Wick has had its new high school and community campus for several years. It opened to pupils in April 2017, replacing the old high school and bringing together education and community facilities in a modern building.
Thurso, meanwhile, is still waiting for its new high school. The existing buildings have significant problems, and Highland Council is now progressing proposals for a major new education campus which could cost around £100 million.
The difference between the two projects is worth examining. Not simply because one town has its new school while the other is waiting, but because the projects illustrate two different approaches to financing public buildings.
And the experience of Wick provides a useful reminder that the cost of a school does not end when the doors open.
Wick: a school built through private finance
The Wick Community Campus was delivered through a public-private partnership arrangement.
The project was financed through a 25-year Design, Build, Finance and Maintain contract involving hub North Scotland (Wick) Ltd. Private finance was used to construct the campus, with Highland Council making payments over the contract period.
The campus included Wick High School, primary school provision, a library and swimming pool facilities. It opened in April 2017.
This arrangement meant the Council did not have to meet the entire construction cost at the beginning. Instead, the private-sector partners financed the project and recovered their costs through payments made over many years.
That may have helped get the project delivered, but it also created a long-term financial commitment for the Council.
Highland Council's annual accounts for 2023/24 show that the service charge for the Wick campus was £4.906 million in that financial year.
The accounts estimated that a further £86.611 million would be payable over the remaining contract period, measured at the prices used in those accounts.
The Scottish Government provides financial support towards the annual charge. The Council's accounts estimated that this support would total £71.106 million over the remaining contract period.
These figures need to be understood in context. They are not simply the original construction cost being paid back. The annual charge covers the contractual arrangements, including the private finance and specified maintenance obligations. But they demonstrate the scale and duration of the commitment.
The school has been open for years, but the financial agreement continues.
Thurso: a different funding approach
Thurso's proposed development is much further from completion.
Highland Council has identified approximately £100 million for a new Community Point of Delivery in the town. The proposals include a new Thurso High School and a new primary school bringing together Pennyland Primary and Miller Academy, with early years and Gaelic Medium Education provision.
Mount Pleasant Primary School would remain open.
The Council has also considered how the campus might work alongside other community services and facilities.
The proposed investment forms part of the Highland Investment Plan, a wider 20-year programme of around £2.1 billion covering schools, roads and other infrastructure.
The Council says the plan will be funded through a combination of borrowing and a ring-fenced 2% allocation of Council Tax revenue.
That is different from the private-finance arrangement used for Wick.
It does not mean the Thurso project will be free of long-term financial consequences. Borrowing has to be repaid, and interest has to be paid. Construction costs, maintenance, energy bills and future repairs will all have to be considered.
But it does mean the Council is presenting this project as part of its own investment programme rather than as another privately financed school contract.
Why the difference matters
There is a wider lesson here from the history of PFI and PPP schemes.
Private finance can allow public buildings to be constructed when governments or councils do not have the money available to pay for them directly. It can also bring construction and maintenance responsibilities together under one contract.
But private finance is not free money.
Investors and lenders expect a return. Payments can continue for 25 or 30 years, and contracts can restrict the ability of public authorities to change arrangements or bring services in-house.
The attraction for politicians is often that a building can be delivered without the full construction cost appearing immediately in the public budget.
The difficulty is that future councils and taxpayers inherit the payments.
Wick is a practical example of this. Its school is already serving pupils, but the Council continues to make substantial payments under the agreement.
That does not automatically mean the Wick project was a mistake. The campus replaced ageing facilities and provided important community services. It would be unfair to judge the project only by its financing costs without considering what the town received in return.
But it does demonstrate why the full lifetime cost matters.
Thurso must be judged on more than its £100 million price tag
The proposed Thurso development is a major opportunity for the town. The condition of parts of the existing school estate has been a concern, and the Council has identified structural, accessibility and suitability problems.
However, £100 million is a substantial commitment for a local authority facing competing demands on its finances.
Residents should be able to see how the money will be raised, how much borrowing will be required, what interest costs are expected and what provision has been made for maintaining the buildings over their lifetime.
They should also be able to compare the cost of building through the Council's proposed funding model with the cost of using private finance.
There is another issue: time.
Wick's statutory consultation began in 2010 and the campus opened in April 2017. That was almost seven years from the start of formal consultation to pupils entering the building.
Thurso's proposals are still progressing through consultation and design. The Council's published indicative timetable has pointed towards construction beginning in February 2028, but that is not the same as a confirmed opening date.
The experience of Wick shows how long major school projects can take. Thurso families will understandably want to know when the new facilities will actually be available.
The question for Highland Council
There is no simple answer to whether private finance or public borrowing is always better.
A council that borrows directly still has to pay interest and repay the money. A privately financed project may transfer some risks and maintenance responsibilities, but the overall cost can be higher.
The important thing is that the public can compare the alternatives.
For Wick, we can now look at an operating school and the payments attached to its original financing agreement.
For Thurso, the Council has an opportunity to explain its proposed funding arrangements clearly before the project moves further ahead.
The questions are straightforward.
How much will the Thurso campus cost over its full working life? What will the borrowing and interest cost? How much will annual maintenance and energy bills be? And how does the proposed approach compare with the private-finance model used for Wick?
Wick has its school. Thurso is still waiting.
The lesson should not be that one town got a better deal than the other. It should be that when public authorities build facilities expected to last for generations, the public deserves to know not just what the building costs, but who will still be paying for it 20 or 30 years later.
Source material
1. Highland Council – Thurso Community Point of Delivery project
https://www.highland.gov.uk/land-property/thurso-community-pod
2. Highland Council – Thurso school consultation, 25 August 2026
https://www.highland.gov.uk/news/article/17440/public-invited-to-have-their-say-on-future-of-thurso-school-estate
3. Highland Council – Unaudited Annual Accounts 2023/24 (PDF)
https://www.highland.gov.uk/download/downloads/id/28729/unaudited_accounts_april_2023_to_march_2024.pdf
A useful alternative: the audited accounts contain the Wick campus figures, including the £4.906 million annual service charge and estimated £86.611 million remaining payments:
https://www.highland.gov.uk/downloads/file/6655/audited-accounts-2023-2024
4. Wick campus – financing agreement announced in January 2015
https://www.infrapppworld.com/news/financing-signed-for-wick-campus-project
5. Caithness Business – Thurso new school and Wick timescale comparison
https://caithness-business.co.uk/article/30659
Note
Highland Council's current school consultation page now records the Thurso consultation as closed and says a report is expected in January 2027, with the matter then going to the Education Committee in February.
https://www.highland.gov.uk/schoolconsultations
Highland