Cairngorm funicular re-opening is postponed

28th August 2021

Photograph of Cairngorm funicular re-opening is postponed

The current phase of engineering works to strengthen the 1.9km viaduct that supports the railway track began in April 2021, with the aim of returning the funicular to service early next year.

However, despite strong progress made in tough conditions, HIE has concluded that the planned timescale now needs to extend into the second half of 2022.

The mountain resort will stay open throughout winter, with skiers and snowboarders able to access the slopes using nine ski tows that will run every day when weather conditions are suitable.

According to the development agency, several factors have combined to lengthen the funicular reinstatement programme.

These include technical challenges associated with designing and implementing effective solutions to an existing structure, as opposed to a new build.

In addition, progress has been hampered by COVID impacts and by extreme weather, particularly blizzard conditions in the spring.

Extra effort has also been required to source vital construction materials that are currently in short supply across the UK.

HIE interim chief executive Carroll Buxton said this combination of challenges had made rescheduling the works inevitable.

"Cairngorm Mountain Estate is a great visitor attraction that plays an important role in the local economy.," she said.

"The funicular has been a key element of what draws people to Cairngorm and it will be again, once these works are completed.

“We've always been upfront in describing the reinstatement programme as one of the most complex and difficult civil engineering projects in Scotland.

“As well as managing technical challenges, the team has to take great care to protect the mountain environment, and deal with difficult terrain and extreme weather conditions that can quickly become hazardous.

“The original schedule was very ambitious, even without the impacts of the pandemic lasting as long as they have and before the more recent problems in sourcing construction materials of suitable quality.

“With limited time available to complete these works before winter, postponement has become inevitable."

The funicular opened in 2001 but was taken out of service in 2018 after an engineers' inspection identified structural defects that raised safety concerns.

More detailed inspection and design work followed before the decision to reinstate the funicular was announced last October by the Scottish Government, as part of a £20.5m business case that includes other priority investments to strengthen Cairngorm Mountain’s year-round appeal.

The business case assessed alternatives to reinstatement before reaching its conclusions, including removing the structure, and replacing it with alternative uplift.

“We’re now working with our designers and contractors on a revised schedule for the remainder of the project,” Ms Buxton added.

“Harsh mountain conditions mean that all work will need to halt over winter and resume next spring. To ensure safety, there also needs to be a period of testing and certification at the end of the programme, so our current expectation is that the funicular can be relaunched in autumn 2022.

“Clearly, a longer timescale will also have a financial impact. We’ll be reviewing costs very carefully and will publicly confirm a revised budget as soon as it’s possible to do so.”

Confirming its commitment to the mountain resort, HIE has also approved up to £780,000 for an extensive refurbishment of the Ptarmigan building that sits on the plateau and includes the UK’s highest restaurant, a shop, exhibition space and viewing platforms.

Following competitive tender, resort operator Cairngorm Mountain (Scotland) Ltd (CMSL) has awarded a contract for the first phase of the Ptarmigan works to Simpson Builders Ltd, based in Beauly. The refurbishment is due to start at the end of August and be completed by the end of 2021.

 

Related Businesses

 

Related Articles

Cairngorm Funicular Remedial Works ProgressingThumbnail for article : Cairngorm Funicular Remedial Works Progressing
A programme of remedial works to bring Scotland's only funicular railway back into service at Cairngorm Mountain is entering a new phase during week beginning Monday 15 April.   With the snowsports season now over, multiple teams from contractor Balfour Beatty, appointed by Cairngorm Estate owner Highlands and Islands Enterprise (HIE), are set to be deployed on the mountainside.  
SRUC and HIE partnership to benefit rural economyThumbnail for article : SRUC and HIE partnership to benefit rural economy
The five-year agreement between Scotland's Rural College (SRUC) and Highlands and Islands Enterprise (HIE) will also play a major role in contributing to regional economic growth.   The signing of the agreement, by Professor Wayne Powell, Principal and Chief Executive of SRUC, and HIE Chief Executive Stuart Black, follows the official opening of SRUC's Rural and Veterinary Innovation Centre (RAVIC), a valued addition to SRUC’s School of Veterinary Medicine, in Inverness by HRH the Princess Royal.  
New Orkney Whisky Distillery In Moves To Create Jobs And Lower EmissionsThumbnail for article : New Orkney Whisky Distillery In Moves To Create Jobs And Lower Emissions
Deerness Distillery Ltd has secured £246,000 from Highlands and Islands Enterprise (HIE) for the £820,000 development.   Construction is underway at the distillery, which was founded by husband-and-wife team Stuart and Adelle Brown.  
Cuts And More Cuts But Still Cash For Arts In Highland - £30,000 For TapestriesThumbnail for article : Cuts And More Cuts But Still Cash For Arts In Highland - £30,000 For Tapestries
The Co-Chairs of the Inverness Castle Delivery Group, Fergus Ewing MSP and Cllr Ian Brown, are delighted to announce the award of £30,000 from Highlands and Islands Enterprise (HIE) in support of framing the 57 panels that will form the Tapestry of the Highlands and Islands.   This financial commitment from HIE has contributed significantly to the preservation of the 57 panels created by communities across the Highlands and Islands, of which 32 will be included in the first exhibition as part of the Inverness Castle Experience.  
£24.5m To Secure £350m Inward InvestmentThumbnail for article : £24.5m To Secure £350m Inward Investment
Sumitomo Electric UK Power Cables Ltd plans to establish major operations in the region, supplying high voltage cables to the growing offshore wind energy sector.   A funding package has been agreed to secure an estimated £350m in inward investment for Scotland, based in the Highlands.  
Property Demand Study Launched By Highlands and Islands Enterprisie
As part of the study, businesses, community groups and social enterprises with future land or property plans are encouraged to complete a short survey by 22 March 2024.   Whether it's interest in land for sale or space to lease, HIE is keen to hear from organisations already based in the region as well as from those that are considering locating a business to the area.  
Shetland Engineering Firm Expands And Creates JobsThumbnail for article : Shetland Engineering Firm Expands And Creates Jobs
L&M Engineering has secured a grant of £58,914 from Highlands and Islands Enterprise (HIE) for the development, which is set to boost business turnover by £1.2m and create two jobs over the next three years.   The company is diversifying its operations to cater for additional aquaculture markets.  
Region's Businesses Value Community Links
Most businesses in the Highlands and Islands consider their links with the local community as either equal to or more important than their profitable growth.   This is one of the key findings of the most recent rural business survey commissioned by Highlands and Islands Enterprise (HIE) in partnership with South of Scotland Enterprise (SOSE).  
Support Programme Takes Young Entrepreneurs To The Next Level
Dynamic business support programme, IMPACT30, is aimed at nurturing and empowering the next generation of innovative leaders.   The fully funded programme is for people aged under 35 in a young enterprise and in a key decision-making role.  
Power Boost For Off-grid Island
A project to increase electricity supply and reduce emissions on a west coast island has been awarded more than £25,000 by HIE.   The HIE funding is being used to replace and upgrade high voltage transformers and other associated equipment to enable a major upgrade of the renewable energy supply on the Isle of Muck.