Buried Hazards, Unfinished Business - What the NDA's 2025 Progress Report Really Tells Us
1st December 2025

The Nuclear Decommissioning Authority (NDA) has released its 2025 Mission Progress Report is a slightly sprawling document chronicling one of the UK's most complex environmental undertakings. The safe dismantling of its early nuclear legacy. It's a story of radioactive waste, strategic milestones, and a timeline that stretches well into the 22nd century.
But for ordinary citizens, the real question is- what does this mean for us, our environment, and our wallets?
The Mission at a Glance
Scope: Decommissioning 17 nuclear sites across the UK, managing spent fuels, plutonium, uranium, and radioactive waste.
Some targets extend to 2125, with ongoing work to reduce uncertainty and improve inventory accuracy.
The report tracks progress across four "driving themes": Spent Fuels, Nuclear Materials, Integrated Waste Management, and Site Decommissioning & Remediation.
Progress Highlights (and Gaps)
Plutonium: 100% produced and consolidated — but 0% repacked for long-term storage, and 0% disposed.
Uranium: 100% produced, 83% consolidated, but only 4% treated and 3% reused or disposed.
Spent Magnox Fuel: All sites defueled (100%), but only 25% of legacy fuel retrieved.
Intermediate Level Waste (ILW): Just 10% treated, 16% in interim storage, and 0% disposed.
Land Release: Only 9% of land has been delicensed or relicensed for future use — with 946 hectares still pending.
These figures paint a picture of partial progress. While some milestones are complete, others remain stubbornly stalled. The NDA's strategy is clear: stabilise the most hazardous materials first, then dismantle and remediate. But the pace is glacial — and the costs, both financial and environmental, are long-term.
What Ordinary Citizens Should Know
This is a taxpayer-funded mission: Billions have been spent, and billions more will be needed. The NDA promises "maximum value for the UK taxpayer," but progress metrics suggest that value is still unfolding.
Environmental safety is the priority: The report stresses secure storage and hazard reduction, but permanent disposal solutions (like Geological Disposal Facilities) remain years away.
Jobs and land reuse are future-facing Decommissioned sites could offer new employment and regeneration opportunities — but only if remediation accelerates.
This isn't just a technical report — it's a window into how the UK handles its nuclear past. The NDA's mission is vast, slow-moving, and essential. But for families and communities near these sites, the stakes are real: land that can't be reused, waste that can’t yet be disposed, and a clean-up that spans generations.
The NDA group - Mission Progress Report 2024/25
Read the full report HERE
Pdf 20 Pages
Related Businesses
Related Articles
Joint venture to develop neutral beams for fusion and non-fusion applications, creating high-skilled jobs and establishing a critical supply chain. TAE Technologies, a leading US private fusion energy firm with over 25 years at the forefront of scientific innovation, today announces a bilateral and reciprocal investment commitment with the United Kingdom's national fusion laboratory, the UK Atomic Energy Authority (UKAEA) to commercialise TAE's proprietary particle accelerator technology for the global market.
The Civil Nuclear Constabulary (CNC) welcomes its newest recruits. The CNC hosted two passing out parades for the graduating Authorised Firearms Officers (AFOs) of Initial Foundation Programme (IFP) 106.
Nuclear Restoration Services Dounreay's Kate Thomson has won Modern Apprentice of the Year at the Highlands & Islands Apprenticeship Awards in Inverness. Kate, who is in the second year of her apprenticeship in commercial and quantity surveying, said she was thrilled by the honour.
Nuclear Regulatory Taskforce publishes final report and calls for radical reset of overly complex nuclear regulatory system. An overly complex nuclear regulatory system has contributed to the "relative decline" of the UK's ability to deliver faster and cheaper nuclear projects.
The NDA group has announced it's working with CX Power as the strategic developer to support the delivery of the green energy hub masterplan at Chapelcross. The Nuclear Decommissioning Authority (NDA) group has announced it's working with CX Power as the strategic developer to support the delivery of the green energy hub masterplan at Chapelcross, a programme set to transform the region.
A specialist ports consultant has been appointed to develop a long-term strategic plan for Wick Harbour Authority (WHA) in Caithness. WHA has secured £47,775 from Highlands and Islands Enterprise (HIE) and the Nuclear Restoration Services, NRS Dounreay towards the cost of the services.
NDA announces £1 million investment to develop masterplan for clean energy development on land adjacent to Sellafield. The Nuclear Decommissioning Authority (NDA) has announced today it's investing £1 million of funding to develop the masterplan for a clean energy development on land adjacent to Sellafield, known as Pioneer Park.
Rising star from North Scotland honoured at event to celebrate brightest and best in industry. An electrical apprentice from North Scotland is celebrating after being recognised for her contribution to industry at the 13th annual Engineering Construction Industry ECI Training and Development Awards in London.
The NDA group graduate scheme offers far more than just a stepping stone into the nuclear industry; it's a chance to grow professionally, explore new places, and become part of a supportive community. Nuala Ledward, Assurance and Performance Graduate, shares how her secondment to Dounreay brought these benefits to life.
The NDA group has been allocated £154 million in government funding to develop specialised capabilities to enable plutonium disposal. People in North West England are benefitting from £154 million in government funding to develop specialised capabilities to enable the disposal of the UK's civil plutonium inventory.