Dounreay Waste Store Construction Work Ahead Of Schedule
23rd October 2019
Construction work on the latest radioactive waste store at Dounreay is setting records.
The concrete floor slab has just been completed ahead of schedule and with an excellent safety record. More than 3,100 tonnes of concrete and 184 tonnes of reinforced metal bars have gone into creating the floor of the building which will hold intermediate waste in long term storage in accordance with Scottish Government policy.
Contractor GRAHAM Construction was awarded the contract to construct the facility which is due to be complete by the end of 2021.
Dounreay Programme Delivery Director, David Hubbard, said:This is a significant milestone for the project, and has been completed without an accident. We are on course to deliver the work on behalf of the Nuclear Decommissioning Authority on time, but the safety of the workforce remains our highest priority always.
Tony Perry, the NDA's Head of Programme, welcomed the news of progress on the new storage facility:
It's good to see this important project progressing quickly, with our colleagues at Dounreay maintaining their continued focus on safety, quality, cost and schedule."
Related Businesses
Related Articles
He joins from AtkinsRealis, where he was market director and delivery lead for its nuclear decommissioning and waste services business, and officially takes up the post today (18 November 2024), He succeeds John Grierson who has served as interim MD since May. NRS CEO Rob Fletcher said, "I am very pleased that Dave Wilson has agreed to join the team at Dounreay.
The Nuclear Decommissioning Authority group have announced five organisations as winners of this year's supply chain awards. Morgan Sindall Infrastructure, The Decommissioning Delivery Partnership, PA Consulting, Antech and The Higher Activity Waste Thermal Treatment Tranche 1 Team are the big winners in this year's supply chain awards.
Find out what has been happening at UKAEA in our monthly newsletter. Read about our recent activities and upcoming events.
With a degree in electrical and electronic engineering and a keen interest in the nuclear sector, Anouschka knew Sellafield would be the best place for her to begin her career in the industry. That career has already seen her relocate from Sheffield to Cumbria and scooping the title of Sellafield Ltd Graduate of the Year.
More than 140 graduates have started at Sellafield Ltd. Over 140 graduates have just started their exciting careers with the company in a range of business and technical disciplines, supporting Sellafield Ltd in its mission to create a clean and safe environment for future generations.
Find out what has been happening at UKAEA in our monthly newsletter. Read about our recent activities and upcoming events.
The Nuclear Decommissioning Authority (NDA) group has on 26 September 2024 published its 2023 to 2024 socio-economic report detailing a record investment in projects across the UK. Over the last five years, the NDA group has invested £60 million in projects that enable permanent and sustainable change in its site communities, leveraging many millions more from partners.
Today, the ponds inside the Thermal Oxide Reprocessing Plant (or as we like to call it, Thorp) are used to store nuclear fuel that has been used in the UK's 7 operational nuclear reactors. Before taking on this new mission, Thorp reprocessed 9,000 tonnes of used nuclear fuel from around the world, generating an estimated £9 billion in revenue for the UK over 2 decades.
Over 100 graduates join the Nuclear Decommissioning Authority group today as applications open for 2025. As applications open for 2025, the Nuclear Decommissioning Authority (NDA) group also welcomed its largest ever cohort of graduates today, with more than 100 new recruits ready to support delivery of one of the world's most important environmental programmes.
In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility. In a world-first, a fully autonomous robot has been used to inspect the inside of a fusion energy facility.