4th November 2026
Highland Council is forecasting expenditure of almost £75 million on its housing capital programme during 2026/27, against an original budget of nearly £84 million, as rising building costs, project delays and the availability of additional government funding influence its investment plans.
A Housing Revenue Account (HRA) capital monitoring report, covering expenditure to 31 August 2026, is being considered by the Housing and Property Committee on 4 November.
The programme covers both improvements to existing council houses and the construction of new affordable homes.
The projected underspend is £9.16 million, although this does not necessarily represent money that has been wasted or projects abandoned. Much of the difference in the existing housing programme results from the Council securing external grants to pay for energy efficiency improvements, reducing the amount required from its own housing budget.
Any final underspend is expected to be carried forward into the next five-year capital programme, covering 2027-2032.
New housing falls short of annual target
One of the more significant figures concerns the delivery of new affordable housing.
The Council expects to complete 105 homes for social rent during 2026/27, compared with its annual target of 180.
However, a further 188 homes are already under construction and expected to be completed after March 2027. Another 71 units are being progressed towards contract commitments and site starts.
This means the wider development pipeline currently stands at 364 homes, although not all are guaranteed to proceed on schedule.
The Council identifies several obstacles, including projects that are no longer financially viable, unsuccessful developer planning applications and the limits on how much the Council can borrow.
Where building costs rise beyond what borrowing can support, additional Scottish Government subsidy is needed to make developments financially viable.
The original affordable housing capital budget was £49 million, but this has been revised to £46.4 million, partly because enabling works at Torvean have been postponed until 2027/28 to coincide with electricity grid improvements.
Improving existing council homes
Alongside new construction, the Council is continuing to invest in its existing housing stock.
By the end of August, the programme had delivered 255 heating installations, 144 bathroom replacements, 119 new kitchens and 25 new roofs. There were also 78 window replacements and 131 new front doors.
Heating and energy efficiency account for around half of the mainstream investment programme.
A separate energy efficiency initiative is also making progress. Since February 2025, 961 improvement measures have been installed in 572 council homes, supported by almost £7.93 million in external Energy Company Obligation funding.
The work includes solar panels, air-source heat pumps, loft insulation and cavity wall insulation.
The ambition is to improve properties with Energy Performance Certificate ratings of D or below to at least a C rating.
This is particularly important in Highland, where older housing, colder weather and the absence of mains gas in many communities can make heating costs a considerable burden.
However, the current Energy Company Obligation scheme ends in December 2026, making future funding arrangements important if the programme is to continue at a similar pace.
An interesting development in Wick
The report also highlights a project in Wick involving Scottish and Southern Electricity Networks (SSEN).
Eighteen housing units have been refurbished to provide accommodation for workers. The project was completed in August 2026 at a cost of £1.555 million, fully funded by SSEN.
The arrangement allows the electricity network company to provide accommodation for workers while major infrastructure projects are being undertaken in the area. The properties will be handed back to Highland Council after five years.
It is an interesting example of how existing housing assets can be used to support major investment projects and provide accommodation for workers who might otherwise struggle to find somewhere to stay.
The financial challenge ahead
The Council's capital programme is funded through a combination of government grants, capital receipts, revenue contributions and borrowing.
Borrowing remains a major part of the funding arrangements, but loan charges represent a continuing pressure on the Housing Revenue Account. The Council has a limit on loan charges equivalent to 43% of its housing income to help maintain financial sustainability.
Officers also warn that inflationary pressures arising from the Middle East crisis could affect construction costs later in the financial year.
The figures demonstrate that Highland Council is continuing to invest in both new and existing homes, but delivering its ambitions is becoming increasingly dependent on external funding and the ability to control construction costs.
For communities such as Wick and Thurso, the real test will be whether the money translates into more affordable homes, better housing conditions and properties that people can afford to heat.
A substantial housing budget is important, but ultimately it is the number of homes delivered and improved that matters to tenants and communities.