Highland Council Major School Projects Progress Report

11th August 2023

At yesterday's (Thursday 10 August 2023) Housing and Property Committee, Members were updated on the progress of the ten major school projects, the actions taken and the revised programme dates for the proposed new Nairn Academy building.

Housing and Property Committee Chair, Cllr Glynis Campbell Sinclair said: "Despite the complexities of the current financial constraints the report highlights the immense work being undertaken to drive progress with all projects to design, pre-planning and build stage.

It is vital that whilst the Capital Programme is under review that work continues to allow all the major school projects to advance. The ‘Capital Major Project Whole Life' reporting has been very useful for Members as it sets out the whole life costs of the major projects along with "RAG" ratings in relation to the main criteria of Cost, Time and Scope.

“I would like to thank the Housing and Property team for all the hard work that has gone into each project stage and to the communities involved for their continuous engagement and understanding during this challenging time."

Construction work on the Tain Campus project, which is included in Phase 1 of the Scottish Government’s Learning Estate Investment Programme (LEIP), commenced in late September 2022 with an expected completion date of December 2024. The new Ness Castle Primary was completed in February 2023 and the design work is progressing on the new school buildings at Broadford Primary School and Nairn Academy, both of which are included in Phase 2 of LEIP.

One of the conditions of the Phase 2 LEIP funding award is that the buildings must be occupied by the end of 2025. However, the Council has made a formal request to the Scottish Government for an extension to the operational date for the new Nairn Academy building to August 2026 due to the time required to carry out a full review of the overall cost plan to bring the build cost within the proposed increased budget.

The Council agreed at its meeting in June 2022 that design and planning work should continue to progress on the major school projects at pre-construction stage that are listed below. The capital funding included in the one-year programme approved in March 2023 will allow the projects to be taken up to tender stage while awaiting the outcome of the review of the Council’s Capital Programme.

Beauly Primary School - New Build (LEIP Phase 3)
Charleston Academy - Extension/Refurbishment
Culloden Academy – Extension/Refurbishment
Dunvegan Primary School – New Build (LEIP Phase 3)
Park Primary School – New Build (LEIP Phase 3)

A funding bid for Phase 3 of LEIP was submitted to the Scottish Government in October 2022 for the following projects: replacement buildings at Beauly, Dunvegan and Park Primary Schools; a replacement building on a new site in Dingwall for St Clement’s School; and a building for the new Primary School at the Tornagrain development to the east of Inverness. It is not known when an announcement will be made by the Scottish Government.

Construction costs remains a significant pressure for the Council including the following:

General inflation/tender cost indices – rising oil and gas prices; material and labour shortages; the impact of various socio-economic factors and worldwide events; manufacturing and distribution constraints; local, national, and worldwide demand.

Extraordinary increases in costs of certain materials or products.
Local supply chain – limited number of sub-contractors in Highland for certain types of work or sizes of project.

Central belt supply chain – already busy so further inflated cost of working on Highland projects, effectively a higher cost location factor.

Risk management – contractors, sub-contractors and suppliers are all factoring in additional risk allowances to cover any further increases, particularly for projects with a longer construction period, thus exacerbating the overall position.

More stringent design and energy performance standards - this includes the adoption of the Passivhaus design principles for new build schools, such as the Tain 3-18 Campus, that are part of the LEIP programme.

There is also a requirement to work towards ambitious targets in relation to achieving Net Zero emissions and a reduction in Construction Embodied Carbon.

The full report is available here (Item 8)
https://www.highland.gov.uk/meetings/meeting/4828/housing_and_property_committee

 

Related Businesses

 

Related Articles

Yesterday : Local Authority

Homelessness statistics in Scotland - April to September 2025

An update on Homelessness Statistics covering 1 April to 30 September 2025 has been released today.   Over that period: There were 20,643 applications for homelessness assistance.  

29/1/2026 : Local Authority

Council Services Outsourced But Not Immune - Why High Life Highland Is Still Vulnerable to Budget Cuts

When Highland Council transferred responsibility for leisure, culture and community learning services to High Life Highland (HLH), the move was often presented as a way to protect valued local services from the worst of council budget cuts.   By placing libraries, leisure centres, swimming pools and cultural provision into a charitable trust, the council could take advantage of tax reliefs, external funding opportunities and more flexible operating arrangements.  

29/1/2026 : Local Authority

How Highland Council's Budget Decisions Expose Some Services More Than Others

Highland Council faces a set of financial pressures that are both familiar across Scottish local government and uniquely intensified by its geography, population size, and historic investment choices.   While headline debates often focus on council tax rises or total debt levels, the real impact of financial tightening is felt in how different services are protected, redesigned, or reduced over time.  

29/1/2026 : Local Authority

Which Services Are Most Likely to Face Cuts or Reductions At Budget Day

When budgets tighten in Highland Council, cuts tend not to fall evenly.  Some services are much more exposed than others because of how local government funding rules work and because of Highland's geography.  

29/1/2026 : Local Authority

How Highland Council Debt Affects Local Services

Highland Council's high debt connects to local services and council tax, in practical, day-to-day terms.   Council debt doesn't pay for services directly — but it affects them.  

29/1/2026 : Local Authority

 
Highland Council Debt Is One Of Highest Per Person in the UK

Highland Council has one of the higher levels of debt among Scottish local authorities, especially when looked at per person.  It is not necessarily the absolute highest in total debt compared with councils that have much larger populations like Edinburgh or Glasgow.  

29/1/2026 : Local Authority

 
Scotland's councils risk becoming financially unsustainable

Whilst councils have made significant savings, the cost of delivering services is rising faster than available funding.  This risks the financial sustainability of councils over the next three to five years.  

29/1/2026 : Local Authority

Asset Management is a catalyst for change for The Highland Council

At the Housing & Property Committee (Wednesday 28 January 2026), Members approved the introduction of a new framework to guide decisions on the future of its assets, supporting a more efficient, sustainable and future-ready approach to service delivery.  The Strategic Asset Management Plan (SAMP) will help streamline the estate, embed new ways of working, and contribute to significant savings set out in the Council's Delivery Plan.  

29/1/2026 : Local Authority

Reduction in households in temporary accommodation and improved housing outcomes

At Housing & Property Committee (Wednesday 28 January 2026), The Highland Council reported a strong performance across several key housing indicators, including a reduction in households in temporary accommodation, improved repairs times, and the lowest level of rent arrears in three years.   New figures show that the number of homeless households living in temporary accommodation has fallen to 421, the lowest level recorded since The Scottish Government introduced this measure in April 2016.  

24/1/2026 : Local Authority

 
New facility for additional support needs pupils at Wick High School

Last week Wick High School was delighted to welcome guests from The Highland Council, Wick High Parent Council and the wider community to the open day of a new facility for children with additional support needs.   Avonlea, which was previously a residential unit, has now been repurposed, and this enhanced provision represents a significant step forward for pupils with complex additional support needs.