Lessons Learned From CHaP Project

11th March 2011

The Highland Council has learned lessons from the Caithness Heat and Power Project in Wick, and introduced measures to ensure the corporate failings are not repeated in any future project.

A total of 39 actions have been put in place in a response to an internal audit of the Wick-based enterprise and these actions have been acknowledged by external audit and the Accounts Commission.

The Council also believes that strong political and managerial leadership, recognised in recent external audits, is in place to prevent similar shortcomings in governance and financial stewardship of a project.

At a special council meeting to consider the findings of the Accounts Commission in respect of the Caithness Heat and Power project, the Council accepted the failings of the project in the early stages of the business, between 2004-2007.

Council Leader Councillor Michael Foxley said: "It is critical that the Council learns lessons from this project. There were real failings but when the extent of these came to light, the Council acted promptly, openly and effectively to ensure that these were highlighted and addressed. The Council has liaised closely and fully with Audit Scotland and continues to do so in taking the project forward.

"Since 2007 the Council has changed significantly. External audits have found there is a strong political leadership within the Council, with an Administration that works consistently and effectively and a strong Opposition, which closely scrutinises proposals. These audits have also recognised the strong managerial leadership that now exists within the Council. This combination should avoid a similar position developing again."

The Council noted that tenants served by ChaP had suffered no detriment, with heat and power maintained at all times.

The Council agreed:

(i) To note the Controller of Audit's report, of 9th February 2011, on the Caithness Heat and Power project, prepared under section 102 of the Local Government (Scotland) Act 1973.

(ii) To note the Accounts Commission's response to the Controller of Audit's report.

(iii) That the actions taken by the Council are sufficient to address the specific issues raised with regard to this project and are sufficient to ensure that no similar failings occur within future projects. This agreement should be confirmed to Audit Scotland and the Accounts Commission.

(iv) That Audit Scotland and the Accounts Commission will be kept fully informed of the progress of the project.

(v) That the Head of Internal Audit & Risk Management will undertake a follow up review in order to ensure that all actions have been implemented and are effective and agree that this report is presented to the Council.

(vi) To acknowledge and support the important role of its statutory officers.

The Council's response will be relayed to the Accounts Commission and published in the local media and on the Council's web site: www.highland.gov.uk

 

Related Businesses

 

Related Articles

29/5/2026 : Local Authority

Highland tourism infrastructure improvements made possible with £7 million funding secured to date

The Economy and Infrastructure Committee met today (Thursday 28 May, 2026) and reaffirmed The Highland Council’s strong progress in delivering its Strategic Tourism Infrastructure Development Plan (STIDP), with more than £7 million secured to date through the Scottish Government’s Rural Tourism Infrastructure Fund (RTIF).   The investment is supporting a wide range of projects across the Highlands.  

29/5/2026 : Local Authority

Highland councillors back new ‘Dark Skies’ planning policy

Highland councillors have agreed to take forward a new planning policy aimed at reducing light pollution across the region.   At a meeting of The Highland Council’s Economy and Infrastructure Committee held (Thursday 28 May 2026), members supported the proposed Dark Skies Draft Planning Policy, which will guide lighting requirements in new developments.  

28/5/2026 : Local Authority

Air Charter Scotland introduces revised fares on Wick-Aberdeen PSO service

Air Charter Scotland – operator of the lifeline public service obligation (PSO) air service connecting Wick and Aberdeen – has announced revised fares designed to make travelling even simpler and more accessible for passengers.   In response to customer feedback, passengers will benefit from lower fares across all ticket types, the introduction of new return rates and discounted travel for children.  

23/5/2026 : Local Authority

Highland councillors to consider new 'Dark Skies' planning policy

A new planning policy aimed at influencing some lighting requirements in new developments that are subject to planning control will be considered by members of The Highland Council’s Economy and Infrastructure Committee when they meet on Thursday (28 May 2026).   The proposed Dark Skies Draft Planning Policy sets out how the Council could reduce light pollution across Highland, supporting environmental protection, community financial and tourism benefits and sustainable development.  

22/5/2026 : Local Authority

Proposed Public Transport Strategy aims to improve connectivity and sustainability across Highland

A new draft Public Transport Strategy for 2026–2036 will be considered by Members of the Economy & Infrastructure Committee on Thursday 28 May 2026, setting out an ambitious vision to strengthen and modernise public and community transport across Highland.   The proposed strategy builds on the Local Transport Strategy Delivery Plan agreed in February 2026 and responds to key challenges, including a shrinking local bus network, rising contract costs, and evolving travel patterns.  

22/5/2026 : Local Authority

Wick town centre streetscape progresses, with phased opening planned

A £1.25 million project to transform Wick town centre into a more welcoming, attractive and pedestrian friendly space is continuing to make steady progress, with completion now expected this summer.   This represents an extension to the original timeline, however, a phased approach to opening, starting this month, will minimise disruption for visitors, local residents, and businesses.  

22/5/2026 : Local Authority

Can Bollards Save Highland Town Centres or Sink Them? Fort William Bollards Switch On And Wick Bollards On Soon

The Highland Council has installed automatic bollards on Fort William High Street as part of the Fort William Pedestrian Improvement Scheme.  The High Street pedestrian zone will commence from Monday 25 May 2026.  

21/5/2026 : Local Authority

 
Longman Park modular homes help deliver ‘Fairer Highland’ commitments

The Highland Council has successfully completed phases one and two of new modular “park-style” homes at the Gypsy/Traveller site at Longman Park, Inverness.   Funded primarily through the Scottish Government’s Gypsy/Traveller Accommodation Fund, more than £7 million has been invested to upgrade and future-proof accommodation and site facilities.  

21/5/2026 : Local Authority

Highland Council commended for continued improvements to services for homeless households

The Highland Council’s performance for homeless households has improved significantly over the past four years, while the national average has continued to rise over the same period.  This sustained focus on improvement was acknowledged by the Scottish Housing Regulator at an engagement meeting in early 2026.  

21/5/2026 : Local Authority

Highland Council strengthens Net Zero progress with improved reporting and funding commitments

Highland Council strengthens Net Zero progress with improved reporting and funding commitments Members of Highland Council’s Climate Change Committee today welcomed progress in delivering the Council’s Net Zero Programme, with new measures to improve carbon reporting, strengthen investment decisions, and secure funding for projects across the Highlands.   Taken together, these measures reflect a wider shift towards a more coordinated, programme-led approach to climate mitigation, adaptation and resilience, following the direction agreed by Council in March 2026.