Britain's Outsourcing Problem: Why Does Government Keep Handing Billions to Private Contractors When So Many Deals Go Wrong?

29th November 2026

From Capita's troubled pension contracts and Fujitsu's cancelled DWP deal to Highland Council's return to in-house IT, a pattern of missed targets, unrealistic expectations and weak contract management raises serious questions about how public money is spent.

There is an uncomfortable question facing governments across Britain. Why do public bodies repeatedly hand essential services to large private contractors, often promising substantial savings and improvements, only to find themselves dealing with missed deadlines, failing computer systems, backlogs and expensive remedial work?

The latest controversy concerns Capita and the administration of the Civil Service Pension Scheme. But this is not an isolated incident. There is a long history of problems involving major government contracts, including work undertaken by Capita, Fujitsu, Atos and Carillion.

Some of these contracts have failed spectacularly. Others have been brought back in-house because public bodies concluded that they could manage services more effectively themselves. Taken together, they raise questions about whether the problem lies with the companies, the way contracts are awarded, the ability of government departments to manage them, or a combination of all three.

And this is not simply a Westminster issue. Highland Council has its own experience of outsourcing computer services, first to Fujitsu and subsequently to Wipro, before deciding to bring much of the work back under council control.

Capita and the Civil Service pension problems

The Civil Service Pension Scheme is one of the largest pension arrangements in the country. It serves hundreds of thousands of current and former civil servants, as well as pensioners and their families.

In 2023, the Cabinet Office awarded Capita a seven-year contract, worth approximately £239 million, to take over administration of the scheme from MyCSP in December 2025. The contract was expected to save £83 million over its lifetime compared with the previous arrangement.

However, difficulties appeared before the new service had properly got going.

The National Audit Office reported that Capita had missed three important transition milestones. The Cabinet Office withheld £9.6 million in transition payments and agreed to a phased introduction, with some functionality delayed.

The problems then continued after Capita took over. Members reported delays in receiving pension payments, difficulties getting cases dealt with and uncertainty about when their benefits would be processed.

The Government introduced emergency support for people affected. By August 2026, more than £22.1 million had been provided in interest-free bridging loans to over 3,900 members. These are loans, not compensation or additional pension benefits, and must be repaid when the proper payments are received.

The Government also withheld further contract payments after Capita missed recovery deadlines. In September 2026, ministers confirmed that Capita had failed to meet major operational commitments, including targets for clearing inherited payment arrears and dealing with sensitive divorce cases.

Capita has argued that it inherited a distressed service with a substantial backlog. That is relevant, because the previous administrator's performance also deserves scrutiny. The National Audit Office had already criticised the Cabinet Office's management of the previous MyCSP contract, including its failure to hold the administrator effectively accountable when service levels fell below expectations.

But that does not remove Capita's responsibility for the commitments it subsequently made.

The question is how a contract intended to improve service and save money has left thousands of members waiting for pension payments and needing temporary financial assistance.

Capita's earlier problems with the NHS and Army recruitment

This is not the first time Capita has encountered serious difficulties with a major public-sector contract.

In 2015, NHS England awarded the company a seven-year contract worth £330 million to provide administrative support to around 39,000 GPs, dentists, opticians and pharmacists.

The intention was to standardise services and reduce costs by 35%.

Problems emerged within a year. Medical records were delayed, payments to healthcare providers were held up and customer support services struggled. The changes included closing local offices while introducing new arrangements, but the transition proved much more complicated than anticipated.

The National Audit Office found that NHS England and Capita had both underestimated the complexity and risks of the work. The report described the resulting service as falling a long way below an acceptable standard.

One particularly disturbing example involved 87 women being incorrectly informed that they were no longer part of the cervical screening programme. The NAO did not identify actual patient harm, but warned that failures in the service had the potential to put patients at risk.

There was also the Army recruitment contract.

In 2012, the Ministry of Defence awarded Capita a £495 million contract as part of a wider £1.36 billion recruitment programme. The aim was to improve recruitment while reducing costs.

Yet Capita missed the Army's annual recruitment targets every year from 2013 onwards during the period examined by the National Audit Office. In 2017–18, recruitment fell around 7,000 below the requirement for regular and reserve personnel.

The Public Accounts Committee subsequently criticised the programme and highlighted the scale of the shortfall.

These examples do not prove that every Capita contract is unsuccessful. The company provides many services across the public and private sectors. But they do demonstrate that problems with large, complicated government contracts have been evident for years.

There is also a newer example. In April 2026, the Government terminated a replacement administration contract for the Royal Mail Statutory Pension Scheme after Capita failed to meet critical transition milestones and IT automation requirements during an 18-month planning period.

The existing service is continuing while the Government considers a new delivery model, so members' benefits are not simply being abandoned. Nevertheless, another major pension administration contract has had to be reconsidered before the planned new arrangement could be delivered.

Fujitsu and the Department for Work and Pensions

The problems are not confined to Capita.

Fujitsu, whose name became internationally associated with the Post Office Horizon scandal, also had a major contract with the Department for Work and Pensions cancelled before it even began.

In February 2010, Fujitsu was selected for a six-year desktop support contract worth approximately £300 million. It was chosen over the incumbent supplier, HP, after a competitive procurement process.

The intention was to transfer responsibility for around 140,000 desktop computers across more than 1,000 sites.

However, the transfer did not go according to plan. Fujitsu failed to meet transition deadlines and the DWP lost confidence in its ability to take over the service. In March 2011, the department cancelled the contract before Fujitsu had completed the handover.

It was an extraordinary outcome. A contract worth hundreds of millions of pounds had been awarded, but the new supplier could not satisfy the department that it could deliver the service.

There is an important distinction here. This was a failed desktop support contract, not the same arrangement as the DWP's older benefit payment systems.

The DWP subsequently undertook a major programme to replace its long-running Fujitsu VME mainframe platform and bring the operation under departmental control. That project was completed in 2021. The reported cost was around £143 million, with projected savings of £257 million by 2028–29.

It is a useful example of a department deciding that it was better to develop and control an important system itself rather than remain dependent on an external supplier.

The Fujitsu question did not end with Horizon

The Post Office Horizon scandal is in a different category from ordinary contract underperformance. It involved the use of faulty accounting software, the wrongful prosecution of sub-postmasters and serious failures of corporate and public accountability.

The consequences have been devastating for those affected.

The scandal also raised questions about why government bodies continued to do business with Fujitsu after serious concerns about Horizon had become public.

In February 2024, the House of Commons Treasury Committee reported that organisations connected with the Treasury had held more than £3.4 billion in Fujitsu contracts active since 2019. Just over £2 billion related to contracts agreed before the landmark 2019 High Court ruling, while around £1.4 billion had been awarded afterwards.

More recent parliamentary scrutiny has shown that the relationship has continued. A parliamentary report published in 2026 found that eight new contracts had been entered into with Fujitsu between May 2024 and September 2025, with a combined value of £362 million. A further 21 contract extensions were also made. Together, the new contracts and extensions amounted to approximately £500 million.

The Government's explanation was that essential services needed to continue while departments arranged replacements or restructured their systems.

That is a practical consideration. It is not always possible to switch off a computer system that handles important public services simply because the supplier has become controversial.

But it raises a wider question about the Government's dependence on a relatively small number of large technology companies. If a department cannot easily replace a supplier, the supplier can become extremely difficult to move away from, even when confidence has been damaged.

The Highland Council experience: Fujitsu, Wipro and bringing IT back in-house

The issue is not confined to central government. Highland Council has had its own long experience of outsourced IT services.

The council had outsourced its computer services for more than 20 years. Fujitsu was the contractor before Wipro took over in 2016.

Wipro secured a five-year contract reported to be worth £50.8 million, after submitting a bid lower than that of the existing contractor. The difference between the bids was reported at around £11 million.

There were subsequent complaints about IT problems affecting council staff and elected members. At one stage, the Press and Journal reported serious concerns about faults that were hampering the council's ability to carry out its work.

It would be unfair, however, to suggest that every problem was simply Wipro's fault. The council was dealing with complicated legacy systems, and the transition involved more than changing the name of the company providing support.

Indeed, a Highland Council report in 2021 acknowledged that outsourcing had provided benefits over the years. But councillors had decided in July 2020 to move towards bringing ICT services back in-house.

The council's stated reasons included the prospect of better value for money, improved service quality and greater flexibility to meet changing demands.

The programme was called Project Dòchas. The first Wipro field services and service desk staff transferred to the council in October and November 2021 under employment transfer arrangements.

This was not an overnight change. It required recruitment, restructuring, planning and the transfer of staff and responsibilities.

The Highland experience is particularly interesting because it demonstrates that bringing a service back in-house is not necessarily a rejection of everything that an external contractor has done. It can be a recognition that a public body needs to retain greater knowledge, control and flexibility over an essential service.

The question for councils and taxpayers is whether the final in-house arrangement delivers the expected improvements. That needs to be judged by looking at actual costs, service standards and performance, rather than simply assuming that either outsourcing or in-house provision is automatically better.

Atos, benefit assessments and another early exit

Another company familiar to anyone following public services is Atos.

The company was responsible for Work Capability Assessments for people claiming Employment and Support Allowance. The assessments became highly controversial, with widespread criticism from claimants, disability organisations and politicians.

In March 2014, the DWP and Atos agreed to end the contract six months early. The Work and Pensions Committee recorded that the Government had lost confidence in Atos's ability to perform the work required.

Atos also said that it had decided not to bid for the replacement contract. It referred to the difficult working environment and the reputational damage associated with the service.

Again, this was not simply a case of a company walking away without explanation. The relationship between the department, contractor and the people being assessed had become deeply problematic.

It illustrates the particular dangers of outsourcing decisions that affect people's incomes, health and ability to manage daily life. A contract can be judged against performance targets, but the human consequences of poor service may be much harder to measure.

Carillion: when the contractor itself collapses

Perhaps the most dramatic warning came in January 2018, when Carillion went into liquidation.

The company provided construction, facilities management and other services to government departments, hospitals, schools, the armed forces and transport organisations.

The National Audit Office estimated that Carillion had around 420 public-sector contracts when it collapsed. Thousands of employees and subcontractors were affected, and public bodies had to work urgently to keep services running.

A parliamentary inquiry afterwards criticised the Government's approach to outsourcing. It argued that the priority had too often been to secure the lowest possible price while transferring unacceptable financial risks to contractors.

The collapse demonstrated another weakness in the system. It is not enough for a government department to ask whether a company can deliver a contract today. It must also consider whether the company is financially strong enough to continue delivering it over several years.

The Government was able to maintain most services after Carillion's collapse, and the parliamentary committee gave credit for the contingency arrangements. But the episode showed how much public services can depend on the financial health of private companies.

Is the Government still learning the lessons?

There are further questions about the Government's continuing use of outsourced services.

The Government Shared Services programme aims to modernise and standardise the way departments handle functions such as payroll, human resources and finance. The Cabinet Office has referred to potential benefits of around £4.3 billion over 15 years across five groups of departments.

But the figures need careful interpretation. In evidence to the Public Accounts Committee in 2026, the Cabinet Office explained that the £4.3 billion was an estimate across all five groups, while the National Audit Office had calculated a net lifetime benefit of around £1 billion for the three groups receiving ring-fenced funding.

One of the groups, known as Synergy, uses Capita to provide back-office services. Other departments have chosen different approaches, including in-house provision.

The important point is that outsourcing is still being used as part of the Government's modernisation plans, despite the history of problems with large contracts.

That does not mean the programme will fail. Nor does it mean that private companies should never provide public services. Specialist suppliers can bring skills, investment and economies of scale that individual departments may struggle to provide themselves.

But the business case must be realistic, the responsibilities must be clear, and the Government must retain enough expertise to challenge a supplier when things go wrong.

Why does the lowest bid so often become such an important consideration?

One of the recurring themes in these examples is the promise of savings.

A company bids for a contract, often promising to reorganise services, introduce new technology, reduce staffing costs and deliver the work more cheaply.

The public body sees the potential savings and awards the contract.

But what happens if the work proves more complicated than expected? What if the computer systems are older and less reliable than the tender documents suggested? What if experienced staff leave, the new supplier cannot recruit enough people, or the promised technology is delayed?

The public body may find that it has lost much of the knowledge needed to run the service itself. It can then become dependent on the contractor to solve problems that the contractor was originally appointed to prevent.

The National Audit Office's findings on the NHS primary care contract are particularly revealing. Both NHS England and Capita underestimated the complexity of the service. The contract encouraged changes and office closures, but the practical consequences were not properly understood.

That is not just a supplier problem. It is a procurement and management problem.

There is also a danger in assuming that a very low bid is automatically a good deal. A contractor may have perfectly legitimate reasons for offering a competitive price. But public bodies need to understand how the promised savings will be achieved and whether the supplier has the resources and experience to deliver them.

If the price is based on assumptions that prove unrealistic, the taxpayer may end up paying in other ways: through emergency support, contract changes, delayed services, replacement systems or the cost of bringing work back in-house.

Did the companies mislead government, or did government buy the wrong promises?

It would be wrong to conclude from these examples that every contractor deliberately misled the Government.

A company can make a genuine mistake in estimating the difficulty of a contract. A public body can also provide incomplete information, set unrealistic deadlines or fail to understand its own systems.

In some cases, both sides appear to have underestimated the work involved.

But that makes the Government's responsibility even greater. It is the public body spending taxpayers' money and ultimately responsible for ensuring that essential services continue.

There should be proper scrutiny of how bids are evaluated, what assumptions are made, how risks are shared and what happens when milestones are missed.

There should also be a realistic exit plan. A department must know how it will continue operating if a supplier fails, goes bust or becomes impossible to work with.

The Highland Council experience is worth remembering here. Bringing ICT back in-house required planning, investment and the transfer of staff. It was not a simple or immediate solution. But it gave the council an opportunity to rebuild its own capacity and retain greater control over a service on which almost every part of its operation depends.

The real cost of getting it wrong

The public does not necessarily care whether a computer system is operated by a civil servant or a private contractor. What matters is whether it works.

A pensioner wants their pension paid on time. A GP wants medical records and payments processed correctly. A soldier wants a recruitment system that works. A council employee needs reliable access to the systems required to serve the public.

When these arrangements fail, the consequences are not confined to contract managers and boardrooms. They are felt by ordinary people who may have little ability to challenge the organisations responsible.

There is also a wider issue of public-sector capability. If departments continually outsource specialist work, they risk losing the knowledge and experience needed to manage that work themselves. Once that expertise disappears, the public body may become increasingly dependent on the very companies it is supposed to supervise.

Outsourcing can work. It can provide genuine savings and access to skills that government does not need to maintain permanently. But the repeated examples of troubled contracts suggest that the public sector has sometimes placed too much faith in promised savings and too little emphasis on the practical difficulties of delivery.

The question is not whether everything should be brought back in-house. It is whether government has become too willing to sign large contracts without fully understanding what it is buying, how it will be delivered and what it will do if things go wrong.

After the DWP's cancelled Fujitsu contract, the Carillion collapse, the NHS and Army recruitment problems involving Capita, the Highland Council's decision to rebuild its own IT service, and the latest pension administration difficulties, it is reasonable to ask how many lessons have actually been learned.

A contract can look like a saving on the day it is signed. The real test is what it costs the taxpayer, and what it delivers to the public, over the whole of its life.

Sources and further reading if you want more details on the projects mentioned.

Civil Service pensions and Capita
National Audit Office – Cabinet Office must improve customer experience in Civil Service Pension Scheme

https://www.nao.org.uk/press-releases/cabinet-office-must-improve-customer-experience-in-civil-service-pension-scheme/

UK Parliament – Question about further interest-free loans for civil servants awaiting pension payments

https://questions-statements.parliament.uk/written-questions/detail/2026-06-25/13404/

UK Parliament – Capita's performance against the Civil Service Pension Recovery Plan

https://questions-statements.parliament.uk/written-questions/detail/2026-08-28/22718/

Cabinet Office – Annual Report and Accounts 2025–26

https://assets.publishing.service.gov.uk/media/6ad23dfae5db84746b47975c/46.36_CO_ARA_25-26_00-Book_v10_ELAY.pdf

UK Parliament – Royal Mail Statutory Pension Scheme deficit update

https://questions-statements.parliament.uk/written-questions/detail/2026-02-11/112896/

Note: this last parliamentary link concerns the scheme's deficit. It is not the best source for the termination of Capita's administration contract, so I would not use it to support that particular claim.
Capita and public services
National Audit Office – NHS England's management of the primary care support services contract with Capita

https://www.nao.org.uk/reports/nhs-englands-management-of-the-primary-care-support-services-contract-with-capita/

House of Commons Public Accounts Committee – Capita's contracts with the Ministry of Defence

https://publications.parliament.uk/pa/cm201719/cmselect/cmpubacc/1736/173606.htm

National Audit Office – Investigation into the British Army's Recruiting Partnering Project

https://www.nao.org.uk/press-releases/investigation-into-the-british-armys-recruiting-partnering-project/
Fujitsu and DWP
Computer Weekly – DWP cancelled £300m Fujitsu deal over transition deadline failures

https://www.computerweekly.com/news/1280097324/DWP-cancelled-300m-Fujitsu-deal-over-transition-deadline-failures

Computer Weekly – DWP completes in-house VME replacement project

https://www.computerweekly.com/news/252498000/DWP-completes-in-house-VME-replacement-project

House of Commons Treasury Committee – More than £3.4 billion of Fujitsu contracts active with Treasury-affiliated organisations since 2019

https://committees.parliament.uk/committee/158/treasury-committee/news/199838/more-than-34-billion-of-fujitsu-contracts-active-with-treasuryaffiliated-organisations-since-2019/

House of Commons Business and Trade Committee – Post Office Horizon scandal: Justice for sub-postmasters

https://publications.parliament.uk/pa/cm5901/cmselect/cmbeis/1598/report.html
Highland Council and Wipro
Highland Council – Project Dòchas progress report, November 2021

https://www.highland.gov.uk/download/meetings/id/79134/15_project_d%C3%B2chas_progress_report

Highland Council – Transformation Directorate Service Plans 2021/22

https://www.highland.gov.uk/download/meetings/id/78243/4c_directorate_service_plans_202122_-_transformation

Press and Journal – Demand for Highland Council IT provider to answer for serious service faults

https://www.pressandjournal.co.uk/fp/news/highlands-islands/1591635/demand-for-highland-council-it-provider-to-answer-for-the-serious-and-severely-hampering-faults-to-service/
Other examples
House of Commons Work and Pensions Committee – Employment and Support Allowance and Work Capability Assessments

https://publications.parliament.uk/pa/cm201415/cmselect/cmworpen/302/30208.htm

House of Commons Public Administration and Constitutional Affairs Committee – After Carillion: Public sector outsourcing and contracting

https://publications.parliament.uk/pa/cm201719/cmselect/cmpubadm/748/74803.htm

National Audit Office – Investigation into the Government's handling of the collapse of Carillion

https://www.nao.org.uk/reports/investigation-into-the-governments-handling-of-the-collapse-of-carillion/

Cabinet Office – Government Shared Services response to the Public Accounts Committee, 3 June 2026

https://committees.parliament.uk/publications/53472/documents/298846/default/