Highland Council Major School Projects Progress Report

11th August 2023

At yesterday's (Thursday 10 August 2023) Housing and Property Committee, Members were updated on the progress of the ten major school projects, the actions taken and the revised programme dates for the proposed new Nairn Academy building.

Housing and Property Committee Chair, Cllr Glynis Campbell Sinclair said: "Despite the complexities of the current financial constraints the report highlights the immense work being undertaken to drive progress with all projects to design, pre-planning and build stage.

It is vital that whilst the Capital Programme is under review that work continues to allow all the major school projects to advance. The ‘Capital Major Project Whole Life' reporting has been very useful for Members as it sets out the whole life costs of the major projects along with "RAG" ratings in relation to the main criteria of Cost, Time and Scope.

“I would like to thank the Housing and Property team for all the hard work that has gone into each project stage and to the communities involved for their continuous engagement and understanding during this challenging time."

Construction work on the Tain Campus project, which is included in Phase 1 of the Scottish Government’s Learning Estate Investment Programme (LEIP), commenced in late September 2022 with an expected completion date of December 2024. The new Ness Castle Primary was completed in February 2023 and the design work is progressing on the new school buildings at Broadford Primary School and Nairn Academy, both of which are included in Phase 2 of LEIP.

One of the conditions of the Phase 2 LEIP funding award is that the buildings must be occupied by the end of 2025. However, the Council has made a formal request to the Scottish Government for an extension to the operational date for the new Nairn Academy building to August 2026 due to the time required to carry out a full review of the overall cost plan to bring the build cost within the proposed increased budget.

The Council agreed at its meeting in June 2022 that design and planning work should continue to progress on the major school projects at pre-construction stage that are listed below. The capital funding included in the one-year programme approved in March 2023 will allow the projects to be taken up to tender stage while awaiting the outcome of the review of the Council’s Capital Programme.

Beauly Primary School - New Build (LEIP Phase 3)
Charleston Academy - Extension/Refurbishment
Culloden Academy – Extension/Refurbishment
Dunvegan Primary School – New Build (LEIP Phase 3)
Park Primary School – New Build (LEIP Phase 3)

A funding bid for Phase 3 of LEIP was submitted to the Scottish Government in October 2022 for the following projects: replacement buildings at Beauly, Dunvegan and Park Primary Schools; a replacement building on a new site in Dingwall for St Clement’s School; and a building for the new Primary School at the Tornagrain development to the east of Inverness. It is not known when an announcement will be made by the Scottish Government.

Construction costs remains a significant pressure for the Council including the following:

General inflation/tender cost indices – rising oil and gas prices; material and labour shortages; the impact of various socio-economic factors and worldwide events; manufacturing and distribution constraints; local, national, and worldwide demand.

Extraordinary increases in costs of certain materials or products.
Local supply chain – limited number of sub-contractors in Highland for certain types of work or sizes of project.

Central belt supply chain – already busy so further inflated cost of working on Highland projects, effectively a higher cost location factor.

Risk management – contractors, sub-contractors and suppliers are all factoring in additional risk allowances to cover any further increases, particularly for projects with a longer construction period, thus exacerbating the overall position.

More stringent design and energy performance standards - this includes the adoption of the Passivhaus design principles for new build schools, such as the Tain 3-18 Campus, that are part of the LEIP programme.

There is also a requirement to work towards ambitious targets in relation to achieving Net Zero emissions and a reduction in Construction Embodied Carbon.

The full report is available here (Item 8)
https://www.highland.gov.uk/meetings/meeting/4828/housing_and_property_committee

 

Related Businesses

 

Related Articles

Environmental schemes on the agenda of Highland Council's Economy and Infrastructure Committee
Environmental schemes on the agenda of Highland Council's Economy and Infrastructure Committee Members of Highland Council's Economy and Infrastructure Committee will have the opportunity to discuss compensatory planting schemes and biodiversity enhancement when they meet on Thursday 29 May.   Economy and Infrastructure Committee Chair, Cllr Ken Gowans said: "Environmental schemes are important for our communities as they ensure that biodiversity is improved when new infrastructure projects are developed.  
Final phase for Community Council Scheme Review public consultation
The Highland Council has launched phase 2 of a public consultation on how Community Councils across the Highlands are created and governed.   The Community Council Scheme Review was on the agenda of the Highland Council meeting held on the 15 May 2025, Members agreed to the phase 2 review of the Scheme and that the proposals informed by the phase 1 review be subject to further public consultation.  
Committee to discuss delivery plan for 2025/26 UK Shared Prosperity Fund
At the meeting Economy and Infrastructure Committee next week (Thursday 28 May) members will decide how over £3 million of funding from the UK Government through the UK Shared Prosperity Fund (UKSPF) will be used over the next 12 months to deliver a positive impact across communities.   The proposed 2025/26 Highland UKSPF Delivery Plan is made up of a range of projects geared to delivering positive impacts.  
Yesterday
Highland Council agrees outcomes for mainstreaming equality
Members of Highland Council's Communities and Place Committee have today welcomed progress against the Council’s Equality Mainstreaming and Outcomes Report.  They also agreed a revised set of equality outcomes for 2025- 2029.  
Yesterday
Highland Council drives forward with fleet management action plan
Highland Council has updated members of the Communities and Place Committee on its Fleet Action Plan supplied to the Office of the Traffic Commissioner for Scotland.   The action plan was developed following an independent audit of the Council's fleet operations and addresses a number of improvements being made in relation to compliance and control processes and monitoring of heavy goods vehicles.  
22/5/2025
Social Value Charter to Ensure Communities Get Fair Share
The work underway to ensure that Highland communities can benefit from profits being generated by renewable developments will be under the spotlight at next week's meeting of the Economy and Infrastructure Committee.   At the meeting on Thursday 29 May, Members will receive an update on progress with the Highland Social Value Charter, which aims to ensure that if developments get the go ahead there is a clear community benefit.  
22/5/2025
Communities face growing expectation gap - Council Budgets Are In TroubleThumbnail for article : Communities face growing expectation gap  - Council Budgets Are In Trouble
Mounting pressures from inflation, increasing costs and demand are exceeding the Scottish Government's additional investment in Scotland's councils.  In 2025/26 councils received over £15 billion in government funding, with more money set to be raised from council tax and charges for some services.  
22/5/2025
Highland Council's Progress Update on Net Zero Programme
At the meeting of the Highland Council's Climate Change Committee, Members were given an update on the Council's Net Zero Programme.   Members welcomed the development of projects that will deliver carbon reductions, operational efficiencies and financial savings.  
22/5/2025
Partnership working to tackle climate adaptation strengthened through Highland Adapts initiative
Highland Council's Climate Change Committee has today reaffirmed its commitment to climate adaptation by supporting the continued work of Highland Adapts - a regional initiative focused on building climate resilience through partnership and community-led action.   Chair of the Climate Change Committee, Councillor Sarah Fanet, said: "The Highland region is already experiencing the effects of climate change from increased flooding to changes in biodiversity and these impacts are only expected to intensify.  
21/5/2025
Impressive new waste and recycling figures for Highland
The Highland Council is pleased to announce new waste and recycling figures for the region, following the introduction of the new waste and recycling services over the last year.   The roll out of the new waste and recycling services to householders and businesses began in April 2024 and has been funded by the Scottish Government's Recycling Improvement Fund.