River Ness Flood Scheme work starts in earnest
12th September 2013

The Inverness public is being advised that work will start in earnest from Monday 16 September on the construction of flood walls along the River Ness between the Ness Bridge and Friars Bridge. Every attempt is being made to minimise disruption by maintaining at all times pedestrian access to shops and businesses, which will continue to trade as normal.
Signs have been put in place to give motorists advance warning of the works, which are part of an �8.5 million first phase of flood wall construction to ease the threat of flooding to 800 homes and 200 businesses.
The work is being carried out for The Highland Council by Morgan Sindall.
Bank Street
From 7am on Monday 16 September there will be no through road on Bank Street from Fraser Street to Friars Lane. This will remain in place until 29 November. Access to Fraser Street via Bank Street will only be authorised for taxis, buses, cyclists, waste management, delivery and emergency vehicles and property, pedestrian and hotel access. Traffic management will be in place during this period. To accommodate advance drainage works, Fraser Street closed at 7am today (Monday 9 September) and will remain closed until the morning of Saturday 14th September, with access restricted for deliveries and to properties only. Pedestrian access will be maintained.
Huntly Street
From 7am on Monday 16 September the one-way system on Huntly Street between Young Street and Greig Street will be permanently reversed. The traffic lights at the Young Street/Huntly St junction will be switched off to improve traffic flow in the direction of Greig Street. There will also be one-way movement in Greig Street, from Huntly Street to Kings Street. This is a permanent measure.
Bus Changes
From Monday 16 September until Friday 29 November, Stagecoach will be re-routing Services 17, 19, 28, 917 and 919 via Friars Bridge. Passengers should note that the Young St bus stop will be moved to Kenneth Street (opposite Central Primary School) There will also be changes to the pick-up points for services 3, 4, 6, 7 which will use bus stops in Union St during the works, rather than on Academy Street at Farmfoods. Stagecoach will be notifying passengers of this change on buses and at the bus stops.
Motorists and cyclists are advised to plan their journeys in advance of these changes.
Flood Alleviations Scheme web pages
Related Businesses
Related Articles
The Highland Council is pleased to announce new waste and recycling figures for the region, following the introduction of the new waste and recycling services over the last year. The roll out of the new waste and recycling services to householders and businesses began in April 2024 and has been funded by the Scottish Government's Recycling Improvement Fund.
The Highland Council is pleased to announce its participation in the UK Real Estate Investment & Infrastructure Forum (UKREiiF), taking place this week in Leeds. The event is recognised as the UK's leading platform for fostering partnerships and securing investment in regeneration, infrastructure, and economic development.
Highland Councillors have considered £756m investment across Highland communities over the next 5 years when they discussed an updated report on the consolidated Highland Investment Plan (HIP) at a meeting of The Highland Council on Thursday 15 May 2025. Convener of the Council, Cllr Bill Lobban said: "The consolidated programme which was presented to Members is part of a longer-term strategy for the Highland Investment Plan which creates a potential £2.1bn of capital investment over a twenty-year period.
Highland Council's Environmental Health team have identified raised levels of naturally occurring bivalve shellfish biotoxins following routine monitoring at Loch Portree. Eating bivalve shellfish such as cockles, mussels, oysters or razor fish from the area of Loch Portree may pose a health risk arising from the consumption of these biotoxins.
After a successful three-week trial of thermal technology in 2024, Highland Council has appointed Thermal Road Repairs for a two-year patching repair contract worth a seven-figure sum. This will provide an additional resource for repairing surface defects such as potholes, cracking and deteriorating surfacing joints.
The scale of transformational opportunity facing the Highlands and Islands economy has been quantified for the first time in a new report. The study reports 251 planned development projects in the economic pipeline of what it refers to as regional transformational opportunities (RTOs).
Maggie Cunningham and Dr. Jim McCormick have been appointed as co-chairs of a new multi-partnership Poverty and Equality Commission Board.
The Highland Council has published its Renewable Energy Mapping Tool. This tool will enable those with an interest in understanding the location and type of renewable energy projects within Highland to discover not only what already exists on the ground but also the stage that any projects may be at within the planning process.
The Highlands and Islands Regional Economic Partnership (HIREP)'s Regional Economic Strategy addresses the challenges affecting the region's businesses and communities. A partnership of public, private and academic organisations in the Highlands and Islands has unveiled its ten-year strategy to deliver sustainable economic growth across the region.
BT has launched a consultation on the removal of 110 public payphones in Highland which they state are no longer needed. Details of the payphones being considered for closure are set out in the list at this link.