Cairngorm funicular re-opening is postponed

28th August 2021

Photograph of Cairngorm funicular re-opening is postponed

The current phase of engineering works to strengthen the 1.9km viaduct that supports the railway track began in April 2021, with the aim of returning the funicular to service early next year.

However, despite strong progress made in tough conditions, HIE has concluded that the planned timescale now needs to extend into the second half of 2022.

The mountain resort will stay open throughout winter, with skiers and snowboarders able to access the slopes using nine ski tows that will run every day when weather conditions are suitable.

According to the development agency, several factors have combined to lengthen the funicular reinstatement programme.

These include technical challenges associated with designing and implementing effective solutions to an existing structure, as opposed to a new build.

In addition, progress has been hampered by COVID impacts and by extreme weather, particularly blizzard conditions in the spring.

Extra effort has also been required to source vital construction materials that are currently in short supply across the UK.

HIE interim chief executive Carroll Buxton said this combination of challenges had made rescheduling the works inevitable.

"Cairngorm Mountain Estate is a great visitor attraction that plays an important role in the local economy.," she said.

"The funicular has been a key element of what draws people to Cairngorm and it will be again, once these works are completed.

“We've always been upfront in describing the reinstatement programme as one of the most complex and difficult civil engineering projects in Scotland.

“As well as managing technical challenges, the team has to take great care to protect the mountain environment, and deal with difficult terrain and extreme weather conditions that can quickly become hazardous.

“The original schedule was very ambitious, even without the impacts of the pandemic lasting as long as they have and before the more recent problems in sourcing construction materials of suitable quality.

“With limited time available to complete these works before winter, postponement has become inevitable."

The funicular opened in 2001 but was taken out of service in 2018 after an engineers' inspection identified structural defects that raised safety concerns.

More detailed inspection and design work followed before the decision to reinstate the funicular was announced last October by the Scottish Government, as part of a £20.5m business case that includes other priority investments to strengthen Cairngorm Mountain’s year-round appeal.

The business case assessed alternatives to reinstatement before reaching its conclusions, including removing the structure, and replacing it with alternative uplift.

“We’re now working with our designers and contractors on a revised schedule for the remainder of the project,” Ms Buxton added.

“Harsh mountain conditions mean that all work will need to halt over winter and resume next spring. To ensure safety, there also needs to be a period of testing and certification at the end of the programme, so our current expectation is that the funicular can be relaunched in autumn 2022.

“Clearly, a longer timescale will also have a financial impact. We’ll be reviewing costs very carefully and will publicly confirm a revised budget as soon as it’s possible to do so.”

Confirming its commitment to the mountain resort, HIE has also approved up to £780,000 for an extensive refurbishment of the Ptarmigan building that sits on the plateau and includes the UK’s highest restaurant, a shop, exhibition space and viewing platforms.

Following competitive tender, resort operator Cairngorm Mountain (Scotland) Ltd (CMSL) has awarded a contract for the first phase of the Ptarmigan works to Simpson Builders Ltd, based in Beauly. The refurbishment is due to start at the end of August and be completed by the end of 2021.

 

Related Businesses

 

Related Articles

Highlands and Islands Enterprise (HIE) will invest up to £24 million at Kishorn Port
A multi-million pound investment is being made in one of Scotland's most strategically important ports.   Highlands and Islands Enterprise (HIE) will invest up to £24 million at Kishorn Port in the west Highlands to enhance its capacity and capabilities, with an expanded dry dock and land reclamation enabling the manufacture of floating offshore wind foundations.  
Commercial diver training company in Argyll to scope expansionThumbnail for article : Commercial diver training company in Argyll to scope expansion
A commercial diver training company in Argyll is exploring the potential to expand the business to include closed bell diver training.   Dunoon based Professional Diving Academy (PDA) has secured £5,000 from Highlands and Islands Enterprise (HIE) to help cover associated market assessment consultancy costs.  
New green training skills facilities open in Stornoway - Fosgladh Goireasan Trèanaidh Sgilean Uaine ann an SteòrnabhaghThumbnail for article : New green training skills facilities open in Stornoway - Fosgladh Goireasan Trèanaidh Sgilean Uaine ann an Steòrnabhagh
The new, state-of-the-art Technology and Innovation Centre at UHI North, West and Hebrides' Stornoway campus officially opened following a £2.3m investment.   It is the first capital project to be delivered under the Islands Growth Deal, a ten-year package that seeks to drive economic growth and the creation of sustainable jobs across Shetland, Orkney and the Outer Hebrides.  
Operator sought for new innovation centreThumbnail for article : Operator sought for new innovation centre
Highlands and Islands Enterprise (HIE) is looking to contract a specialist operating company to run a new multi-million-pound innovation centre under development in Moray to support manufacturing.   The three-year contract will involve developing and managing the service offering of the new Manufacturing Innovation Centre Moray (MICM), as well as stakeholder engagement, marketing and promotion of the facility.  
Innovative project at Moray carrot firm will lead to growthThumbnail for article : Innovative project at Moray carrot firm will lead to growth
An innovation project by a major carrot grower in Moray is forecast to strengthen the company's position and create more jobs.   Family-run firm, AA Carrots Ltd grows carrots on 400 acres of land around Moray and Aberdeenshire, of which around half is organic.  
Highlands and Islands supply chain spotlight at All-Energy 2025
More than 30 of the region's businesses are took centre stage at the UK's biggest renewable energy exhibition and conference at Glasgow’s SEC 14-15 May.   Global experts, academics and innovators gathered at the annual All-Energy exhibition and conference to advance Scotland’s goal of net zero and achieving a sustainable future.  
£100bn potential of ‘transformational' projects in the Highlands and IslandsThumbnail for article : £100bn potential of ‘transformational' projects in the Highlands and Islands
The scale of transformational opportunity facing the Highlands and Islands economy has been quantified for the first time in a new report.   The study reports 251 planned development projects in the economic pipeline of what it refers to as regional transformational opportunities (RTOs).  
Region's clean energy credentials attracts UK Government visit
The renewable energy credentials of the Highlands and Islands has attracted a visit this week from a top UK Government official leading the drive to secure clean energy by 2030.   Chris Stark leads the UK Government's Mission for Clean Power by 2030, in the Department of Energy Security and Net Zero (DESNZ).  
Planning application for Inverness Campus Marks Final PhaseThumbnail for article : Planning application for Inverness Campus Marks Final Phase
Highlands and Islands Enterprise (HIE) has submitted an application for planning permission in principle to make way for the second and final phase of development at Inverness Campus.   Most of the development in the proposals is for commercial floorspace, with other elements including hotel and academic space.  
Highland food and drink sector urged to apply for support programmeThumbnail for article : Highland food and drink sector urged to apply for support programme
Highland food and drink supply chain or manufacturing businesses are being encouraged to take advantage of fully funded one-to-one technology advice and funding support.   The support is part of the second phase of Food and Drink TechHUB, which itself is part of the Northern Innovation Hub (NIH), a multi-million-pound initiative led by Highlands and Islands Enterprise (HIE) under the Inverness and Highland City-Region Deal.