A new intermediate waste store is being constructed at Dounreay.
28th August 2019

The first concrete pour has taken place on a new waste store at Dounreay that will be needed for the closure of the site.
Dounreay awarded the contract to construct the new intermediate level waste store to GRAHAM Construction Ltd. It is due to be finished by the end of 2021.
A 250 tonne mobile crane, which can be seen on the skyline, is assisting with the pouring of an estimated 1,200 tonnes of concrete, needed to construct the heavy duty floor slab.
Dounreay Project Manager Dave Busby said:It's great to see the progress of the floor slab, which is now 25% complete slightly ahead of schedule.
The store will hold drums of waste in safe long term storage in accordance with Scottish Government policy.
Related Businesses
Related Articles
The Nuclear Decommissioning Authority (NDA) group played a pivotal role in defueling Hunterston B on time and on budget. On 24 April 2025 EDF announced Hunterston B nuclear power station has been successfully defueled on time and on budget, in less than three years, following rigorous checks by the Office for Nuclear Regulation (ONR).
Spot, the robot "dog," recently assisted colleagues in Dounreay's Fuel Cycle Area by reactivating a crucial building crane in a reprocessing plant. The crane had been deactivated at the switchboard in 2023 due to concerns about the ageing asset.
The Nuclear Decommissioning Authority has announced it's establishing a Plutonium Ceramics Academic Hub with the Universities of Manchester and Sheffield. The Nuclear Decommissioning Authority (NDA) has announced it's establishing a Plutonium Ceramics Academic Hub with the Universities of Manchester and Sheffield.
One of Britain's most complex environmental restoration projects is taking on 23 new apprentices. The decommissioning of the former centre of fast reactor research and development at Dounreay is continuing to create long-term opportunities for young people.
NDA utilises innovative technology to bring to life progress in delivering its nationally important mission at ‘Nuclear Week in Parliament'. The Nuclear Decommissioning Authority (NDA) group utilised innovative technology to bring to life progress in delivering its nationally important mission at the Nuclear Industry Association's ‘Nuclear Week in Parliament' (NWIP).
The NDA group's Supply Chain Event saw 2,000 people and 300 exhibitors assemble at Telford International Centre yesterday (Thursday) for the decommissioning-focused networking event. The day was launched by David Peattie, Chief Executive of the NDA group.
The Nuclear Decommissioning Authority (NDA) group has launched a specialised cyber facility to accelerate collaboration across nuclear operators and the supply chain. The adoption of innovative technologies such as AI and robotics is enhancing their collective ability to successfully defend against cyber threats.
He joins from AtkinsRealis, where he was market director and delivery lead for its nuclear decommissioning and waste services business, and officially takes up the post today (18 November 2024), He succeeds John Grierson who has served as interim MD since May. NRS CEO Rob Fletcher said, "I am very pleased that Dave Wilson has agreed to join the team at Dounreay.
The Nuclear Decommissioning Authority group have announced five organisations as winners of this year's supply chain awards. Morgan Sindall Infrastructure, The Decommissioning Delivery Partnership, PA Consulting, Antech and The Higher Activity Waste Thermal Treatment Tranche 1 Team are the big winners in this year's supply chain awards.
Find out what has been happening at UKAEA in our monthly newsletter. Read about our recent activities and upcoming events.