Dounreay low level waste vaults begin to accept waste
23rd May 2015
A major programme milestone has been achieved with the placement of the first low level waste disposed into the new Low Level Waste Facilities at Dounreay.
DSRL were granted planning permission to construct up to six vaults in April 2009. Phase one vaults; a low level waste vault and a demolition low level vault was constructed to accommodate waste accumulated on the site arising from previous operations and from decommissioning operations. The construction of this stage of the vaults was ceremoniously celebrated in April 2014.
On April 24 2015, active commissioning began at the Encapsulation Plant where one half-height ISO container packed with low level waste was filled with grout. This followed a successful grouting process demonstration with inactive waste to SEPA on April 14.
Packages of demolition low level waste have also been transferred from storage on the Dounreay site to the demolition low level waste vault and the first grouted half height ISO container has been disposed of at the low level waste vault, starting the active commissioning of the process and operation of the new Low Level Waste facilities.
DSRL has now confirmed that phase two will also be required and will comprise of a further two low level waste vaults, to accommodate further waste from decommissioning.
To meet the site decommissioning requirements phase two would be required by 2020, however DSRL is planning to bring the construction programme forward within the overall portfolio of site projects.
Work continues to assess the waste arising rates and total waste volumes and this will influence the programme for construction and operation of the vaults and any requirement for phase three.
DSRL remains committed to waste avoidance and minimisation and to the safe decommissioning of the Dounreay site.
Related Businesses
Related Articles
He joins from AtkinsRealis, where he was market director and delivery lead for its nuclear decommissioning and waste services business, and officially takes up the post today (18 November 2024), He succeeds John Grierson who has served as interim MD since May. NRS CEO Rob Fletcher said, "I am very pleased that Dave Wilson has agreed to join the team at Dounreay.
The Nuclear Decommissioning Authority group have announced five organisations as winners of this year's supply chain awards. Morgan Sindall Infrastructure, The Decommissioning Delivery Partnership, PA Consulting, Antech and The Higher Activity Waste Thermal Treatment Tranche 1 Team are the big winners in this year's supply chain awards.
Find out what has been happening at UKAEA in our monthly newsletter. Read about our recent activities and upcoming events.
With a degree in electrical and electronic engineering and a keen interest in the nuclear sector, Anouschka knew Sellafield would be the best place for her to begin her career in the industry. That career has already seen her relocate from Sheffield to Cumbria and scooping the title of Sellafield Ltd Graduate of the Year.
More than 140 graduates have started at Sellafield Ltd. Over 140 graduates have just started their exciting careers with the company in a range of business and technical disciplines, supporting Sellafield Ltd in its mission to create a clean and safe environment for future generations.
Find out what has been happening at UKAEA in our monthly newsletter. Read about our recent activities and upcoming events.
The Nuclear Decommissioning Authority (NDA) group has on 26 September 2024 published its 2023 to 2024 socio-economic report detailing a record investment in projects across the UK. Over the last five years, the NDA group has invested £60 million in projects that enable permanent and sustainable change in its site communities, leveraging many millions more from partners.
Today, the ponds inside the Thermal Oxide Reprocessing Plant (or as we like to call it, Thorp) are used to store nuclear fuel that has been used in the UK's 7 operational nuclear reactors. Before taking on this new mission, Thorp reprocessed 9,000 tonnes of used nuclear fuel from around the world, generating an estimated £9 billion in revenue for the UK over 2 decades.
Over 100 graduates join the Nuclear Decommissioning Authority group today as applications open for 2025. As applications open for 2025, the Nuclear Decommissioning Authority (NDA) group also welcomed its largest ever cohort of graduates today, with more than 100 new recruits ready to support delivery of one of the world's most important environmental programmes.
In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility. In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility.