Dounreay revises site closure plans

10th May 2014

Photograph of Dounreay revises site closure plans

Two years into its major contract to complete the clean-up and shutdown of Dounreay, the consortium in charge of Dounreay Site Restoration Ltd is now revising its programme of work to accommodate changes being made by the Nuclear Decommissioning Authority.

The NDA awarded a contract in April 2012 to Cavendish Dounreay Partnership. At the time the NDA was seeking comments on the credible options for the future of nuclear materials at Dounreay.

Subsequently the decision was taken to transfer the nuclear materials to Sellafield. This means funding is no longer required in the later years of the programme to build high-security stores. Instead, funding is required in the earlier years to meet the costs of packaging and transport of the fuel.

DSRL management are briefing staff this week on the work now underway to accommodate these changes in the clean-up programme within the funding available from the NDA.

"Removing the requirement to modernise the stores at Dounreay and replacing it with a programme to transfer the fuel to Sellafield starting this year, removes both the modernisation costs from the later years of the decommissioning programme and substantial security costs from long-term care and maintenance of the site,” said DSRL managing director Mark Rouse, “but it does require significant preparation and handling operations, and will add transport and associated security costs in the next few years of the decommissioning programme.

"In order to insert the removal of the fuel into the earlier years of the programme and release the several hundred million pounds needed to fund this, some other work that had been planned for this period needs to be moved out to later years.
“A new plan showing how the fuels removal programme integrates with the rest of the decommissioning work should be ready by the autumn 2014. DSRL expects no reduction in supply chain spend and will be looking to place substantial additional new packages of work into the supply chain over a longer period of time than the original contract award plan shows.

"In short, this is a 'spend to save' measure. Although the fuels consolidation and removal programme adds several hundred million pounds to the bill for Dounreay during its decommissioning phase, it will remove even more in security costs from its long term care and maintenance.”

Meanwhile, the NDA will look to utilise its portfolio management process, where efficiencies and savings made across its estate can be re-allocated to other projects where they represent value for money and progress the NDA's mission, to assist DSRL in the near term as it works through the longer term implications of accommodating this further scope.

Two years and 20% in, the contract to take the Dounreay site to an interim end state by 2025 saving well over £1bn is progressing well. All annual milestones have been met to date, significant progress has been made in hazard reduction projects, and construction of the first two new low level waste repository vaults has been completed.

 

Related Businesses

 

Related Articles

28/7/2026 : Other Public Services

Caithness at the Centre of Scotland’s Electricity Revolution: The Transformation Happening Around Us

Caithness at the Centre of Scotland’s Electricity Revolution: The Transformation Happening Around Us Look across Caithness today and it is easy to see individual electricity projects – a new substation here, a cable route there, construction work around Dounreay or Spittal.  But put them together and a much bigger picture emerges.  

28/7/2026 : Other Public Services

Orkney Link Reaches Major Milestone at Dounreay – What It Means for Caithness and Scotland’s Energy Future

A major piece of underground engineering at Dounreay has been completed, bringing the Orkney electricity link another step closer to reality and putting Caithness at the centre of a project designed to unlock hundreds of megawatts of renewable energy.   SSEN Transmission has announced the successful completion of horizontal directional drilling (HDD) at Dounreay, describing it as a major milestone in the construction of the Orkney Link.  

30/6/2026 : Other Public Services

 
Innovative robotics trialled to tackle nuclear waste challenges

Innovative robotic solutions being trialled at Nuclear Restoration Services (NRS) Oldbury site to tackle most challenging aspects of legacy waste management.   Oldbury nuclear decommissioning site is a trailblazer for robotics and other innovative approaches, with NRS deploying robotics trials in South Gloucestershire to tackle some of the most challenging aspects of legacy waste management, reducing risk to workers and improving efficiency.  

16/6/2026 : Other Public Services

 
NDA group employees recognised by His Majesty the King

Three NDA group employees awarded honours in the 2026 King’s Birthday Honours list.   Three NDA group employees have been awarded honours in the 2026 King’s Birthday Honours list, for services to the nuclear industry and the local community.  

4/6/2026 : Other Public Services

Wylfa Decommissioning But With Good Propects For Future Nuclear Dvelopments

Wylfa, located on Anglesey, North Wales, is a historic nuclear site that operated from 1971 to 2015, featuring the UK's largest and last Magnox reactors.   Known for its significant contribution to UK energy, it is currently undergoing decommissioning while being designated as a premier location for new, small modular reactor (SMR) technology.  

20/5/2026 : Other Public Services

 
Scottish nuclear site hails e-learning platform as great example of industry collaboration

The Engineering Construction Industry Training Board’s (ECITB) award-winning e-learning platform has been hailed as a great example of industry collaboration in action.   To mark Learning at Work Week 2026, NRS Dounreay has highlighted how the ECITB’s Learning Experience Platform (LXP) has become a “go-to training solution” for its 1,400 workers.  

15/5/2026 : Other Public Services

 
NRS socio-economic funding supports 129 UK community projects

Almost £2 million was invested by Nuclear Restoration Services (NRS) last year in socio-economic initiatives, supporting good causes in communities local to its 14 decommissioning sites.   The NRS socio-economic scheme provided £1,979,721 during 2025-26 to enhance the social and economic wellbeing of communities located near NRS sites.  

15/4/2026 : Other Public Services

Buried in the Sand: The Radioactive Legacy Washing Up on Britain's Shores

It sounds like something from a Cold War thriller, not a family day out: fragments of radioactive material, invisible to the naked eye, quietly lying in the sand.  Yet for decades, beaches near Dounreay and Sellafield have been the final resting place for exactly that.  

14/3/2026 : Other Public Services

 
Why Repaint a Building Marked for Demolition? The Practical Logic Behind the Dounreay Dome's Fresh Coat

At first glance, the decision to repaint the iconic Dounreay dome as it is a structure already scheduled for demolition seems baffling.  Why spend money maintaining a building that will soon be torn down? Why refresh the exterior of a landmark whose days are numbered? The answer is far more practical than it appears.  

11/3/2026 : Advisory / Counseling Services

 
Nuclear project academy goes national

The Nuclear Decommissioning Authority (NDA) is launching a UK‑wide training programme to support the development of project professionals across the nuclear sector.   The One NDA Project Academy is an expansion of a programme initially launched at Sellafield in 2016.