Caithness Map :: Links to Site Map Great value Unlimited Broadband from an award winning provider SAT 7TH JUN 2025    12:09:32 PM BST
This site uses cookies, by continuing to use this site you accept the terms of our privacy policy
Back To Top
Caithness.Org Quick Links
Home
Construction
Leisure
Manufacturing
Misc.
Primary
Professional
Public
Retail
Tourism
Transport
Site Map
 
 
 
 
 
 
 
 
 
 
 
 
 

Feed 2.0 Loading...

3 Wind Turbines For Community Group In Caithness Get Planning Permission

19th June 2012

The north Planning committee of Highland council agreed on Tuesday 19th June 2012 to grant planning permission for construction of a Community Wind Farm at Rumster Forest with Three 900 kW Wind Turbines, with a Height to Hub of 50m and a Rotor Diameter of 50 m, Formation of Access Track and Erection of a Switchgear Building and Associated Cabling.

The applicants were Latheron, Lybster and Clyth Community Development Company formed a few years ago following the set up of an Initiative at the Edge project. The project has carried out a number of community activities and smaller projects to improve the area on the east of Caithness that had a falling population, falling school rolls and markedly growing number of elderly people. It was recognised that if the community were to be able top continue to have future a source of revenue was essential to help with further projects and job creation.

The application was for the development and operation of a wind farm consisting of three wind turbines with an overall generating capacity of 2.7MW. The wind turbines to be employed are from a choice of three machines - Enercon E44 900kW or E48 800kW, or alternatively the Gamesa or Vestas 850kW. The proposal has considered a generic wind turbine of 80m to tip for the purposes of calculating the degree of potential impacts. A new section of access track, a switchgear building and both underground and above ground cabling to link with the national
grid is proposed. This proposal represents the first 'Community' renewable energy development of this scale in Caithness.

The site is located in a clearfelled area at Gaultiquoy within the wider Rumster Forest situated approximately 7 km to the north west of the village of Lybster in east Caithness. The site is accessed directly by forestry track from the C1053 Lybster-Achavanich road which in turn is accessed from either the A9 (T) at Achavanich or from the A99 (T) by Lybster. A roadside public car park is located adjacent to the start of the forestry track at Rumster Forest.

The access route for the turbine components will be via the A99 from Wick Harbour to Lybster and thereafter the C1053 to Rumster Forest and onto the existing forestry track. A short section of new track will be required to link the site with the existing forestry track, widening the existing track to 4m and minor works to the Smerlie Road/A99 road junction are envisaged works to facilitate access to the site.

The landscape is upland in character with areas, outwith the commercial coniferous plantations of Rumster Forest, in heather and rough grass. The nature of the area is remote with no nearby houses or steadings. The general landform continues to rise to the north west to the summit of Stemster Hill whilst the shoulder of land on which the proposal is made eventually falls beyond the application site to the north east. Ground conditions on site are peat overlying rock with surface vegetation becoming re-established following clear felling although the general area remains characterised by brashings and tree stumps making general access to/across the site, on foot, difficult.

There were 10 objectors to the proposal some of whom are members of an anti wind farm lobbying group. None of the statutory consultees raised any objections although Scottish Natural Heritage asked for mitigations -
The proposal lies approximately 350m from the Shielton Peatlands Site of Special Scientific Interest (SSSI) which is a component of the Caithness and Sutherland Peatlands Special Area of Conservation (SAC) and Special Protection Area (SPA).

It is also noted that the qualifying interests of the East Caithness Cliffs SPA may also be ffected.

SNH note concerns regarding potential pollution arising from the development which require assessment to this end a pollution prevention plan is advised to avoid impacts to watercourses and supported species.

In consideration of bird species it is advised that works are completed outside of the bird breeding season. Thereby avoiding disturbance to ground nesting birds and damage to their nest sites.

Mammals of particular note include Water Voles, Otters and Pine Martins. SNH note licensing requirements regarding works on site owing to the presence of Water Voles and list a number of mitigation methods to be employed.

In consideration of avoidance of breeding seasons for Water Voles the period March to October inclusive is recommended. Other mitigation methods including re-routing of new sections of track, pollution prevention plans, tunnelling under watercourses and pre-construction surveys are advocated.

Impacts to Otters may be mitigated through a pollution prevention plan. Impacts to Pine martins may either be mitigated through construction works being avoided during the breeding season (April - July inclusive) or preconstruction surveys. Landscape and visual interests are appraised to the extent that SNH agree with the conclusions of the Landscape and Visual Impact Assessment (LVIA) noting the adverse impacts upon; the Flow Country and Berriedale Coast Special Landscape Area; the Small Farms and Crofts and Moorland Slopes and Hills landscape character types and sequential cumulative impacts together with the Burn of Whilk
wind farm along the A99. SNH do not believe that the impacts are significantly adverse. It is noted with concern the repeated mention within the LVIA of scope for further development - the application is assessed as presented, comment should not be construed in excess of the current application.

An annex is provided by SNH appraising impacts to the East Caithness Cliffs SPA, Caithness & Sutherland Peatlands SAC and Caithness and Sutherland Peatlands SPA. In the main conservation objectives remain undiminished in respect of this development subject to the mitigation methods noted.

In the report the planning officer noted various points including the fact that there would be little affect from noise as the nearest dwelling was over 2 kilometers away from the turbines.

The planning officer pointed out to eh committee that a bond of one million pounds had been considered at an early stage. Vehicle movements and haulage of parts and materials has been raised as concern by the Roads Authority. Of particular concern is the C1053 Lybster-achavanich road which is subject to weight restrictions owing to failures of sections of this road in areas of underlying peat in 1996. This led to the consideration of a substantial roads bond of �1million. On further consideration of all the facts this bond had been reduced to �30,000.

 

Related Businesses

 

Related Articles

8/6/2025
Applications open for Education Maintenance Allowance 2025/26 - £30 per week Apply now
All eligible young people are being encouraged to apply for a weekly, term time allowance of £30 per week from August 2025.   The Highland Council administers Education Maintenance Allowance (EMA) in respect of eligible young people from across its 29 secondary schools.  
Support secured for LGBT Veterans
Legislation has been amended to ensure veterans who receive a payment from the LGBT Financial Recognition Scheme do not lose out on council tax support.   More than 1,200 people in Scotland who served under and suffered from the ban on lesbian, gay, bisexual and transgender (LGBT) personnel serving in HM Armed Forces between 1967 and 2000 have applied to the UK Government for compensation so far.  
5/6/2025
Integrated Children Services Planning Board - Annual Update
At the Education Committee of Highland Council on Wednesday 4 June, Members were presented with the Integrated Children Services Plan Annual Report 2024/25.   The Integrated Children's Service’s work continues as it enters the 3rd year of the delivery of the Integrated Children’s Service Plan.  
5/6/2025
Education update and positive destinations for our school leavers
The Highland Council, Education Committee met today (Wednesday 4 June 2025) and received a comprehensive overview of recent developments in the Education and Learning Service.  It included positive school leaver destinations and an update on the refreshed attainment strategy and the Education and Learning management restructure.  
5/6/2025
Expanding opportunities to learn Gaelic at school
Tha comhairlichean Chomhairle na Gàidhealtachd air fàilte a chur air an obair ionmholta a thathar a' dèanamh gus cothroman a leudachadh do luchd-ionnsachaidh òga na Gàidhlig.   Aig coinneamh Chomataidh na Gàidhlig an-diugh (Diciadain 4 Ògmhios) chaidh an obair leasachaidh a thathar a’ dèanamh aig Bun-Sgoil Bhaile an Fhraoich ann an Inbhir Nis a chomharrachadh mar dheagh eisimpleir de bhith a’ cruthachadh "spiorad mhath is ion-ghabhaltach airson na Gàidhlig thar na sgoile".  
5/6/2025
Dedicated road marking team mobilised throughout the HighlandsThumbnail for article : Dedicated road marking team mobilised throughout the Highlands
Highland Council's dedicated road marking team has been fully mobilised to carry out road marking across the Highland region.  Finally after many years of depending on contractors from the south a Highland council team will be able to get on with the work regularly as weather allows.  
4/6/2025
New Seasonal Access Rangers start across Highland
Last weekend saw the first patrols of The Highland Council's, new Seasonal Access Ranger team.  The new rangers will seek to promote and advise on responsible access to the countryside through the Scottish Outdoor Access Code.  
3/6/2025
Food in Schools project surveys underway - Help Stop Waste and reduce costs
The Highland Council's ‘Food in Schools' project is a key component of the Council’s Delivery Plan and the Redesign Board Chaired by the Convener of the Council - Councillor Bill Lobban has launched a range of surveys to better understand the various components of food provision in school settings.   The surveys will be issued by Head Teachers, on behalf of the Food in Schools project team, to current pupils (P1-S6), parents and carers, teachers and non-teaching staff (e.g.  
3/6/2025
Applications Now Open for Highland Council's Strategic Events Grant
Applications Now Open for Highland Council's Strategic Events Grant.   The Highland Council is pleased to announce the official launch of its new Strategic Events Grant Fund, a £75,000 initiative designed to support the region's dynamic events sector and strengthen the local economy during the quieter shoulder and off-season months.  
2/6/2025
The Highland Council to trial ballot paper overlay to make voting more accessible Thumbnail for article : The Highland Council to trial ballot paper overlay to make voting more accessible
In a recent survey of blind and partially sighted people, only a quarter feel that the current system allows them to vote independently and in secret.  We want to change that.