11th September 2011
South West Inverness Flood Relief Channel - Fourth and Final Phase
Highland Councillors have given the go ahead for the fourth and final phase of a £16 million scheme to protect 600 houses, which are at risk of flooding on the south side of Inverness.
The final phase of the South-West Inverness flood relief channel lies between Old town of Leys and the Alt na Skiah Burn to the south of Fairways Golf course. The scheme intercepts four watercourses; Lochardil Burn, Slackbuie Channel, Slackbuie Springs and Alt na Skiah Burn and channels the waters into the River Ness, via the Holm Burn.
The total length of construction for this final phase is 1,400 metres. Approximately half of this will be buried precast concrete box culverts and the remainder will be open channel.
The contract value is £6.57 million and the Council hopes to confirm award of the contract before the end of this month.
The contract period is 12 months and construction will commence before the end of this year.
A public meeting will be held following the award of the contract on a date and at a venue to be confirmed.
The works have been designed by AECOM based in Leeds and works will be supervised by the Council.
Councillor John Laing, Chairman of The Highland Council's Transport Environment and Community Services Committee, said: "I am delighted that the Council has invested so heavily in this important project, which will provide flood protection for many houses on the south side of Inverness. It is important that the Council takes account of the impact of climate change by investing in flood mitigation measures such as this to ensure that cost effective measures are in place to deal with exceptional weather flood events as and when they may arise in the future."
Phase one commenced at the River Ness and travels up the Holm Burn to Holm Burn Bridge. The works involved increasing the capacity of Holm Burn, bunding works on the banks, the widening and deepening of an existing sediment pond, the construction of a fish pass and the replacement of two bridges.
Phase two commenced at the Holm Burn just downstream of Torbreck Bridge and terminates at Culduthel Channel. The works involved construction of the confluence at Holm Burn, a sedimentation pond and weir to catch sediment from the channel prior to its discharge into the Holm Burn. The channel travels in a culvert until beyond Essich Road, and then travels largely in open channel until Culduthel Channel.
Phase three began at Culduthel Channel and ended at Ault na Skiah, taking in Lochardil Burn, Slackbuie Channel and Slackbuie Spring. The channel is a combination of culverted sections and open channel.
Works are also underway to replace Holm Burn Bridge on Dores Road as part of the scheme. This replacement increases the flood capacity of this bridge, but devlopers are also funding the widening of the bridge and provision of a cycleway to access a proposed adjacent development. Works at the bridge are programmed to be complete by Christmas.
Related Businesses
Related Articles
The Highland Council welcomes moves by the Scottish Government to introduce greater flexibility on how it could design a Visitor Levy Scheme for consultation. The Visitor Levy (Scotland) Act 2024 currently provides local authorities with discretionary powers to implement percentage-based levies following statutory consultation.
As it looks to set out its forthcoming priorities, the council is seeking involvement from members of the public, including businesses, community groups, parents, and young people. All their opinions are going to be crucial in deciding how Highland Council will take on its budget challenge for 2026-2027.
Thurso is to benefit from £100m investment in education and community facilities and are rolling out the first phase of public consultations on 9 and 10 December 2025. The Highland Council is inviting people that live, work, or study in Thurso, to come along to the public consultation events to have their say; this is an opportunity to help shape the future of Thurso, to gather views and ideas.
A new online portal has been launched to bring empty homeowners together with prospective buyers or developers with the aim of facilitating more properties to be used as homes again. Covering the whole of Scotland, this builds on the success of local pilots, referred to as "matchmaker schemes".
Steps towards introducing a short term let control area have been considered by Highland Council's Isle of Skye and Raasay area committee. On Monday (1 December 2025) the committee heard evidence to justify the grounds for the introduction of a Short Term Let Control Area covering all or part of Skye and Raasay.
EMPLOYERS and educators from across the Highlands have gathered to hear how a new initiative is aiming to transform the region's economy. Workforce North - A Call to Action brought together business leaders and teachers from primary and secondary schools from across the Highland Council area with a wide range of partners geared towards education, learning and skills development at Strathpeffer Pavillion.
The Highland Council continues to call for meaningful engagement from the Home Office over its plans to temporarily accommodate up to 300 adult male asylum seekers at Cameron Barracks, Inverness. It follows an email on Monday from Alex Norris MP, Minister for Border Security and Asylum, to Council Leader, Raymond Bremner, which failed to answer questions raised by the Council or address community concerns.
SSEN Transmission has become the first company to sign up to the Highland Social Value Charter (HSVC), marking a significant milestone in delivering long-term socio-economic benefits for communities across the Highlands. Investment commitments from the company include funding for roads, new homes, jobs, and work for local contractors in addition to a local and regional fund for communities to apply to.
The Highland Council continues to work through the procurement process for the provision of the Wick Public Service Obligation for the Highland Council. We have now entered the preferred bidder stage and have entered a standstill period.
Maps of the Council's gritting routes by priority and policy are available online at www.highland.gov.uk/gritting (external link) The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.