90 Jobs For Wick in £2.5 Billion Beatrice Offshore Wind Farm

24th May 2016

Photograph of 90 Jobs For Wick in £2.5 Billion Beatrice Offshore Wind Farm

* 84 turbines will provide 588MW of power once operational in 2019.

* New windfarm expects to provide an average annual gross employment i Scotland of over 890 jobs during construction and is one of Scotland's largest private infrastructure project.

*The project is expected to power roughly 450,000 homes; approximately three times the number of homes in the Moray and Highland regions.

The £2.6bn Beatrice Offshore Windfarm Ltd (BOWL) project has been given the green light for construction by owners SSE (40%), Copenhagen Infrastructure Partners (CIP) (35%) and SDIC Power (25%) after the project reached Financial Close. The project will be one of the largest private investments ever made in Scottish infrastructure.

The 588MW, 84 turbine project, situated in the Outer Moray Firth, was consented by the Scottish Government in March 2014 and granted an Investment Contract by the UK Government in May 2014.

Today's [23 May] decision signals the green light for manufacturing and construction to begin. Work at the operations and maintenance facility in Wick and the transmission works in Moray will commence this year. Offshore construction will begin in 2017. The wind farm is expected to become fully operational in 2019.

Beatrice is expected to bring a range of socio-economic benefits to the local, regional, Scottish and UK economies during both the construction and operational phases. Expected opportunities include job creation, skills training, investment in Scottish ports and harbours, supply chain opportunities and community benefit funding.

Paul Cooley, Director of Renewables at SSE, stated: "We are delighted that Beatrice has achieved Financial Close and we are extremely grateful for all of the support received throughout the development of the project from stakeholders such as the Scottish Government, DECC, HIE, the Highland Council, Moray Council and local communities. Contracts have already been placed with many UK based suppliers, and Siemens intend to undertake turbine blade construction from Siemen's new manufacturing facility in Hull.

"Around £10m of investment is planned at Wick Harbour to house the wind farm's operations and maintenance facilities and improving the existing RNLI facilities. We expect a peak of around 65 jobs during construction of the O and M base with around 90 long-term jobs anticipated during the operational phase.

Wick Councillor Bill Fernie chair of Resources and Budget Leader of Highland Council said,"I am very very happy that we are finally see the investment that will bring so many new jobs both in construction and long-term to Wick. This adds to the already significant things going on in Wick from the new primary schools and High school, Nuclear Archive Centre and new council offices. The announcement about the Beatrice offshore wind farm means Wick has a long-term future with many new jobs and some of the best education facilities anywhere in Scotland coming on-stream at the same time."

"The decision reaffirms SSE's commitment to offshore wind and we are proud to progress such a flagship project for the Scottish offshore wind industry and the UK’s skilled supply chain. It shows SSE will continue to play its part in investing in the critical energy infrastructure the country needs to power homes across the UK both today and in the future."

The wind farm is being developed with a tier 1 supply chain comprising Seaway Heavy Lifting, Subsea 7, Nexans and Siemens and is expected to deliver c. £680m into the UK and Scottish economy via employment and supply chain opportunities during the construction phase and c. £400m - £525m during the wind farm’s 25 year operational life. Three supply chain events were held last year through SSE’s Open4Business procurement portal to engage with interested businesses and provide information on possible contracts.

Christina G. Sorensen, Senior Partner in CIP, said: "CIP’s investment in Beatrice represents one of the largest commitments from a financial sponsor to an offshore wind project, and follows our investment in the German offshore wind project Veja Mate in June 2015. CIP has a long track record in offshore wind and in accordance with our investment strategy, we decided to enter the project in the late development phase in November 2014. Thereby CIP has been able to actively engage in the sourcing strategy and contract execution where the fundamental risk profile of the project is decided.

"CIP’s ambition is to be a proactive financial investor and project partner in the development, construction and operations phase. The project will deliver clean, green and affordable renewable energy based on a stable investment contract price and a 15 year inflation linked revenue stream. It’s a great project with very capable partners and SSE as the experienced operator, and we look forward to continue the cooperation in the many years to come."

Yang Lin, at SDIC Power stated: “We are delighted to see the Financial Close for Beatrice. This milestone is achieved as a result of all parties’ dedication and collaboration. Beatrice is SDIC Power’s first exposure to the European offshore wind market, and we fully believe it has a promising future. We will continue to work closely with our partners and we expect Beatrice to contribute more to the region’s economy."

Secretary of State for Energy and Climate Change Amber Rudd said: “The UK is the world leader in offshore wind; and this industry, backed by the UK Government and benefiting from our access to the EU single market, is a success story going from strength to strength.

“This project will provide home-grown clean energy boosting skills and creating jobs and financial security for working people and their families in Scotland, and across the UK."

Paul Wheelhouse, Minister for Business, Innovation & Energy in the Scottish Government, said: “This is great news for the industry and I congratulate the owners SSE, Copenhagen Infrastructure Partners and SDIC Power on achieving this significant milestone in the development of this multi-billion pound infrastructure project.

“The Beatrice Offshore Windfarm has the opportunity to deliver so much to Caithness and Scotland as a whole, in terms of employment and community benefit. Scotland’s renewables sector is stronger than ever and our early adoption of clean, green energy technology and infrastructure was the right thing to do. Renewables are now Scotland’s biggest electricity generator, and nearly half of gross electricity consumption comes from renewables.

“Scotland is well on course to meet its interim renewables target and is delivering a strong contribution to global climate efforts. I look forward to this project contributing to our green energy mix."

Ronnie Quinn, General Manager of The Crown Estate’s Scotland Portfolio - the business which manages leasing of the seabed and granted a lease for the Beatrice project - said: “It’s incredibly exciting to see this project given the final go ahead. Any offshore wind farm of this scale is a very complex development - putting the finance and final lease in place for Beatrice is a huge achievement that will result in investment and jobs at a local, regional and national level. We look forward to continuing to support the team.”

 

Related Businesses

 

Related Articles

Today : Local Authority

 
Highland's Growth Ambitions: Billions in Investment Promised, But Can the Numbers Really Add Up?

Highland Council has set out an ambitious vision for the economic future of the Highlands, with the possibility of attracting between £10 billion and £16 billion of public and private investment over the next 25 years.   On paper, it is an impressive prospect.  

Today : Local Authority

Caithness Committee approves six Community Regeneration Fund applications - £237,155

The Caithness Area Committee which met (Monday 2 November 2026) has approved six applications submitted to the Community Regeneration Fund (CRF).   This approval securing significant investment to support local projects that will benefit communities across the north.  

31/10/2026 : Local Authority

Caithness at the Sharp End: Broadband, Buses and Public Services Under Pressure

From the loss of a direct bus link to Inverness to uncertainty over rural broadband, a difficult council budget and the future of community organisations, the past week has provided plenty for Caithness residents to think about.  But there have also been celebrations, local achievements and signs of community spirit.  

31/10/2026 : Local Authority

 
Highland Council Faces a £39.2 Million Budget Gap: Will Council Taxpayers and Services Pay the Price?

Highland Council is facing another difficult financial challenge, with councillors being told that a further £39.2 million in savings must be found over the next three years to balance the authority's finances.   The announcement, made at the full council meeting on 29 October 2026, represents a substantial deterioration in the financial outlook.  

30/10/2026 : Local Authority

 
Highland Council Visitor Levy Consultation In-person Events Announced

Residents, businesses, community groups and visitors are encouraged to continue to take part in a series of public engagement events to learn more about the proposed Highland Visitor Levy and how they can contribute to the statutory public consultation.   In addition to the online webinars held earlier in the process, a programme of in-person events will continue throughout November.  

30/10/2026 : Local Authority

The Highland Council agrees budget engagement programme

Members of the public, community groups, the business sector and young people will be invited to share their views on how The Highland Council balances its budget and plans spend over the next three years.   The Council needs to find £39.2 million of additional savings over the next three years to deliver a balanced financial plan, driven largely by the impact of rising costs and the ongoing impact of wider economic events.  

29/10/2026 : Local Authority

The Hidden Cost of a 1% Capital Budget Cut: Could Scotland's Schools, Roads and Highland Investment Plans Be Affected?

The Chancellor's decision to reduce departmental capital budgets by 1% could have consequences well beyond Westminster.  Scotland faces a reduction in capital funding, while Highland Council is embarking on a £2.1 billion investment programme that includes a proposed £100 million education campus in Thurso.  

28/10/2026 : Local Authority

When Fuel Prices Rise, Who Pays the Bill for Public Services?

Councils, the NHS and other public bodies face a difficult choice when rising diesel and energy costs threaten the contractors they depend on.  School transport in rural Scotland illustrates the problem.  

27/10/2026 : Local Authority

Gaelic Spending Under Scrutiny: Can Highland Council Afford Another Post While Jobs Are Under Pressure?

The council has legal responsibilities to support Gaelic, but with budgets stretched and services facing difficult choices.  Residents are entitled to ask how priorities are decided across the Highlands.  

24/10/2026 : Local Authority

 
Libraries, Leisure Centres and Local Culture Face Growing Pressure as Council Charges Rise

Audit Scotland warns that cuts to community services could deepen inequalities, while councils lack the evidence to measure the full consequences.   Scotland’s councils are spending less on culture and leisure services while asking the public to pay more to use them, raising questions about the future of libraries, swimming pools, sports facilities, museums and other important parts of community life.