Sellafield Silo Installs Second Waste Retrieval Machine

3rd March 2023

The second of 3 machines which are set to safely remove waste out of the Magnox Swarf Storage Silo has successfully been assembled.

Last month, another silo emptying machine was fully built inside the Magnox Swarf Storage Silo, with the final piece of equipment - the main control cubicle - being lifted into the silo and fixed into position.

Standing in the oldest part of the Sellafield site, the Magnox Swarf Storage Silo has stored nuclear waste for the last 60 years and was originally constructed as 6 silos in the 1960's and then extended 3 times.

This latest machine now sits fully assembled next to the first silo emptying machine, which has been busy retrieving waste out of Sellafield's most hazardous building since April 2022.

These silo emptying machines are far bigger than any of the entry points into the silo, so have to be lifted in in 22 different modules and then assembled inside the legacy building - like ships in a bottle.

The machines work by lowering a grab into the waste, lifting it back up and placing the waste into a metal skip which is gradually filled and then sent to a separate waste store in more modern, safe containment. With no control over what waste the grab picks up, it's a ‘lucky dip' arrangement with every grab.

Weighing in at 360-tonnes and comprising of around 13,500 working parts, the design, manufacture and assembly of the first machine has been a job we started over 2 decades ago - reflecting the complexity of the task and the engineering behind the final design.

It will take another 3 years of preparation and commissioning work inside the silo before the machine actually starts retrieving waste.

Neil Rogerson, senior project manager, Sellafield Ltd said, "This is a big moment for ‘machine number 2' - we've fully rebuilt it inside the silo and can now start the job ahead of making it work.

It’s been a challenging but rewarding project with a truly integrated team. I wouldn’t want to have been on any other job because nothing is as big as this in creating a clean and safe environment for future generations.

All 3 machines were originally designed and manufactured in Wolverhampton by Ansaldo NES, and all are now under the wing of Sellafield Ltd and the Decommissioning Delivery Partnership Framework Partner - i3 Decommissioning Partners.

Mike Lacey, i3 project director said, "Delivering this project has taken real collaboration, determination and a one-team approach, with every single person working as dedicated nuclear professionals. Sellafield Ltd and i3 shared the same milestones target, so we can now share all the same recognition and success.

Gary Kershaw is one of the i3 engineering team who assembled this second machine, he said, "It’s a big task involving lots of different skills: fitters, riggers, electricians and all the people behind the project too. At any given time during assembly there’ll be roughly a dozen people in our team working on site and half a dozen people at the off-site locations. Everyone knows just how important getting this right is.

PHOTO
The second silo emptying machine has been installed in the silo.

 

Related Businesses

 

Related Articles

30/6/2026 : Other Public Services

 
Innovative robotics trialled to tackle nuclear waste challenges

Innovative robotic solutions being trialled at Nuclear Restoration Services (NRS) Oldbury site to tackle most challenging aspects of legacy waste management.   Oldbury nuclear decommissioning site is a trailblazer for robotics and other innovative approaches, with NRS deploying robotics trials in South Gloucestershire to tackle some of the most challenging aspects of legacy waste management, reducing risk to workers and improving efficiency.  

16/6/2026 : Other Public Services

 
NDA group employees recognised by His Majesty the King

Three NDA group employees awarded honours in the 2026 King’s Birthday Honours list.   Three NDA group employees have been awarded honours in the 2026 King’s Birthday Honours list, for services to the nuclear industry and the local community.  

4/6/2026 : Other Public Services

Wylfa Decommissioning But With Good Propects For Future Nuclear Dvelopments

Wylfa, located on Anglesey, North Wales, is a historic nuclear site that operated from 1971 to 2015, featuring the UK's largest and last Magnox reactors.   Known for its significant contribution to UK energy, it is currently undergoing decommissioning while being designated as a premier location for new, small modular reactor (SMR) technology.  

20/5/2026 : Other Public Services

 
Scottish nuclear site hails e-learning platform as great example of industry collaboration

The Engineering Construction Industry Training Board’s (ECITB) award-winning e-learning platform has been hailed as a great example of industry collaboration in action.   To mark Learning at Work Week 2026, NRS Dounreay has highlighted how the ECITB’s Learning Experience Platform (LXP) has become a “go-to training solution” for its 1,400 workers.  

15/5/2026 : Other Public Services

 
NRS socio-economic funding supports 129 UK community projects

Almost £2 million was invested by Nuclear Restoration Services (NRS) last year in socio-economic initiatives, supporting good causes in communities local to its 14 decommissioning sites.   The NRS socio-economic scheme provided £1,979,721 during 2025-26 to enhance the social and economic wellbeing of communities located near NRS sites.  

15/4/2026 : Other Public Services

Buried in the Sand: The Radioactive Legacy Washing Up on Britain's Shores

It sounds like something from a Cold War thriller, not a family day out: fragments of radioactive material, invisible to the naked eye, quietly lying in the sand.  Yet for decades, beaches near Dounreay and Sellafield have been the final resting place for exactly that.  

14/3/2026 : Other Public Services

 
Why Repaint a Building Marked for Demolition? The Practical Logic Behind the Dounreay Dome's Fresh Coat

At first glance, the decision to repaint the iconic Dounreay dome as it is a structure already scheduled for demolition seems baffling.  Why spend money maintaining a building that will soon be torn down? Why refresh the exterior of a landmark whose days are numbered? The answer is far more practical than it appears.  

11/3/2026 : Advisory / Counseling Services

 
Nuclear project academy goes national

The Nuclear Decommissioning Authority (NDA) is launching a UK‑wide training programme to support the development of project professionals across the nuclear sector.   The One NDA Project Academy is an expansion of a programme initially launched at Sellafield in 2016.  

3/2/2026 : Other Public Services

 
From Headlines to Hidden Lines - Dounreay's Quiet Legacy of Radioactive Particles

For years, radioactive particles discovered near Dounreay were headline news.  Each find triggered a press release, picked up by local and national outlets, reminding communities that the nuclear legacy was still with us.  

17/12/2025 : Advisory / Counseling Services

UKAEA and NDA strengthen collaborative approach to decommissioning

UKAEA and NDA sign formal agreement to share knowledge and expertise, advancing the delivery of major decommissioning programmes.   Memorandum of Understanding agreed to enable and encourage knowledge sharing, and improve best practice.