Highest Hazard Materials Disposed Of At Dounreay

6th August 2016

Photograph of Highest Hazard Materials Disposed Of At Dounreay

The destruction of one of the highest hazards remaining in the Nuclear Decommissioning Authority (NDA) estate has been completed at Dounreay.

Around 68 tonnes of highly radioactive liquid metal coolant was removed from the Dounreay Fast Reactor (DFR) and safely destroyed over a ten year period. The liquid metal, a blend of sodium and potassium called NaK, was used to remove heat from the reactor's nuclear fuel.

Dounreay used a specially built plant and removal system to safely convert the NaK to hydrogen gas and salt water. Handling the material is a particularly complex technical challenge as it reacts vigorously when exposed to air or water, eventually catching fire. This meant that it had to be kept under a nitrogen gas blanket to prevent reactions.

Reactors Director, Ken Heider of CH2M Hill, said: "The Dounreay team, in partnership with our supply chain, worked extremely hard over a long time to remove and convert the highly radioactive NaK into safe products. Most importantly, our highly skilled team delivered the work safely and in compliance with our environmental authorisations.

Pete Lutwyche, NDA Chief Operating Officer, added: "This was one of the highest radiological hazards in the NDA estate, as well as a significant conventional safety hazard.

"The difficulty of this task can't be understated, and I welcome the news that this work is complete. Everyone involved should be proud of their achievement."

The bulk removal of NaK was completed in 2012 and, since then, work has been underway to remove the last of the coolant from the pipework and base of the structure. This final stage was extremely challenging because the hazardous material was difficult to access.

Detailed technical solutions, including remotely drilling through parts of the reactor, had to be developed. The team also had to work with outdated original drawings which, as the reactor had been modified over several decades, did not give a full reflection of the plant they were working with.

It is the latest achievement at Dounreay as work progresses on one of Europe's most complex closure programmes. Focus now turns to the removal of around 1,000 breeder elements still in the DFR reactor vessel. This must be completed before cleaning and removing the reactor and its nine kilometres of cooling pipework.

DSRL operates under contract to the Nuclear Decommissioning Authority (NDA) and is a wholly-owned subsidiary of the Cavendish Dounreay Partnership Ltd (CDP), a consortium of Cavendish Nuclear, CH2M and AECOM. It is funded by the NDA to deliver the Dounreay site closure programme.

To find out more about CH2M Hill see their web site at www.ch2m.com

 

Related Businesses

 

Related Articles

15/4/2026 : Other Public Services

Buried in the Sand: The Radioactive Legacy Washing Up on Britain's Shores

It sounds like something from a Cold War thriller, not a family day out: fragments of radioactive material, invisible to the naked eye, quietly lying in the sand.  Yet for decades, beaches near Dounreay and Sellafield have been the final resting place for exactly that.  

1/4/2026 : Advisory / Counseling Services

 
Hunterston B nuclear power station has transferred to the NDA

Hunterston B nuclear power station in North Ayrshire has transferred ownership from EDF to the Nuclear Decommissioning Authority.   Today, Hunterston B nuclear power station in North Ayrshire has transferred ownership from EDF to the Nuclear Decommissioning Authority (NDA) to be decommissioned by its subsidiary Nuclear Restoration Services (NRS).  

19/3/2026 : Advisory / Counseling Services

Two weeks to go: Hunterston B achieves licence milestone

Office for Nuclear Regulation grant a site licence to Nuclear Restoration Services (NRS) - major milestone that will enable the site's decommissioning.   With exactly two weeks until Hunterston B becomes the UK's first Advanced Gas-cooled Reactor (AGR) site to transfer into UK Government ownership, a major milestone that will enable the nuclear power station’s decommissioning has been achieved.  

14/3/2026 : Other Public Services

 
Why Repaint a Building Marked for Demolition? The Practical Logic Behind the Dounreay Dome's Fresh Coat

At first glance, the decision to repaint the iconic Dounreay dome as it is a structure already scheduled for demolition seems baffling.  Why spend money maintaining a building that will soon be torn down? Why refresh the exterior of a landmark whose days are numbered? The answer is far more practical than it appears.  

11/3/2026 : Advisory / Counseling Services

 
Nuclear project academy goes national

The Nuclear Decommissioning Authority (NDA) is launching a UK‑wide training programme to support the development of project professionals across the nuclear sector.   The One NDA Project Academy is an expansion of a programme initially launched at Sellafield in 2016.  

24/2/2026 : Advisory / Counseling Services

NDA publishes latest nuclear decommissioning strategy

NDA publishes latest strategy setting out long term roadmap for the safe and secure decommissioning of the UK's legacy nuclear sites.   The Nuclear Decommissioning Authority (NDA) has published its latest strategy, setting out its long term roadmap for the safe and secure decommissioning of the UK's legacy nuclear sites.  

3/2/2026 : Other Public Services

 
From Headlines to Hidden Lines - Dounreay's Quiet Legacy of Radioactive Particles

For years, radioactive particles discovered near Dounreay were headline news.  Each find triggered a press release, picked up by local and national outlets, reminding communities that the nuclear legacy was still with us.  

22/1/2026 : Advisory / Counseling Services

 
Decommissioning underpins ambitions for homegrown clean energy

NDA group puts decommissioning at the forefront of the agenda at Nuclear Week in Parliament.   The Nuclear Decommissioning Authority (NDA) group put decommissioning at the forefront of the agenda at this year's Nuclear Week in Parliament, as the essential foundation underpinning the Government's ambition to become a clean energy superpower.  

17/12/2025 : Advisory / Counseling Services

UKAEA and NDA strengthen collaborative approach to decommissioning

UKAEA and NDA sign formal agreement to share knowledge and expertise, advancing the delivery of major decommissioning programmes.   Memorandum of Understanding agreed to enable and encourage knowledge sharing, and improve best practice.  

3/12/2025 : Other Public Services

 
TAE Technologies and UKAEA partner to commercialise fusion tech

Joint venture to develop neutral beams for fusion and non-fusion applications, creating high-skilled jobs and establishing a critical supply chain.   TAE Technologies, a leading US private fusion energy firm with over 25 years at the forefront of scientific innovation, today announces a bilateral and reciprocal investment commitment with the United Kingdom's national fusion laboratory, the UK Atomic Energy Authority (UKAEA) to commercialise TAE's proprietary particle accelerator technology for the global market.