Council agrees site for Materials Recovery Facility

16th August 2018

The Council's Environment, Development and Infrastructure Committee has today agreed the Longman Landfill site in Inverness as the preferred location to construct a new centralised waste management facility (Materials Recovery Facility) to recover recyclates and produce Refuse Derived Fuel, as the Council's preferred interim arrangements for meeting the requirements of the ban on landfilling which commences in January 2021. This facility will process all of the Highland’s 83,000 tonnes of residual (non-recyclable) waste from 2021 onwards.

The Materials Recovery Facility (MRF) will be designed to process mixed residual waste and look to recover value from the material by removing recyclable streams such as metals and plastics, but in the main, producing a refuse derived fuel in readiness for sending to Energy from Waste facilities elsewhere.

The planning application process can now proceed in liaison with the Inverness Common Good Fund which is the site landowner. An implementation team have been preparing an external design of the facility and will preparing for the submission of a planning application, later in the autumn.

The Council will also carry out further work to look at the feasibility of constructing an Energy-from-Waste (EfW) facility co-located on the site in the future as a long term option if resources can be identified.

Thousands of tonnes of waste are produced in Highland every year, a large proportion of which currently ends up in landfill. The vast majority of waste is from households.

The Council handles some 140,000 tonnes or waste per annum, and around 57,000 tonnes of this material is currently re-used, recycled or recovered from kerbside collections from households and businesses, as well as from Recycling Centres and Points.

However, around 83,000 tonnes of biodegradable municipal waste is sent to landfill at a cost of approximately £11 million a year.

Councillor Allan Henderson who chairs the Council’s Environment, Development and Infrastructure Committee said: "I strongly believe that waste produced in the Highlands should be dealt with in the Highlands and the Longman site provides the best strategic location with excellent transport links.

"Long gone are the days when it was ok to just bury our waste out of sight in sites such as this, and allow future generations to deal with the consequences. The national legislation changes coming in on 1 January 2021 mean, like all other councils, we will not be allowed to landfill our biodegradable municipal waste. The aims of this ban are to promote waste being regarded as a commodity or resource, maximise reuse and recycling, and stimulate a circular economy. The ban will also reduce the amount of methane being produced by landfill sites. Methane is a greenhouse gas that is 30 times more powerful than CO2. Failure to address the ban on landfilling waste is a significant risk for the Council. Urgent action is now required, and doing nothing is not an option."

Councillor Jimmy Gray, the Administration’s Environmental Spokesperson, added: “Highland needs an overall waste strategy that is sustainable, affordable, friendly to the environment and efficient (SAFE).

“Our waste strategy needs to go beyond finding a clean and efficient way of dealing with our waste. We also need to promote a massive culture change - to change people’s behaviour and attitudes to waste and litter. We need the support of everyone, as individuals, families, schools, businesses and communities, to ensure that we in the Highlands set an example for the rest of Scotland to follow."

Notes:

Big changes to the way that all Councils in Scotland manage their waste were introduced by the Scottish Government in 2012. The Waste (Scotland) Regulations 2012 and Making Things Last (A circular economy strategy for Scotland) set out the context for future waste management in Scotland.

The Highland Council’s proposed Residual Waste Strategy focuses on the ban of biodegradable municipal waste from landfill from January 2021.

The Council will also decide on whether to investigate the viability of building an Energy from Waste Plant in the Inner Moray Firth.

The benefits of EWP are that it would:

Provide long-term skilled employment opportunities for plant operation

Contribute to the Council’s low carbon energy strategy and plans, by generating low carbon power for export to grid and heat for use locally by industry or in District Heating scheme

Provide a focus for future ‘green’ industrial development (through provision of low cost, low carbon process heat)

Reduce vehicle movements on the A9 by eliminating bulk haulage of waste to central Scotland

Contribute towards the Council’s sustainability objectives.

The Council has compared the cost of its current arrangements over 25 years against these proposals, and estimates that they would cost between £4 million and £20 million more over the same period. However, the doing nothing option is unacceptable

The Council is also looking for suitable locations for these new facilities, and this is taking into account all the natural heritage and land use issues, including Sites of Special Scientific Interest and Nature Conservation areas

The Council’s Waste Awareness Team will continue to engage with the public including school pupils to promote the Council’s recycling facilities and to encourage waste minimisation to help meet the Council’s recycling and landfill targets set by the Scottish Government.

The Council is investigating how it can use the new facilities to help the Highlands minimise its impact on the environment by, for example, banning Single Use Plastics in its schools and offices, and tackling plastic litter on its coastline

In the longer term, the Council wants to take responsibility for dealing with its own waste at its own facility within the Highlands and not rely on facilities in the Central Belt or the North of England which involve costly and environmentally unfriendly transporting of waste

Modern Energy from Waste technology is well regulated and minimises harm to the environment. SEPA’s position on Energy from Waste is that appropriately located and well managed Energy from Waste (EfW) facilities, that meet modern requirements such as the stringent emission standards, should not cause significant pollution of the environment or harm human health.

The Council will continue to work within the waste hierarchy of Prevent, Reuse, Recycle, Recover Value

With regards to recycling, SEPA’s position is that Energy from Waste is compatible with high rates of recycling. High recycling levels depend on efficient segregation of the recyclable materials: waste that cannot be technically or economically recycled can be processed and the energy recovered

Currently almost all residual waste is landfilled with around 32,000 tonnes being bulked and transported out of the Highlands for landfill disposal in Aberdeenshire under a contract with SUEZ until September 2019. The remainder is landfilled at

Council sites at Seater in Caithness or Grainish in Aviemore, or

Duisky landfill site in Lochaber

What is a Materials Recovery Facility (MRF)? These can fall into two main categories, those that are designed to process large volumes of mixed recyclables (e.g from the blue bins) into their individual material streams and prepare them for sale in the commodity markets; or , as in this case, others that deal with mixed residual waste and look to recover value from the material by removing small amounts of recyclable streams such as metals and plastics, but in the main, producing a refuse derived fuel in readiness for sending to Energy from Waste facilities.

What is Refuse Derived Fuel (RDF)? Fuel that is produced from waste that cannot currently be recycled. Refuse derived fuel is used in thermal treatment facilities such as Energy from Waste plants and can generate electricity and hot water for communal heating systems in the local area.

What is Energy from Waste? Energy from waste is the process of creating energy, in the form of electricity and/or heat, from treating waste at high temperature. Energy from waste facilities can be designed to provide power (electricity) and/or heat.

 

Related Businesses

 

Related Articles

1/9/2026 : Local Authority

 
Candidates for Highland Council Ward 3 Wick and East Caithness By-Election confirmed

Following today’s deadline for nominations, The Highland Council can confirm the details of the 5 candidates that are standing in the Ward 3 Wick and East Caithness by-election.  There are 5 candidaes.  

Today : Local Authority

Head Teacher at Thurso High School, outlined measures that have helped improve educational outcomes

Highland Council’s strategy to raise attainment in the region is making good progress, with encouraging early data emerging from this year's examination results.   Last week councillors on the education committee noted the work undertaken in Highland Council's Education and Learning Improvement Plan (ELIP) and the associated Raising Attainment and Achievement Strategy (RAAS).  

28/8/2026 : Local Authority

Council Funded Advice services assist 25,000 customers and exceed £30.3 million in financial gains

Almost 25,000 customers were assisted by the Council’s Welfare Support Team and Citizens Advice during 2025/26 for support with welfare, debt and housing issues.   As a result, financial gains for clients exceeded £30.3 million, representing a £18.84 return for every £1 allocated to these services by the Council.  

28/8/2026 : Local Authority

 
Do We Need a New Kind of Cemetery? Could Highland's Greenspaces Help Make Funerals More Affordable?

There may be no more appropriate time to ask Highland Council whether we need to rethink the way we remember those who have died.   The Council has just launched a six-week consultation on its draft Greenspace Biodiversity Management Strategy 2026-2030.  

26/8/2026 : Local Authority

The Triple Squeeze: Energy, Mortgages and Council Tax — How Much More Can Households Take?

There is a point at which individual increases in household costs stop being individual problems and become something much bigger.   A £100 increase in the annual energy bill may be manageable.  

24/8/2026 : Local Authority

Thurso Schools: Public Meeting and Statutory Consultation – Key Dates

Highland Council has now formally launched its statutory consultation on proposals to replace Thurso High School and reorganise primary school provision in the town.   The consultation concerns the proposed relocation of Thurso High School, Pennyland Primary School and Miller Academy Primary School to a new education campus based around the existing Thurso High School site and the proposed Community Point of Delivery.  

21/8/2026 : Local Authority

Public consultation to help shape future policy protecting Highland's dark skies

Councillors have approved the launch of a public consultation on draft guidance aimed at reducing light pollution across the Highlands, supporting environmental protection, public wellbeing and the area's internationally recognised dark skies.   Members of the Economy and Infrastructure Committee yesterday (Thursday 20 August) agreed to publish the draft Reducing Light Pollution: Good Practice Guidance for consultation, once minor clarifications are included, giving residents, communities, businesses and developers the opportunity to help shape future policy.  

21/8/2026 : Local Authority

Highland bus service improvement plans

The Highland Council's Economy and Infrastructure Committee has endorsed plans to launch a 12-week public consultation on a proposed Highland Bus Service Improvement Partnership (BSIP), giving communities, passengers and stakeholders the opportunity to help shape the future of bus services across the region.   The consultation will seek views on draft proposals developed by The Highland Council in partnership with HITRANS and bus operators to improve the operational performance, accessibility, attractiveness and consistency of bus services across Highland.  

19/8/2026 : Local Authority

Demand for social housing remains high across Highland Butit is part of a biggr Scottish Problem

Demand for social housing across the Highlands remains high, with almost 8,826 households on the Highland Housing Register (HHR).   Housing and Property Committee Chair, Cllr Glynis Campbell Sinclair, said: “The demand for social housing across Highland remains significant and continues to outstrip the number of homes available in many areas.  

19/8/2026 : Local Authority

Highland Council to consider Draft Visitor Levy Scheme at Special Meeting

A special meeting of The Highland Council will take place Tuesday 25 August 2026 to consider a draft Visitor Levy proposal.   No decision is being sought at this stage on whether a Visitor Levy should be introduced in the Highlands.