Lifting The Lid On The Dismantling Of Dounreay's Material Test Reactor
11th February 2022

Original internal steelwork is being stripped out of the Dounreay Material Test Reactor (DMTR) as it continues preparations for a major skyline change.
Original internal steelwork is being stripped out of the Dounreay Material Test Reactor (DMTR) as it continues preparations for a major skyline change.
DMTR became Scotland's first operating reactor when it achieved criticality in 1958. It was used for irradiation tests on materials until its shutdown in 1969. In 2018 a contract was awarded to Cavendish Nuclear Limited to dismantle and demolish the reactor. The fuel, heavy-water coolant and some redundant plant have been removed, leaving the reactor vessel, supports and containment shell ready for final demolition.
Work is currently focused on the fuel element storage block (FESB), where irradiated fuel was stored after its removal from the reactor. The 8.9 tonne lid, known as the top plate, mezzanine floor and steel beams surrounding the top of the 5m tall FESB have now all been removed.
DSRL Project Manager, Fiona Forbes, said:When DMTR was constructed in the late 1950s, it was technologically advanced and innovative. Sixty years on, its demolition will be a major milestone for the site. This is the first time that the top plate has been lifted since the early 1970s.
The work is being carried out by a team of up to 50 personnel including local firms, Cavendish and DSRL staff, who are working together to move the project on in a safe and secure way.
Whilst all deconstruction activities are currently inside, demolition of the reactor will be the biggest change to the Dounreay skyline since decommissioning began, and a major strategic achievement.
Using the waste hierarchy, efforts are being made to maximise materials for recycling and identify options for sentencing the metal as low level waste.
The next phase of work, to surround the FESB with an atmosphere-controlled containment structure, is underway and will enable operators to demolish the reinforced concrete block. This is expected to be carried out using a remotely-operated demolition machine in the coming months.
Related Businesses
Related Articles
In April 2021, Dounreay Site Restoration Ltd (DSRL) became a subsidiary company of the Nuclear Decommissioning Authority (NDA) Group. The Cavendish Dounreay Partnership ceased.
Three long-serving NDA group employees have been awarded honours by Her Majesty The Queen in the Platinum Jubilee Honours List for services to the nuclear industry and their local communities. Cath Giel, Communications and Stakeholder Relations Director at the LLW Repository Site in Cumbria until her retirement earlier this year, was made a Member of the Most Excellent Order of the British Empire (MBE).
A celebration of innovation at Dounreay held recently, recognising how innovation is part of everything they do at the site to achieve our mission. On the day, we celebrated the many successes we have achieved in our approach to decommissioning.
Two large redundant items that were removed from Dounreay's facilities have now left the site for disposal or diversion, opening up new waste routes. Dounreay in partnership with Nuclear Waste Services and its contractor Cyclife first trialled an alternative treatment option for the site's metallic waste in 2019, when 66 tonnes of redundant metal equipment were sent to Cyclife's specialist facility for recycling.
A robot has successfully surveyed an underground radioactive ventilation duct in Dounreay's redundant laboratories. Dounreay Site Restoration Ltd (DSRL) and the Robotics and Artificial Intelligence in Nuclear (RAIN) Hub are working together to develop a robot capable of accessing areas that are inaccessible or unsafe for humans to work in.
This strategy sets out the NDA group's five-year path to becoming a leader in sustainability. Transforming nuclear legacies into sustainable opportunities is the focus of the Nuclear Decommissioning Authority (NDA) group's new Sustainability Strategy 2022.
This report published on 28 March 2022 summarises the gender pay gap for the NDA group as a whole. Within the individual organisations that make up the group: Nuclear Decommissioning Authority Sellafield Limited Magnox Limited Dounreay Site Restoration Limited Low Level Waste Repository Limited Radioactive Waste Management Limited International Nuclear Services Limited Direct Rail Services Limited.
A new approach to decommissioning the Vulcan nuclear site next door to Dounreay by the Ministry of Defence has been been indicated. It was confirmed at Wednesday's meeting of Dounreay Stakeholder Group (DSG) that the Nuclear Decommissioning Agency was being considered to take over the work.
The details of particle finds on Dounreay foreshore has been updated. See full details at - https://www.gov.uk/government/publications/radioactive-particles-in-the-environment-around-dounreay/dounreay-foreshore-particle-finds-2021.
Particles are fragments of irradiated nuclear fuel discharged to sea as a result of historic practices in reprocessing. Used fuel from the reactors on site and other research reactors in Britain and abroad was recycled in the site's reprocessing facilities.