Wick Campus Delay Until 2017
22nd September 2016
At a Wick stakeholders meeting held on Monday 19 September at Wick High School, representatives from Hub North Scotland and Morrison Construction gave an update on reasons for the delay and outlined a revised programme for the Wick campus delivery.
The meeting was chaired by Highland Councillor for Wick Bill Fernie who expressed the Council's disappointment at the delay, and re-stated the Council's priorities to ensure that the flagship facility is completed to the standard expected, and accepting handover only at that point.
Angus MacFarlane, Chief Executive of Hub North Scotland advised the group of a revised handover date for the Campus of Friday 2 December 2016 which remains subject to a number of risks.
He explained that there is a detailed dialogue taking place between Highland Council, Hub North Scotland and Morrison Construction on the revised programme and decant arrangements for Wick High School, Newton Park Primary and High Life Highland community facilities.
The head of Morrisons construction also laid to rest several rumours regarding the construction that there was no sinking/subsidence of any foundations and any broken windows were repaired as required. The faulty steel beam had been replaced. Several people who had been round to see the position were happy with what is going to be provided when the school finally opens.
The Council is working on detailed plans for the school moves with Head Teachers and High Life Highland, and is considering options for the moves either side of the festive period, with anticipated occupation of the new campus in early January, or around the mid-term break in February, with occupation by the end of February. The Council made clear to the Stakeholder Group that the move plans are still being developed and had to be realistic, achievable, and not impact on the learning and teaching of pupils. The Council recognises that pupils and parents will want early notification of when the schools' will commence within the new facility and that will be provided as soon as possible.
Depending on Hub north Scotland and their contractor Morrison Construction handing over the building and the Council accepting it on 2 December, the Council will provide early notification to parents of the expected occupation arrangements.
Ian MacGillivray from the Council's Project Design Unit provided an update on the delayed Safer Routes to Schools elements of work on the approaches to the school. BEAR Scotland will install a new pedestrian crossing on Francis Street and the Council's contractor will carry out work in Seaforth Avenue and Thurso Road - all during October.
There will be a further package of safety improvements next spring after demolition of the existing school is complete. The delay to the Road Traffic Orders for the 20mph zone around Wick Noss school is also being prioritised as a matter of urgency.
Related Businesses
Related Articles
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
Households across Scotland have received £4.1 billion in relief since the Council Tax Reduction scheme was introduced in 2013. People on low incomes are eligible for the benefit if they live in Scotland - there is no equivalent in England where most councils require each household to contribute a minimum amount of council tax, irrespective of ability to do so.
The Highland Council is preparing to carry out improvement works in Thurso at Ormlie Road and at The Mall riverside path adjacent to Janet Street. The scope of works on Ormlie Road will include junction improvements between Castlegreen Road and Juniper Drive with new drop kerbs and tactile paving and some surface repairs.
A Highland-wide partnership launched earlier in 2024 to support people on their journey towards, into and within employment is looking forward to a New Year in 2025 full of exciting opportunities designed to help hundreds more people across the Highlands unlock their work potential. Work.
The Highland Council is delighted to share that its Energy Efficient Scotland: Area Based Scheme has won the Outstanding Project Award at the Scottish Green Energy Awards. Described by Scottish Renewables as a "pioneering clean power scheme", this £7 million project demonstrates the incredible impact that can be achieved through combined public and private sector investment.
The ambitious yet focused ‘Highland Investment Plan' is committed to addressing our asset challenges over the next twenty years. By using a place based approach, to ensure a more integrated community offering through the creation of new community facilities.
Applications to the Inverness Winter Payments Scheme, which is fully funded by the Inverness Common Fund, have already been awarded to 1,035 eligible households within the 7 specified Inverness Wards. Leader of Inverness Area, Councillor Ian Brown said: "Since the Scheme was opened to applications for this winter, already £114,885 has been awarded to people who live in the eligible Wards of Aird and Loch Ness, Inverness West, Inverness Central, Inverness Ness-side, Inverness Millburn, Culloden and Ardersier and Inverness South Wards.
The first Highland-wide virtual jobs fair held last month has proved to be a hit with participants and businesses. The week-long virtual event, which was delivered by the Local Employability Partnership for the West - The Highland Council, Skills Development Scotland, Highlands and Islands Enterprise, Department for Work and Pensions, Developing the Young Workforce and UHI North West and Hebrides was timed to coincide with Scottish Careers Week 2024.