Council making progress on Roads Improvement Project
1st December 2022
At Monday's meeting of the Highland Council’s Redesign Board (28 November 2022) members received an update on progress made with the Roads Improvement Project which is part of the Council’s Business Change programme.
The Project’s purpose is to redesign the service and identify opportunities to improve the effective, efficient and sustainable delivery of all Engineering and Roads Operations, while aspiring to improve road condition across the Highlands.
The update confirmed that the project team is now in place. The team consists of a Project Manager, a Principal Engineer, a Senior Engineer, Senior Technician, Technician and two Operational Support Officers. Their priority over the next 3 to 6 months is to deliver a programme of work to review policies and guidance currently in place.
Work has already started on reviewing the Council’s Verge Maintenance guidance. The team are also gathering information and comparisons with other Roads Authorities.
The following priorities have been identified and are currently undergoing a LEAN review to suggest improvements:
Permit Applications
Temporary and Permanent Traffic Regulation Orders
Compensation Claims
In addition to these, a rapid review of the Utilisation of Materials from Sconser Quarry has begun and the Road Construction Consent process review will be starting soon.
After a successful Redesign Workshop held in October, Council Leader Raymond Bremner and Councillor Russell Jones and Councillor Trish Robertson have been appointed to the Roads Redesign Working Group.
Councillor Raymond Bremner said: "It was good to get this update and although the project is in its early stages, progress is being made now the project team are in place. An important aspect of the project will be improving communication, both with staff and customers so we look forward to more updates as work progresses. We need to ensure our roads’ service is as efficient as possible. I would hope that the outcome of this project will ensure that any money that we spend on roads infrastructure delivers the best value and most efficient outcome we can get."
Related Businesses
Related Articles
A further £20 million will speed up actions to make Scotland's buildings safe from dangerous cladding, Housing Secretary Màiri McAllan has announced. Publishing an update to the Cladding Remediation Programme action plan, Ms McAllan confirmed additional funding and expanded eligibility, setting out that social housing will now be eligible for remediation funding.
Caledonia North Offshore Wind Farm - construction and operation of an offshore wind farm comprising up to 77 turbines with a maximum blade tip height of 355m, subsea interconnector and export cabling and associated infrastructure. The north planning committee of Highland council will decide today 6 August 2025.
Following the high winds forecast and experienced due to Storm Floris, The Highland Council is encouraging landowners to check trees and vegetation near to public roads which may have been damaged. Landowners are also asked to check the drainage from their property that it is not blocked and overflowing onto public roads.
Representatives from across the Highlands are being invited to a meeting that will focus on the current provision and future of Community Transport. The event, organised and hosted by The Highland Council, will take place at Council HQ in Inverness on Wednesday 13 August.
Young people in the Highlands can call a dedicated helpline offering expert advice to anyone receiving their full Higher, National, and Advanced results on Tuesday, 5 August 2025. The pupils and students- along with their parents and carers - will be able to get support with their results through Skills Development Scotland's (SDS) Results Helpline, which opens from 8am on results day.
Wick Business Park has welcomed wind energy technology company ENERCON as the first occupant of one of four new units completed last year. ENERCON specialises in designing, producing, installing and servicing onshore wind turbines and has been operating in the Caithness area since 2013.
Additional empty homes officers are being recruited to bring more privately owned houses back into use. The new posts are being supported as part of a £2 million investment through the Scottish Empty Homes Partnership in 2025-26 which will see staff take a more proactive and targeted approach to tackling local housing issues.
The Highland Strategic Local Action Group (LAG) met in June 2025 and considered and agreed funding for 28 projects submitted to the Community-Led Local Development fund (CLLD), which makes up part of The Highland Council Community Regeneration Fund (CRF) programme. CRF is an umbrella term used to cover multiple external funding programmes administered by The Highland Council.
Highland Council has provided 12 ‘Talking Tub' resources for use in primary schools across the Highlands, in partnership with Union Technical who deliver community benefits as part of the Energy Efficient Scotland: Area Based Scheme programme. Chair of Highland Council's Education Committee, Councillor John Finlayson, said: "This is a fantastic initiative being rolled out across Highland primary schools which brings innovation and inspiration to early years children.
Visitors will find it easier to dispose of their litter at several popular spots across Highland after the rollout of additional bins. The rollout has been planned to support the tourism season as part of the Council's ongoing commitment to improve and support sustainable tourism in the area.