A9 Kessock Bridge – Introduction of permanent route changes
5th February 2013
The commissioning process of the new traffic management arrangements to reduce delays as the result of the resurfacing of the Kessock Bridge from 11 February is now underway. The introduction of the traffic signals will be phased to reduce the immediate impact of the change on road users.
From lunchtime to-day (Tuesday) the new traffic lights at the junction of Henderson Road/Longman road, allowing right turns out of Henderson Road, were switched on to enable essential fine adjustments to the system.
The new traffic lights on the three main approaches to the Longman Roundabout will be similarly commissioned from prior to evening peak on Wednesday 6th February with the Traffic Signals on Rose Street in operation from Thursday afternoon, 7th February, also prior to the evening peak.
The new dedicated slip road between Stadium road and the A9 southbound dual carriageway is programmed to be open to all traffic by 7am on Saturday 9th February 2013.
Motorists should allow extra time for their journeys and pay attention to any advisory signs which will be in place throughout the works. For real time journey planning information visit www.trafficscotland.org
Related Businesses
Related Articles
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time. It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.
Households across Scotland have received £4.1 billion in relief since the Council Tax Reduction scheme was introduced in 2013. People on low incomes are eligible for the benefit if they live in Scotland - there is no equivalent in England where most councils require each household to contribute a minimum amount of council tax, irrespective of ability to do so.
The Highland Council is preparing to carry out improvement works in Thurso at Ormlie Road and at The Mall riverside path adjacent to Janet Street. The scope of works on Ormlie Road will include junction improvements between Castlegreen Road and Juniper Drive with new drop kerbs and tactile paving and some surface repairs.
A Highland-wide partnership launched earlier in 2024 to support people on their journey towards, into and within employment is looking forward to a New Year in 2025 full of exciting opportunities designed to help hundreds more people across the Highlands unlock their work potential. Work.
The Highland Council is delighted to share that its Energy Efficient Scotland: Area Based Scheme has won the Outstanding Project Award at the Scottish Green Energy Awards. Described by Scottish Renewables as a "pioneering clean power scheme", this £7 million project demonstrates the incredible impact that can be achieved through combined public and private sector investment.
The ambitious yet focused ‘Highland Investment Plan' is committed to addressing our asset challenges over the next twenty years. By using a place based approach, to ensure a more integrated community offering through the creation of new community facilities.
Applications to the Inverness Winter Payments Scheme, which is fully funded by the Inverness Common Fund, have already been awarded to 1,035 eligible households within the 7 specified Inverness Wards. Leader of Inverness Area, Councillor Ian Brown said: "Since the Scheme was opened to applications for this winter, already £114,885 has been awarded to people who live in the eligible Wards of Aird and Loch Ness, Inverness West, Inverness Central, Inverness Ness-side, Inverness Millburn, Culloden and Ardersier and Inverness South Wards.
The first Highland-wide virtual jobs fair held last month has proved to be a hit with participants and businesses. The week-long virtual event, which was delivered by the Local Employability Partnership for the West - The Highland Council, Skills Development Scotland, Highlands and Islands Enterprise, Department for Work and Pensions, Developing the Young Workforce and UHI North West and Hebrides was timed to coincide with Scottish Careers Week 2024.