Education capital projects progress in Highland schools

14th November 2013

Progress was welcomed today by members of The Highland Council's Adult and Children's Service's Committee on a number of several major education capital projects.

Approval to bring forward the fourth and final phase of the redevelopment of Lochaber High School was given by members. The council anticipates that this will achieve:
· a considerable reduction in the capital expenditure required to complete the redevelopment;
· clear educational benefits with less disruption to the operation of the school; and
· completion of the redevelopment approximately two years ahead of programme.

Also in Lochaber, members were informed that tenders have been received for the three Fort William Primary Schools projects and the council anticipates that all three contracts will be awarded before the end of December 2013.

Members were informed of proposals for a new £1million annex to Bun-sgoil Ghàidhlig Inbhir Nis that would provide two nursery classrooms. The existing nursery classroom would be used as a primary classroom resulting in 10 classrooms in the main building. Projected increases in the school roll have also prompted the Authority to give consideration to providing additional primary classroom capacity and any related impact on social and dining space. Members agreed to a review of the options at the Bun-sgoil and that design work would commence subject to formal approval at the next meeting of the Committee.
Approval was also given to:
· upgrade emergency lighting and fire alarms at Mount Pleasant and Pennyland Primary Schools in Caithness at an estimated cost of £1.5 million; and
· to upgrade accommodation at St Clement’s and St Duthus Schools at the estimated costs of £1.2 million and £2 million respectively.

An extra £300,000 funding was approved by members for the £1.2 million works at Central Primary School in Inverness to provide new kitchen and dining facilities, two nursery classrooms and an expanded “Doorways” pupil support facility.

Recommendations to carry out £450,000 works in Summer 2014 on the Lochaber High School, Synthetic Turf Playing Field to upgrade the facility to a 3G surface were welcomed by members. This development will benefit the school and sports clubs in the area seeking appropriate training facilities throughout the year.

Wick High School and Primary Schools

The revised programme to construct the building to replace the existing Wick
High School, Pulteneytown Academy Primary School, South Primary School,
Wick Carnegie Public Library and Wick Swimming Pool, which will be known as
the Wick Community Campus, has been formally agreed with Hub North
Scotland Limited (HNSL) and Miller Construction UK (MCUK).

The key milestone dates are as follows:

• Stage 2 submission – 10/01/14
• Financial close and contract agreement - 07/02/14
• Construction start on site – 31/03/14
• Practical completion – 29/01/16
• Handover period – February to April 2016
• Completion of external works – August 2016

The construction work packages are currently being tendered in accordance with
the requirements of the Territory Partner Agreement (TPA) which includes a
significant proportion of the contracts being made available to local contractors.

The replacement school for Hillhead Primary School and North Primary School
remains on programme to open in August 2015. The Stage 1 submission has
been received and the Council’s project team and specialist advisers are
considering the detail. It is proposed that, subject to the Stage 1 submission
being within the Affordability Cap approved at the New Project Request stage
(when adjusted for indexation), approval to allow the project to progress to Stage
2 is delegated to the Directors of Education, Culture and Sport and Finance and
the Interim Director of Housing and Property Services. This approach will ensure
that there are no delays to the programme as a result of waiting for the
appropriate Committee approval for the Stage 1 submission. The evaluation of
the Stage 1 submission should be completed by mid-November 2013. The key
programme dates are as follows:

• Enabling works commence – 20/01/14
• Contract award - 17/03/14
• Construction starts – 14/04/14
• School handover – 12/06/15
• Completion of all external works – 26/02/16

Councillor Alasdair Christie, Chairman of the Adult and Children’s Services Committee welcomed the work that has been done to progress the education services capital projects, he said: “I am delighted that we are able to make progress and see these major capital investments taking place in the schools that needs them most. I am certain that they will bring major benefit to the quality of education that we provide and will help to future-proof the schools that we are investing in to make them fit-for-purpose.”

 

Related Businesses

 

Related Articles

Yesterday : Local Authority

 
Nature Restoration Fund Community Grants Programme opens for applications

Community groups, charities, public sector bodies and other eligible organisations across Highland are being encouraged to apply for funding through the 2026/27 Highland Nature Restoration Fund (NRF) Community Grants Programme, which opens for applications on Friday 14 August 2026.   Applications will be assessed on a rolling basis, with grants available from £2,000 to £25,000 for capital projects that help restore nature, safeguard wildlife and address biodiversity loss.  

7/8/2026 : Local Authority

Convener welcomes funding to support Cairngorms businesses

The Scottish Government has confirmed a £3 million fund to support businesses affected by the Cairngorms wildfire.   The funding package was announced today by the Cabinet Secretary for Economy and Tourism, Stephen Flynn, during a visit to Glenmore.  

6/8/2026 : Local Authority

Timetable for Ward 3 Wick and East Caithness By-Election confirmed

A Highland Council by-election is being held for Ward 3 Wick and East Caithness following the resignation of Willie Mackay.   The Notice of Election and timetable for this election will be published on the Council’s website on Friday 14 August 2026.  

5/8/2026 : Local Authority

Qualifications Scotland exam results for young people across Highland 2026

Yesterday 4 August 2026 we celebrate the success and achievements of all our young people as they receive their Qualifications Scotland (QS) results, previously known as SQA.  These results are an initial snapshot of attainment and achievement for the 2025/26 session.  

30/7/2026 : Local Authority

Highland Council Launches Community Transport Grant Funding for 2027–2030

Community groups and organisations across the Highlands are being invited to apply for funding through The Highland Council's Community Transport Grant Scheme.   The scheme supports community-led transport services that help people access healthcare, employment, education, shopping and social activities.  

30/7/2026 : Local Authority

Council leader welcomed Wick Air Service Funding for 2026/27

The Leader of The Highland Council has welcomed confirmation from Transport Scotland of almost £1.8 million funding to support Public Service Obligation (PSO) air services from Wick for the year ahead.   Following an open tender exercise, the Council has awarded the contract to Air Charter Scotland, which will continue to operate services between Wick and Aberdeen and introduce scheduled flights between Wick and Glasgow from 15 August 2026 to 14 August 2027.  

30/7/2026 : Local Authority

Businesses invited to help shape recovery response following Cairngorms wildfire

As the emergency response to the wildfire in the Cairngorms National Park continues, attention is now turning to economic recovery and supporting the businesses and people whose livelihoods have been impacted.   The Highland Council through Business Gateway Highland is working with Highlands and Islands Enterprise, the Scottish Government, the Cairngorms National Park Authority and the Cairngorms Business Partnership as part of a multi-agency business recovery group.  

23/7/2026 : Local Authority

England Cuts Business Rates for Hospitality – Will Scottish Businesses Be Left Behind?

The UK Government has announced a 20% cut in business rates for many hospitality businesses in England, offering welcome relief to pubs, restaurants, cafés, hotels and live music venues that have struggled with rising costs in recent years.   For thousands of businesses south of the Border, it could mean lower bills and a little more breathing space.  

16/7/2026 : Local Authority

Highland Small Grants Programme Reopens with Expanded Support for Community Organisations

The Highland Local Action Group (LAG) is re-opening the Highland Community-Led Local Development (CLLD) Small Grants Programme following a review of the remaining funding.   Community and voluntary organisations across rural Highland are being invited to apply for grants of up to £10,000.  

14/7/2026 : Local Authority

 
Do you want a say in the future development of Highland?

Share your ideas and help shape the places, spaces and communities of tomorrow.   The Highland Council is inviting people to share their ideas relating to the development or long-term land use in Highland.