Education capital projects progress in Highland schools

14th November 2013

Progress was welcomed today by members of The Highland Council's Adult and Children's Service's Committee on a number of several major education capital projects.

Approval to bring forward the fourth and final phase of the redevelopment of Lochaber High School was given by members. The council anticipates that this will achieve:
· a considerable reduction in the capital expenditure required to complete the redevelopment;
· clear educational benefits with less disruption to the operation of the school; and
· completion of the redevelopment approximately two years ahead of programme.

Also in Lochaber, members were informed that tenders have been received for the three Fort William Primary Schools projects and the council anticipates that all three contracts will be awarded before the end of December 2013.

Members were informed of proposals for a new £1million annex to Bun-sgoil Ghàidhlig Inbhir Nis that would provide two nursery classrooms. The existing nursery classroom would be used as a primary classroom resulting in 10 classrooms in the main building. Projected increases in the school roll have also prompted the Authority to give consideration to providing additional primary classroom capacity and any related impact on social and dining space. Members agreed to a review of the options at the Bun-sgoil and that design work would commence subject to formal approval at the next meeting of the Committee.
Approval was also given to:
· upgrade emergency lighting and fire alarms at Mount Pleasant and Pennyland Primary Schools in Caithness at an estimated cost of £1.5 million; and
· to upgrade accommodation at St Clement’s and St Duthus Schools at the estimated costs of £1.2 million and £2 million respectively.

An extra £300,000 funding was approved by members for the £1.2 million works at Central Primary School in Inverness to provide new kitchen and dining facilities, two nursery classrooms and an expanded “Doorways” pupil support facility.

Recommendations to carry out £450,000 works in Summer 2014 on the Lochaber High School, Synthetic Turf Playing Field to upgrade the facility to a 3G surface were welcomed by members. This development will benefit the school and sports clubs in the area seeking appropriate training facilities throughout the year.

Wick High School and Primary Schools

The revised programme to construct the building to replace the existing Wick
High School, Pulteneytown Academy Primary School, South Primary School,
Wick Carnegie Public Library and Wick Swimming Pool, which will be known as
the Wick Community Campus, has been formally agreed with Hub North
Scotland Limited (HNSL) and Miller Construction UK (MCUK).

The key milestone dates are as follows:

• Stage 2 submission – 10/01/14
• Financial close and contract agreement - 07/02/14
• Construction start on site – 31/03/14
• Practical completion – 29/01/16
• Handover period – February to April 2016
• Completion of external works – August 2016

The construction work packages are currently being tendered in accordance with
the requirements of the Territory Partner Agreement (TPA) which includes a
significant proportion of the contracts being made available to local contractors.

The replacement school for Hillhead Primary School and North Primary School
remains on programme to open in August 2015. The Stage 1 submission has
been received and the Council’s project team and specialist advisers are
considering the detail. It is proposed that, subject to the Stage 1 submission
being within the Affordability Cap approved at the New Project Request stage
(when adjusted for indexation), approval to allow the project to progress to Stage
2 is delegated to the Directors of Education, Culture and Sport and Finance and
the Interim Director of Housing and Property Services. This approach will ensure
that there are no delays to the programme as a result of waiting for the
appropriate Committee approval for the Stage 1 submission. The evaluation of
the Stage 1 submission should be completed by mid-November 2013. The key
programme dates are as follows:

• Enabling works commence – 20/01/14
• Contract award - 17/03/14
• Construction starts – 14/04/14
• School handover – 12/06/15
• Completion of all external works – 26/02/16

Councillor Alasdair Christie, Chairman of the Adult and Children’s Services Committee welcomed the work that has been done to progress the education services capital projects, he said: “I am delighted that we are able to make progress and see these major capital investments taking place in the schools that needs them most. I am certain that they will bring major benefit to the quality of education that we provide and will help to future-proof the schools that we are investing in to make them fit-for-purpose.”

 

Related Businesses

 

Related Articles

Yesterday
Council welcomes Visitor Levy flexibility plan
The Highland Council welcomes moves by the Scottish Government to introduce greater flexibility on how it could design a Visitor Levy Scheme for consultation.   The Visitor Levy (Scotland) Act 2024 currently provides local authorities with discretionary powers to implement percentage-based levies following statutory consultation.  
Yesterday
Highland Council is reaching out for views to shape its next 26/27 budget.
As it looks to set out its forthcoming priorities, the council is seeking involvement from members of the public, including businesses, community groups, parents, and young people.   All their opinions are going to be crucial in deciding how Highland Council will take on its budget challenge for 2026-2027.  
Yesterday
Have your say in Thurso's future £100million investment by attending public consultation events
Thurso is to benefit from £100m investment in education and community facilities and are rolling out the first phase of public consultations on 9 and 10 December 2025.   The Highland Council is inviting people that live, work, or study in Thurso, to come along to the public consultation events to have their say; this is an opportunity to help shape the future of Thurso, to gather views and ideas.  
2/12/2025
Finding new owners for empty homes - Scheme launched to help return more empty homes to active use
A new online portal has been launched to bring empty homeowners together with prospective buyers or developers with the aim of facilitating more properties to be used as homes again.   Covering the whole of Scotland, this builds on the success of local pilots, referred to as "matchmaker schemes".  
1/12/2025
Consideration for short term let control area in Skye and Raasay
Steps towards introducing a short term let control area have been considered by Highland Council's Isle of Skye and Raasay area committee.   On Monday (1 December 2025) the committee heard evidence to justify the grounds for the introduction of a Short Term Let Control Area covering all or part of Skye and Raasay.  
28/11/2025
Workforce North event spotlights Highland economyThumbnail for article : Workforce North event spotlights Highland economy
EMPLOYERS and educators from across the Highlands have gathered to hear how a new initiative is aiming to transform the region's economy.   Workforce North - A Call to Action brought together business leaders and teachers from primary and secondary schools from across the Highland Council area with a wide range of partners geared towards education, learning and skills development at Strathpeffer Pavillion.  
27/11/2025
Council calls for meaningful engagement from Home Office Over 300 Asylum Seekers Being Sent to Inverness
The Highland Council continues to call for meaningful engagement from the Home Office over its plans to temporarily accommodate up to 300 adult male asylum seekers at Cameron Barracks, Inverness.   It follows an email on Monday from Alex Norris MP, Minister for Border Security and Asylum, to Council Leader, Raymond Bremner, which failed to answer questions raised by the Council or address community concerns.  
27/11/2025
SSEN Transmission becomes first signatory to Highland Social Value Charter
SSEN Transmission has become the first company to sign up to the Highland Social Value Charter (HSVC), marking a significant milestone in delivering long-term socio-economic benefits for communities across the Highlands.   Investment commitments from the company include funding for roads, new homes, jobs, and work for local contractors in addition to a local and regional fund for communities to apply to.  
25/11/2025
Wick - Aberdeen PSO - Update issued 24/11/2025
The Highland Council continues to work through the procurement process for the provision of the Wick Public Service Obligation for the Highland Council.   We have now entered the preferred bidder stage and have entered a standstill period.  
25/11/2025
Highland Council winter road condition and school closure report for 25 November 2025
Maps of the Council's gritting routes by priority and policy are available online at www.highland.gov.uk/gritting (external link) The information provided is a summary of reports from operational staff and is intended to give a general indication of typical conditions in each area at a point in time.  It is not intended to imply that any individual route is entirely snow and ice free and drivers must be aware that conditions can change rapidly and make their own assessment of conditions for travelling.  

 

0.0133