Dounreay Waste Store Construction Work Ahead Of Schedule

23rd October 2019

Construction work on the latest radioactive waste store at Dounreay is setting records.

The concrete floor slab has just been completed ahead of schedule and with an excellent safety record. More than 3,100 tonnes of concrete and 184 tonnes of reinforced metal bars have gone into creating the floor of the building which will hold intermediate waste in long term storage in accordance with Scottish Government policy.

Contractor GRAHAM Construction was awarded the contract to construct the facility which is due to be complete by the end of 2021.

Dounreay Programme Delivery Director, David Hubbard, said:This is a significant milestone for the project, and has been completed without an accident. We are on course to deliver the work on behalf of the Nuclear Decommissioning Authority on time, but the safety of the workforce remains our highest priority always.

Tony Perry, the NDA's Head of Programme, welcomed the news of progress on the new storage facility:

It's good to see this important project progressing quickly, with our colleagues at Dounreay maintaining their continued focus on safety, quality, cost and schedule."

 

Related Businesses

 

Related Articles

NDA group enjoys a big WiN at awards ceremonyThumbnail for article : NDA group enjoys a big WiN at awards ceremony
Employees from across the Nuclear Decommissioning Authority group have been honoured at a prestigious national awards ceremony in London.   The Women in Nuclear (WiN) Annual Awards recognises those who have gone above and beyond to promote gender balance and diversity across the nuclear sector.  
Radio Active Particles At Dounreay Foreshore Latest ListThumbnail for article : Radio Active Particles At Dounreay Foreshore Latest List
The latest particle find on the Dounreay foreshore was on 17th January 2020.   See the updated list.  
Engineering Apprenticeships (mechanical, Electrical & Instrumentation) Closing Date 19 February 2020Thumbnail for article : Engineering Apprenticeships (mechanical, Electrical & Instrumentation) Closing Date 19 February 2020
Starting Salary: £12,595 in Year 1 rising to £18,191 in Year 4.   Dounreay is working at the forefront of nuclear decommissioning, waste management and environmental restoration.  
Dounreay Heritage Annual Report 2018 To 2019
Dounreay heritage strategy - Updated 26 November 2019 The Dounreay Heritage Strategy was published in 2010 and is managed by the DSRL heritage officer with advice from a panel of external experts from Historic Environment Scotland (HES), National Museums Scotland (NMS), Highlife Highland (HLH) and the Nuclear Decommissioning Authority (NDA).  The Heritage Advisory Panel held its ninth meeting on 26 March 2019 in Nucleus: The Nuclear and Caithness Archives.  
Decommissioning In Japan - Learning From DounreayThumbnail for article : Decommissioning In Japan - Learning From Dounreay
As part of the nuclear sector deal, to foster ever-stronger links between the British and Japanese nuclear industry, Councillor Struan Mackie who represents Thurso and North West Caithness on Highland Council (Deputy-Chair of the Dounreay Stakeholder Group) undertook a five day Japanese visit to discuss the impact of nuclear decommissioning on local communities with stakeholders in Tsuruga City, Fukui prefecture.   The whistle-stop visit included two days in Tsuruga on , the home of the Japanese Atomic Energy Agencies fast reactor ‘Monju', is generally regarded to be a ‘partner plant' to Dounreay's PFR in Caithness.  
Dounreay Supplier Day Looks At Clean-up OpportunitiesThumbnail for article : Dounreay Supplier Day Looks At Clean-up Opportunities
Dounreay's latest supplier information day, hosted jointly with companies appointed to its decommissioning services framework, has proved popular with companies from around the UK.   Around 200 people packed into a venue in Wick, Caithness to hear about plans for future work to decommission the site.  
The Pensions Regulator Authorises Combined Nuclear Pension Plan Master Trust
This latest approval brings the total number of schemes authorised by TPR up to 35, following the approval of the University of Oxford Staff Pension Scheme earlier this month (8 October).   CNPP is an industry-wide scheme, set up in 2006, for workers in the nuclear decommissioning industry.  
Half the fuel gone from iconic Dounreay reactorThumbnail for article : Half the fuel gone from iconic Dounreay reactor
Half of the last remaining radioactive fuel elements jammed for decades inside the iconic Dounreay Fast Reactor (DFR) have now been removed.   DFR with its famous dome once led the world in fast breeder technology.  
Dounreay Apprentices Celebrate Completion Of Training SchemeThumbnail for article : Dounreay Apprentices Celebrate Completion Of Training Scheme
Seven Dounreay apprentices have received their indenture certificates at a special event to mark the successful conclusion of their 4-year training programme.   The latest group ‘graduating' joined the company in 2015 - the 60th year apprentices had been part of the workforce at Dounreay and the first time in more than a decade that design office apprentices had been recruited.  
A new intermediate waste store is being constructed at Dounreay.Thumbnail for article : A new intermediate waste store is being constructed at Dounreay.
The first concrete pour has taken place on a new waste store at Dounreay that will be needed for the closure of the site.   Dounreay awarded the contract to construct the new intermediate level waste store to GRAHAM Construction Ltd.  

[Printer Friendly Version]