottom of the reactor by attaching a camera to a purpose-built pump that was lowered into the "heel" of the reactor vessel.

This was the most difficult part of the sodium to reach and required innovative design and extensive testing by the reactor clean-up team to develop a system that would clear the final pools of metal. It was the first time anyone has seen inside the vessel since its construction 40 years ago.

Attached to a steel hose, the camera assembly manoeuvred through the complex internals of the reactor to reach the very bottom. Operating in an extreme radiation environment with temperatures in excess of 200 degrees Celsius, it filmed the pump removing the final 20 tonnes from the mirror-like pool of sodium.

It has taken eight years to drain the reactor in a way that ensured the safety of the workforce and the environment was protected.

The final stage was completed using the innovative camera-pump device designed in-house by UKAEA's specialist design team. It was built by JGC Technical Services Ltd and operated by Nukem. Initially mock-ups were built and tested at the T3e facility at Janetstown where the whole assembly was also commissioned and the operators trained.

Billy Husband, alkali metal residues removal project manager at PFR, said: "Achieving this project is a major step forward in our programme to decommission PFR. We have worked on this particular stage of the project for two years and it has without doubt been a success due to the dedicated team of UKAEA and contractor staff working together."

Lead designer Robin Herrick helped with the deployment and operations. "Seeing the equipment in use is very exciting. To keep the camera cool way down at the bottom of the reactor vessel, I designed something akin to a 23-metre long flexible Thermos flask. It was a big challenge."

The lead operations engineer on this project is Evan Park, who also worked at PFR in its infancy and watched the sodium being loaded into the reactor in 1974. He said: "When I worked here during the construction of PFR I never thought I would be standing here today overseeing such a major phase of its decommissioning."

The removal of the sodium means the decommissioning team can now "steam-clean" the last traces of sodium from the pipework using a water vapour nitrogen process, making it safe to begin dismantling the entire system.

 

Related Businesses

 

Related Articles

Diamonds Are Forever? World-first Carbon-14 Diamond Battery Made In UkThumbnail for article : Diamonds Are Forever? World-first Carbon-14 Diamond Battery Made In Uk
The world's first carbon-14 diamond has been produced with the potential to provide power for thousands of years.   Scientists and engineers from the UK Atomic Energy Authority (UKAEA) and the University of Bristol have successfully created the world's first carbon-14 diamond battery.  
UKAEA Monthly Newsletter Latest EditionThumbnail for article : UKAEA Monthly Newsletter Latest Edition
Find out what has been happening at UKAEA in our monthly newsletter.  Read about our recent activities and upcoming events.  
UKAEA Newsletter - Edition 11 Published TodayThumbnail for article : UKAEA Newsletter - Edition 11 Published Today
Find out what has been happening at UKAEA in our monthly newsletter.  Read about our recent activities and upcoming events.  
Corwm Visits Dounreay Nuclear SiteThumbnail for article : Corwm Visits Dounreay Nuclear Site
Members were given an overview of the scale of the problem and challenges faced in the decommissioning of the site.   In the last week of March 2024, several members of CoRWM led by the Chair, Sir Nigel Thrift, made the long journey up to the North of Scotland to visit the Dounreay nuclear site, now managed by Nuclear Restoration Services.  
Design Contract Awarded For Dounreay Shaft And Silo WorkThumbnail for article : Design Contract Awarded For Dounreay Shaft And Silo Work
Dounreay has awarded an important waste clean-up contract to Jacobs as the site plans for the future of its deepest historic radioactive waste store.   Jacobs and its supporting partners have been awarded a 6-year contract to provide a design management team to produce a fully integrated design for the shaft and silo project.  
Radiation dose to public from Dounreay reducesThumbnail for article : Radiation dose to public from Dounreay reduces
Dounreay’s radioactive impact on the environment continues to fall, according to a report.  The annual survey report “Radioactivity in Food and the Environment” (RIFE 2012) has recently been published and it can be read here - http://www.sepa.org.uk/radioactive_substances/publications/rife_reports.aspx The report uses data obtained from samples of air, fresh water, grass, soil, and locally sourced meat, fish, milk and vegetables during 2012.  
57,000 Tonnes Of Hazardous Materials Finally Dealt With At Dounreay
Dounreay today completed the destruction of one of the most hazardous legacies of Britain's earliest atomic research.  A purpose-built chemical plant processed the last of 57,000 litres of liquid metal lifted from the primary cooling circuit of the experimental fast breeder reactor.  
Dounreay Dome Paint Job ScrappedThumbnail for article : Dounreay Dome Paint Job Scrapped
Bosses at Dounreay agreed that they won't now be spending £500,000 on a repaint of the sphere.   They money saved will go instead towards actual decommissioning work.  
Clean-up Reveals 6000 Years Of Human HistoryThumbnail for article : Clean-up Reveals 6000 Years Of Human History
Getting rid of Britain's 20th century experiment with fast breeder nuclear reactors is illuminating the history of human settlement on Scotland's north coast stretching back 6000 years.   Archaeologists hired as part of the closure of the nuclear site at Dounreay have pieced together the legacy left by previous generations who occupied the site as long ago as 4000BC.  
New Report Lists Radioactive Wastes At DounreayThumbnail for article : New Report Lists Radioactive Wastes At Dounreay
The Nuclear Decommissioning Authority has published the latest edition of the UK's radioactive waste inventory.   This sets out the type and volumes of radioactive waste at sites such as Dounreay, as of April 1, 2010.