Highland Council Major School Projects Progress Report

11th August 2023

At yesterday's (Thursday 10 August 2023) Housing and Property Committee, Members were updated on the progress of the ten major school projects, the actions taken and the revised programme dates for the proposed new Nairn Academy building.

Housing and Property Committee Chair, Cllr Glynis Campbell Sinclair said: "Despite the complexities of the current financial constraints the report highlights the immense work being undertaken to drive progress with all projects to design, pre-planning and build stage.

It is vital that whilst the Capital Programme is under review that work continues to allow all the major school projects to advance. The ‘Capital Major Project Whole Life' reporting has been very useful for Members as it sets out the whole life costs of the major projects along with "RAG" ratings in relation to the main criteria of Cost, Time and Scope.

“I would like to thank the Housing and Property team for all the hard work that has gone into each project stage and to the communities involved for their continuous engagement and understanding during this challenging time."

Construction work on the Tain Campus project, which is included in Phase 1 of the Scottish Government’s Learning Estate Investment Programme (LEIP), commenced in late September 2022 with an expected completion date of December 2024. The new Ness Castle Primary was completed in February 2023 and the design work is progressing on the new school buildings at Broadford Primary School and Nairn Academy, both of which are included in Phase 2 of LEIP.

One of the conditions of the Phase 2 LEIP funding award is that the buildings must be occupied by the end of 2025. However, the Council has made a formal request to the Scottish Government for an extension to the operational date for the new Nairn Academy building to August 2026 due to the time required to carry out a full review of the overall cost plan to bring the build cost within the proposed increased budget.

The Council agreed at its meeting in June 2022 that design and planning work should continue to progress on the major school projects at pre-construction stage that are listed below. The capital funding included in the one-year programme approved in March 2023 will allow the projects to be taken up to tender stage while awaiting the outcome of the review of the Council’s Capital Programme.

Beauly Primary School - New Build (LEIP Phase 3)
Charleston Academy - Extension/Refurbishment
Culloden Academy – Extension/Refurbishment
Dunvegan Primary School – New Build (LEIP Phase 3)
Park Primary School – New Build (LEIP Phase 3)

A funding bid for Phase 3 of LEIP was submitted to the Scottish Government in October 2022 for the following projects: replacement buildings at Beauly, Dunvegan and Park Primary Schools; a replacement building on a new site in Dingwall for St Clement’s School; and a building for the new Primary School at the Tornagrain development to the east of Inverness. It is not known when an announcement will be made by the Scottish Government.

Construction costs remains a significant pressure for the Council including the following:

General inflation/tender cost indices – rising oil and gas prices; material and labour shortages; the impact of various socio-economic factors and worldwide events; manufacturing and distribution constraints; local, national, and worldwide demand.

Extraordinary increases in costs of certain materials or products.
Local supply chain – limited number of sub-contractors in Highland for certain types of work or sizes of project.

Central belt supply chain – already busy so further inflated cost of working on Highland projects, effectively a higher cost location factor.

Risk management – contractors, sub-contractors and suppliers are all factoring in additional risk allowances to cover any further increases, particularly for projects with a longer construction period, thus exacerbating the overall position.

More stringent design and energy performance standards - this includes the adoption of the Passivhaus design principles for new build schools, such as the Tain 3-18 Campus, that are part of the LEIP programme.

There is also a requirement to work towards ambitious targets in relation to achieving Net Zero emissions and a reduction in Construction Embodied Carbon.

The full report is available here (Item 8)
https://www.highland.gov.uk/meetings/meeting/4828/housing_and_property_committee

 

Related Businesses

 

Related Articles

Today : Local Authority

Head Teacher at Thurso High School, outlined measures that have helped improve educational outcomes

Highland Council’s strategy to raise attainment in the region is making good progress, with encouraging early data emerging from this year's examination results.   Last week councillors on the education committee noted the work undertaken in Highland Council's Education and Learning Improvement Plan (ELIP) and the associated Raising Attainment and Achievement Strategy (RAAS).  

28/8/2026 : Local Authority

Council Funded Advice services assist 25,000 customers and exceed £30.3 million in financial gains

Almost 25,000 customers were assisted by the Council’s Welfare Support Team and Citizens Advice during 2025/26 for support with welfare, debt and housing issues.   As a result, financial gains for clients exceeded £30.3 million, representing a £18.84 return for every £1 allocated to these services by the Council.  

28/8/2026 : Local Authority

 
Do We Need a New Kind of Cemetery? Could Highland's Greenspaces Help Make Funerals More Affordable?

There may be no more appropriate time to ask Highland Council whether we need to rethink the way we remember those who have died.   The Council has just launched a six-week consultation on its draft Greenspace Biodiversity Management Strategy 2026-2030.  

26/8/2026 : Local Authority

The Triple Squeeze: Energy, Mortgages and Council Tax — How Much More Can Households Take?

There is a point at which individual increases in household costs stop being individual problems and become something much bigger.   A £100 increase in the annual energy bill may be manageable.  

24/8/2026 : Local Authority

Thurso Schools: Public Meeting and Statutory Consultation – Key Dates

Highland Council has now formally launched its statutory consultation on proposals to replace Thurso High School and reorganise primary school provision in the town.   The consultation concerns the proposed relocation of Thurso High School, Pennyland Primary School and Miller Academy Primary School to a new education campus based around the existing Thurso High School site and the proposed Community Point of Delivery.  

21/8/2026 : Local Authority

Public consultation to help shape future policy protecting Highland's dark skies

Councillors have approved the launch of a public consultation on draft guidance aimed at reducing light pollution across the Highlands, supporting environmental protection, public wellbeing and the area's internationally recognised dark skies.   Members of the Economy and Infrastructure Committee yesterday (Thursday 20 August) agreed to publish the draft Reducing Light Pollution: Good Practice Guidance for consultation, once minor clarifications are included, giving residents, communities, businesses and developers the opportunity to help shape future policy.  

21/8/2026 : Local Authority

Highland bus service improvement plans

The Highland Council's Economy and Infrastructure Committee has endorsed plans to launch a 12-week public consultation on a proposed Highland Bus Service Improvement Partnership (BSIP), giving communities, passengers and stakeholders the opportunity to help shape the future of bus services across the region.   The consultation will seek views on draft proposals developed by The Highland Council in partnership with HITRANS and bus operators to improve the operational performance, accessibility, attractiveness and consistency of bus services across Highland.  

19/8/2026 : Local Authority

Demand for social housing remains high across Highland Butit is part of a biggr Scottish Problem

Demand for social housing across the Highlands remains high, with almost 8,826 households on the Highland Housing Register (HHR).   Housing and Property Committee Chair, Cllr Glynis Campbell Sinclair, said: “The demand for social housing across Highland remains significant and continues to outstrip the number of homes available in many areas.  

19/8/2026 : Local Authority

Highland Council to consider Draft Visitor Levy Scheme at Special Meeting

A special meeting of The Highland Council will take place Tuesday 25 August 2026 to consider a draft Visitor Levy proposal.   No decision is being sought at this stage on whether a Visitor Levy should be introduced in the Highlands.  

11/8/2026 : Local Authority

 
Nature Restoration Fund Community Grants Programme opens for applications

Community groups, charities, public sector bodies and other eligible organisations across Highland are being encouraged to apply for funding through the 2026/27 Highland Nature Restoration Fund (NRF) Community Grants Programme, which opens for applications on Friday 14 August 2026.   Applications will be assessed on a rolling basis, with grants available from £2,000 to £25,000 for capital projects that help restore nature, safeguard wildlife and address biodiversity loss.