Caithness And North Sutherland Regeneration Partnership - Update

17th November 2017

Week Commencing 13 November 2017

Energy & business services:

A reminder that SeaCat Services, the operators of the crew transfer vessels that will support both construction and operations work for the Beatrice Offshore Windfarm (BOWL) project, will be running a recruitment event in Wick next week for those interested in working on the vessels. SeaCat are seeking suitably qualified candidates for roles such as Master, Mate and Deckhand, and will be hosting a drop-in session at Wick Job Centre, Girnigoe Street, Wick from 9am til 12pm on Thursday 23rd November. To find out more about the roles, and other information, please see http://www.seacatservices.co.uk/wick/

It's good to see the progress at AGM Batteries in Thurso reflected in its current drive to recruit additional staff. http://caithness-business.co.uk/article/7848 As I have previously mentioned here, the company has been at the forefront of recent developments in the UK regarding battery cell technology, particularly in the automotive industry, with AGM leading a consortium of companies last year awarded funding for research into the next generation of battery technology. http://www.bbc.co.uk/news/uk-scotland-scotland-business-35643358



Enabling Activities:

I attended a meeting in Thurso this week of the large number of local sports clubs who came together back in 2014/15 to develop the Thurso Sports Hub concept Representatives from Sports Scotland, HighLife Highland also attended, and heard about the very clear need for such facilities in the area. Discussions with local, regional and national bodies have been taking place since 2014 to move forward proposals to develop a facility on Viewfirth field in Thurso, on land currently owned by CNSRP partner the NDA. The project was part of the CNSRP 2014-17 Programme, and although it does not feature on the 2017-2020 Programme, I have offered to bring together potential funding bodies to look at a way forward for the project.



Communications:

As part of an ongoing process of helping communicate progress with the delivery of aspects of our economic transition programme CNSRP's partners work together to generate news stories for local, regional and national media. I also speak on a regular basis to individuals and organisations across the area to update on progress. This week:

The CNSRP Delivery Group continues to work together to help progress the main projects on the CNSRP Programme. This week the group met and discussed progress with projects, as well as discussing and agreeing how projects are assessed and potentially prioritised for active support from partners. This should also allow the current discussions on the remaining opportunity in our programme (Oil & Gas West of Shetland) to be taken forward, agreed, fully scoped and planned.

I'm pleased to have the newly redesigned CNSRP website going live today (Friday) - with the kind support of DSRL and the Developing the Young Workforce programme Navertech have designed a very sleek, modern-looking site, and as part of our continuing work to engage with young people in particular the site now features a developing section titled "The Economy Challenge", where you can manually raise and lower projections for future jobs potential in the key CNSRP priority areas. The Challenge pages http://jobtool.cnsrp.org/ will also provide a link on into CNSRP partner Skills Development Scotland's My World of Work website, where visitors can get more information on some of the job types that might relate to these future opportunities. We will continue to grow this part of the site, working with DYW and SDS along with other partners.

NHS Highland has this week announced a welcome funding increase for ambulance provision in Caithness, which has been the subject of much concern. http://www.nhshighland.scot.nhs.uk/News/Pages/InvestmentboostannouncedforAmbulanceServiceinCaithness.aspx

Dounreay Site Restoration Ltd (DSRL) this week applied to Highland Council for planning permission for what is being described as "phase three" of the decommissioning of the Dounreay site. The application covers a series of major decommissioning projects due to take place between 2018 and the anticipated "interim end state" date for the site (currently estimated to be reached between 2030 and 2033). We have been working with DSRL to understand the expected staffing profile for DSRL between now and interim end state, and are currently working with DSRL to understand the anticipated supply chain implications for these major projects, which will see significant changes to the Dounreay skyline as buildings are taken down. For more information on the application see https://dounreay.com/2017/11/phase-three-planning-application-submitted/



This and my previous updates are also available to view on the Partnership's Blog on our newly-redesigned CNSRP website at



Eann Sinclair

Programme Manager

Caithness & North Sutherland Regeneration Partnership

Tel: 01847 805211

Mob: 07717 694055

Mail: eann.sinclair@hient.co.uk

Web: www.cnsrp.org.uk

Twitter: @eanncnsrp

Instagram: eanncnsrp

 

Related Businesses

 

Related Articles

Caithness And North Sutherland Regeneration Partnership - Update
Weeks commencing 17th September- 1st October 2018.   Energy & Business Services: CNSRP partner Highlands and Islands Enterprise, in association with the Offshore Renewable Energy Catapult and Scottish Government, has launched a programme called "Fit For Offshore Renewables (F4OR)." This is a service to help the UK supply chain get ready to bid for work in the offshore renewable energy sector.  
HIE Leadership Changes In The North As Spaceport Plans Get UnderwayThumbnail for article : HIE Leadership Changes In The North As Spaceport Plans Get Underway
Highlands and Islands Enterprise (HIE) has made leadership changes in Caithness and Sutherland, following the recent announcement of plans to create a spaceport near Tongue.   Roy Kirk has moved from his role as area manager to become project director for the new spaceport, where he will lead HIE's plans to develop the new satellite launch facility.  
Caithness And North Sutherland Regeneration Partnership - Update
WeekCommencing 20th August 2018 Energy & Business Services: Good to see another Beatrice milestone being reached this week, with the news that all of the inter-array cabling for the development has now been completed.  With the crew transfer vessels based in Wick now able to use the new pontoon berths at the harbour the project is reaching the critical phase where construction work and operations work are both moving ahead quickly.  
Caithness And North Sutherland Regeneration Partnership - Update
19 August 2018 Energy & Business Services: It was good to meet this week with Mike Muir of M2 Procurement & Commercial Services.  Mike has extensive experience in procurement and commercial services, particularly in the nuclear sector, and I was delighted to hear that M2PCS has recently been awarded a contract to help develop the "Open4Business" portal that SSE has used to advertise many of its supply chain contracts.  
13/8/2018
Caithness And North Sutherland Regeneration Partnership - Report to Council
On Thursday 16th August 2018 councillors on the Environment, Development and Infrastructure committee will discuss the update from Caithness and North Sutherland Regeneration Partnership which is reproduced below.   3.  
Caithness And North Sutherland Regeneration Partnership - Update
Week Commencing 23 July 2018 UK Vertical Launch Sutherland: Following last week's major announcements concerning the vertical satellite launch facility proposed for North Sutherland, it is good to see interest and comment continue to appear in the press.  I was particularly delighted to see the pieces in this week's local press with Caithness Chamber's Chief Executive Trudy Morris highlighting the work that has been put in from a number of CNSRP partners in attracting the opportunity to the north.  
Caithness And North Sutherland Regeneration Partnership - Update
Week Commencing 16 July 2018 UK Vertical Launch Sutherland: Around three years ago, Roy Kirk and colleagues from CNSRP partner Highlands and Islands Enterprise (HIE) began to investigate the potential economic benefits of developing a facility somewhere on the north coast from which to launch small scale satellites into polar and sun synchronous orbits.  The market for small scale satellite applications continues to grow, with Glasgow already a centre for space industry businesses.  
Caithness And North Sutherland Regeneration Partnership - Update
Week commencing 9th July 2018.   Energy & Business Services: * Yet another milestone was achieved for the Beatrice Offshore Windfarm (BOWL) project this week, as the final turbine foundation (number 86 of 86) was installed by contractor Seaway Heavy Lifting.  
Welcome for new Independent Chair of north partnership
Partners in the Caithness & North Sutherland Regeneration Partnership (CNSRP) have given a warm welcome to Ian Ross as he takes over the role of Independent Chair from Sir Anthony Cleaver.   Following a public recruitment campaign Ian Ross this week takes on a two-year contract as Independent Chair of CNSRP, as its partners continue to support the area's economy to transition away from dependence on nuclear decommissioning work.  
Caithness And North Sutherland Regeneration Partnership - Update
Week Commencing 17 June 2018 Energy & Business Services: Representatives of Sykes @ Home were in Caithness this week to begin a recruitment process for Homeworkers, beginning with a well-supported drop-in recruitment event in Thurso.  CNSRP partner Highlands and Islands.  

[Printer Friendly Version]